Fidelity & Deposit Co. v. Ables

1931 OK 745, 5 P.2d 740, 153 Okla. 278, 1931 Okla. LEXIS 459
CourtSupreme Court of Oklahoma
DecidedDecember 1, 1931
Docket21008
StatusPublished
Cited by2 cases

This text of 1931 OK 745 (Fidelity & Deposit Co. v. Ables) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Ables, 1931 OK 745, 5 P.2d 740, 153 Okla. 278, 1931 Okla. LEXIS 459 (Okla. 1931).

Opinion

HEFNER, J.

On the 16th day of August, 1926, the State Highway Commission entered into a contract with W. M. Short and Joe E. Abies, partners, doing business under the firm name of Short & Abies, to grade approximately four miles of highway on State Highway No. 9 in Caddo county, Okla. The contractors were to receive for this work the sum of $27,787.40, and such an additional amount as was mentioned in the contract. The total amount due under the contract upon completion of the work amounted to the sum of $27,160.83. The Fidelity & Deposit Company of Maryland executed a surety bond for the contractors whereby they guaranteed the faithful performance of the contract and payment of all bills for material and labor used in connection with the work. Before the surety company executed the bond it requested indemnity, and in response to this request John T. Abies, brother of Joe Abies, delivered to it the following letter:

*279 “Re Abies & Short, Contractors
“EAP No. 203 Sec. ‘B’ Caddo Co., Okla.
“ Gentlemen!:
“Reference this job awarded to Abies & Short, of Madill, Okla., and Joe E. Abies of this firm, my brother, and my verbal agreement with you that in case these contractors fail to complete this work, I would step in and complete.
“I understand that you want a letter of record on this agreement and to furnish the Fidelity & Deposit Company. Please accept this letter as an agreement, binding me to step ini and finish the job should these contractors for any reason fail to complete.
“My brother, Joe E. Abies, is an experienced road contractor and his partner, Mr. W. M. Short, is a former State Highway Inspector, and both know their business, anid they will go thru with this contract as agreed and as signed up for.
“Your etc.
“J. T. Abies.”

Upon receipt of this letter the bond was executed and shortly thereafter the contractors commenced work and continued until August 24, 1927, at which time they defaulted and abandoned the contract. The surety company, after ascertaining that the contract had been abandoned, communicated with John T. Abies and demanded that he complete the work in accordance with his letter of indemnity and, after some negotiations between the parties, a contract to this effect was entered into by them. The contract in part provides:

“And in consideration thereof, the Fidelity & Deposit Company of Maryland, party of the second part, covenants and agrees to pay to the party of the first part for the work performed and material furnished on the basis of the unit prices as provided in the said original contract between Messrs. Short & Abies and the State Highway Commission of the state of Oklahoma, and agrees to make said payments only and when payments are made to the party of the secon¡d part by the State Highway Commission, and agrees to pay to the party of the first part any retained percentage held back by the State Highway Commission covering work performed and material furnished by the party of the first part when and as paid to the party of the second part by the State Highway Commission; and the party of the second part hereby covenants and agrees to indemnify the party of the first part against any penalties which may heretofore have accrued under the said contract or which may hereafter accrue as a result of failure of completion of project within the time specified in the original contract, or which may hereafter accrue up to the time fixed in this agreement for the completion of the project, but not for any penalties which may accrue by reason of failure of party of the first part to complete the contract within the time fixed in this agreement.”

The work was thereafter completed by John. T. Abies and, according to the final estimate of the engineer, there was due under the contract a balance in the sum of $5,675.89. This amount, less $1,100, which was claimed by the State Highway Commission as a penalty under the contract because of a delay in completing the work, was paid to the surety company. John T. Abies contended that the entire amount paid the surety company was due him under his contract with that company. The surety company contended that $700 of the penalty charged against it was properly chargeable to Abies, and further contended that there was included in the amount paid upon completion of the work the sum of $2,387.22 retained percentage held by the Highway Commission on work performed by the original ■contractors, and also contended that there was included the sum of $768.50, earned by the original contractors between the date of the last estimate and the date they abandoned the contract. That Abies had only earned in completing the work the sum of $2,520.70, and that, deducting from this sum the sum of $700, the amount of penalty chargeable against him, it owed him a balance only of $1,820.07, which amount it alleged it was ready and willing to pay. The surety company contended that under the terms of the contract between it and John T. Abies, Abies was not entitled to the retained percentage on the work done by the original contractors. Abies contended that the following phrase in the contract relative to retained percentage : “covering work performed and material furnished by the party ;of the first pai*t,” was inserted by mutual mistake of the parties and that he was entitled to this retained percentage. The parties to the conr tract were unable'to adjust their differences and John T. Abies, as plaintiff, brought this action against the surety company to reform the contract and to recover the sum of $5,675.89. The trial was to the court and resulted in a judgment in favor of plaintiff reforming the contract and for the entire amount claimed.

Defendant first contends that the evidence is insufficient to authorize a reformation of the contract. On this question the evidence on behalf of plaintiff establishes, in substance, the following facts: At the time plaintiff gave the lfetter of indemnity to the defendant it was agreed between him and Ben G. Hunter, defendant’s agent, that in *280 the event of default on the part of the contractors and he was compelled to complete the work, he was to-be paid all money due the contractors at the time of default, including all retained percentage. After default oin the part of the original contractors there was some correspondence between Abies and the surety company relative to completion of the work by plaintiff and the terms under which it should be completed. In the latter part of September, 1927, Mr. Thomas, who was a lawyer and a special adjuster for defendant and working in the office of Lloyd J. Mullen, general attorney for defendant, called on plaintiff at Madill, Okla., for the -purpose of reaching an agreement with plaintiff under which the work could be completed. Some time thereafter a contract was prepared by Mr. Mullen and Mr. Thomas and presented -to plaintiff at Madill for hi-s signature. Plaintiff did not at that time sigjn the contract, but did s'o several days later at the office of Mr. Mullen in Oklahoma (Sty. Plaintiff testified that it was agreed between him and Thomas that, as a part consideration for completing the work, he was to receive all money then due the original contractors, including the retained percentage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn Mut. Life Ins. v. Miller
32 F. Supp. 206 (W.D. Missouri, 1940)
Whittaker v. White
1934 OK 587 (Supreme Court of Oklahoma, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
1931 OK 745, 5 P.2d 740, 153 Okla. 278, 1931 Okla. LEXIS 459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-ables-okla-1931.