Fidelity & Deposit Co. of Maryland v. City of Auburn

272 P. 34, 150 Wash. 114, 1928 Wash. LEXIS 944
CourtWashington Supreme Court
DecidedNovember 30, 1928
DocketNo. 21309. Department Two.
StatusPublished
Cited by7 cases

This text of 272 P. 34 (Fidelity & Deposit Co. of Maryland v. City of Auburn) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. of Maryland v. City of Auburn, 272 P. 34, 150 Wash. 114, 1928 Wash. LEXIS 944 (Wash. 1928).

Opinion

French, J.

In April 1927 the Dillon Concrete Company entered into a contract with the city of Auburn for the construction of a septic tank to be used by the city in connection with its sewer system. The contract was in the form usually used by cities, and provided that the contractor should pay for all materials purchased by him in connection with this work, and should pay the wages of all persons employed. It also *115 provided, “The city of Auburn may withhold any and all payments under this contract until the provisions of this section have been fully complied with. ’ ’ It provided also that, on the tenth day of the month following the issuance of the estimate by the engineer, the city would deliver warrants to the contractor in an amount equal to eighty-five per cent of the estimate, and provided for retaining the balance of fifteen per cent for a period of thirty days after the final completion of the work and its acceptance.

Appellant, Fidelity and Deposit Company of Maryland, furnished a bond for the contractor in the full amount of the contract price. At the time of the execution of the bond, the Dillon Concrete Company executed to the bonding company an indemnity agreement, in which it agreed

“. . . to assign, transfer and set over, and does or do hereby transfer, assign and set over to the company as collateral, to secure the obligations herein and any other indebtedness or liability of the undersigned to the company, such assignment to become effective as of the date of said contract bond, but only in event of any such abandonment, forfeiture or breach of contract, . . . (b) all his, its or their rights in, and growing in any manner out of, said contract or said bond or bonds; . . . (d) any and all percentages retained on account of said contract, and any and all sums that may be due under said contract at the time of such abandonment, forfeiture or breach or that thereafter may become due.”

The work progressed in due course until the early part of October, at which time the contractor, needing money, applied to the respondent First National Bank of Auburn for a loan, representing to the bank that there was due and unpaid on the contract, exclusive of the retained percentages, something like seven thousand dollars, no part of which had been pledged or *116 assigned. The president of the bank made inquiries of the city clerk and the city engineer as to the amounts due and as to whether there was any assignment thereof, and, being informed that there was an amount in excess of six thousand dollars still due the contractor, exclusive of the retained percentages, and that no part of it had been assigned, loaned the contractor fifty-seven hundred dollars, which money was all paid out by the contractor for materials and labor used on the job. As security for this loan the contractor executed to the bank an assignment of all money due or to become due under the contract, which assignment was duly filed with the city clerk and called to the attention of the city council, and record of the notice thereof was made in the minutes of the council meeting.

On the 28th day of October, claims of laborers and materialmen began to be filed in the office of the city clerk of the city of Auburn. In the meantime, however, the contractor had completed his contract, and the entire fund in controversy had accumulated. On the first day of November, appellant filed notice with the clerk of the city that there were outstanding and lienable claims in excess of seven thousand dollars, and requested that the city make no further payments to either the contractor or his assignee, and on the 23d day of November notified the city clerk of the assignment which had theretofore been made to it by the Dillon Concrete Company, and filed with the city clerk a copy of such assignment; and on December 6, presented the assignment to the city council. At this same meeting, held on the 6th day of December, there was submitted to the city council the last monthly estimate of the city engineer, which showed retained percentages in the hands of the city of $2,790.72, and a balance .of $3,808.15 due the contractor on his monthly estimate. The city council passed a resolu *117 tion directing the city clerk and the mayor to issue a warrant and deliver the same to respondent hank in the sum of $3,808.15. The Dillon Concrete Company being insolvent, the appellant commenced this action to enjoin the city from delivering the warrant to the First National Bank. The city answered, setting up the fact that it waived its right to retain any amount in excess of the retained percentages, and made payment to the First National Bank. The First National Bank of Auburn answered, setting up its claim to the warrant by virtue of its assignment and by virtue of the fact that the money advanced to the contractor had been used by it in completing this contract, and alleged that its assignment was in fact a prior assignment to that held by appellant, by reason of the equities involved.

The case was tried on an agreed statement of facts. From a judgment in favor of the respondents, the bonding company appeals.

Two questions are presented by appellant; first, that by the doctrine of subrogation the surety is entitled to all the rights of the city of Auburn.

Contrary to the rule in many states this court by an unbroken line of decisions has held adversely to appellant’s contention, and there is therefore no need to again or further discuss the question. Among other cases holding contrary to appellant’s view, see: Dowling v. Seattle, 22 Wash. 592, 61 Pac. 709; Maryland Casualty Co. v. Washington National Bank, 92 Wash. 497, 159 Pac. 689; National Surety Co. v. American Savings Bank & Trust Co., 101 Wash. 213, 172 Pac. 264.

The second question raised is that, as the appellant surety is the first assignee in point of time, by reason of the indemnity agreement, it is therefore entitled to. priority over the respondent bank. It must *118 be remembered that the assignment held by appellant is not absolute, but conditional, the provision therein contained being:

* Such assignment to become effective as of the date of said contract bond, but only in event of any such abandonment, forfeiture or breach of said contract, or the breach of any of said bonds or of any of the agreements herein contained.”

A breach having occurred, the indemnity agreement may, as between the bonding company and the contractor, relate back to the inception of the contract. But as between the bonding company and the bank a far different question arises. By the express provisions of the contract, the contractor was entitled to collect from the city all funds represented by monthly estimates, so long as the work was not in default. Eighty-five per cent of the price of the work was to be paid on these monthly estimates, and no limitation was placed on the right or power of the contractor to collect these payments and expend them. The bonding company had no control of any kind over these payments unless the contractor breached the contract, and could assert no claim until this contingency arose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Surety Corporation v. Fisher
317 S.W.2d 334 (Supreme Court of Missouri, 1958)
North Pacific Bank v. Pierce County
167 P.2d 454 (Washington Supreme Court, 1946)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Indemnity Insurance Co. of North America v. Nelson
22 P.2d 984 (Washington Supreme Court, 1933)
United States Fidelity & Guaranty Co. v. Armstrong
142 So. 576 (Supreme Court of Alabama, 1932)
Hall & Olswang v. Aetna Casualty & Surety Co.
296 P. 162 (Washington Supreme Court, 1931)
Bank of Dallas v. McCanless
154 S.E. 621 (Supreme Court of North Carolina, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
272 P. 34, 150 Wash. 114, 1928 Wash. LEXIS 944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-of-maryland-v-city-of-auburn-wash-1928.