Fern Hill Farm, Ltd, Work Plan

CourtVermont Superior Court
DecidedDecember 12, 2008
Docket121-06-07 Vtec
StatusPublished

This text of Fern Hill Farm, Ltd, Work Plan (Fern Hill Farm, Ltd, Work Plan) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fern Hill Farm, Ltd, Work Plan, (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

} In re Fern Hill Farm, Ltd., Work Plan } Docket No. 121-6-07 Vtec }

Decision on Motion for Summary Judgment Appellant Fern Hill Farm, Ltd., appealed from a determination of the Secretary of the Vermont Agency of Natural Resources (“ANR” or “Agency”) rejecting a work plan (“Work Plan”) submitted by Fern Hill Farm for the remediation of waste illegally disposed of at a farm dump. In July 2006, Fern Hill Farm submitted the Work Plan to ANR pursuant to this Court’s January 20, 2006 Decision and Order in Docket Number 129-8-03 Vtec (“January 20, 2006 Order”), which modified the Agency’s Administrative Order for the solid waste illegally buried on Fern Hill Farm. Fern Hill Farm was previously represented by John D. Hansen, Esq., and is now represented by John R. Ponsetto, Esq., and Heather Rider Hammond, Esq. The Agency has been represented by Gary S. Kessler, Esq. Fern Hill Farm has moved for summary judgment on all issues raised in its Statement of Questions, which generally asks whether ANR summarily denied the Work Plan without considering its merits, which Fern Hill Farm contends is in contravention of the Court’s directives, as announced in the January 20, 2006 Order. ANR opposes the pending summary judgment motion and asserts that the Work Plan was rejected because it failed to comply with ANR policy and the language from the 2006 Order.

Factual Background Rather then repeat the factual history surrounding the farm dump on Fern Hill Farm, we incorporate by reference the Findings already made by this Court, following a merits hearing, in the January 20, 2006 Order. See Agency Natural Res. v. Fern Hill Farm, Ltd., No. 129-8-03 Vtec (Vt. Envtl. Ct. Jan. 20, 2006) (Wright, J.).1 Against this background, we need only add the following facts, which we understand to be undisputed unless otherwise noted below:

1 The January 20, 2006 Order was amended on April 28, 2006 in response to a motion to reconsider or alter filed by ANR. See Agency Natural Res. v. Fern Hill Farm, Ltd., No. 129-8-03 Vtec (Vt. Envtl. Ct. April 28, 2006) (Wright, J.). However, the revised decision did not implicate the Work Plan, but rather clarified a penalty provision unrelated to this appeal.

1 1. On July 13, 2006, in response to the January 20, 2006 Order, Fern Hill Farm submitted its Work Plan to the ANR Waste Management Division. The Work Plan was prepared by an engineering firm retained by Fern Hill Farm. The Work Plan provided a framework for investigating possible environmental contaminants that may be leaching from the farm dump site, via either ground or surface waters. 2. Because the pre- and post-1991 waste was buried in the same vertical column and was located along the same groundwater flow path, the Work Plan proposed to evaluate the entire body of buried solid waste as one risk element. The Work Plan proposed to install four monitoring wells at varying depths near the boundary of the farm dump and then to conduct groundwater sampling at the four wells. 3. The groundwater sampling plan had various parameters to detect a variety of possible contaminants, including heavy metals, volatile organic compounds, semi-volatile organic compounds, polycyclic aromatic hydrocarbons, and other contaminant indicators. Also, the Work Plan proposed to conduct a “Sensitive Receptor Survey” in order to evaluate any contamination based on the groundwater flow direction, nearby potable wells, the basements of nearby structures, and the nearby surface waters. 4. After the collection of data, the Work Plan proposed the submission of a comprehensive report describing the results of this preliminary evaluation and recommendations for appropriate follow-up steps. The Work Plan did not exclude the possibility that its operation may result in a requirement that some or all of the buried waste be removed and disposed of in an off-site certified waste disposal facility. 5. On October 2, 2006, the ANR Waste Management Division reviewed the proposed Work Plan and concluded that it “cannot approve the proposed work plan for clean-up since it does not propose any clean-up of illegally disposed solid waste.” Letter from Barb Schwendtner, Compliance Specialist, ANR Solid Waste Program, to Anthony Stout, Senior Planner, Heindel & Noyes, at 1 (Oct. 2, 2006). Ms. Schwendtner stated that “[w]aste—except for IWMEA2 eligible wastes such as concrete and brick—cannot remain in place without a solid waste certification (required by 10 V.S.A. § 6605(a)(1)). . . . The site does not meet the standards of the Solid Waste Management Rules required for approval of a discrete disposal facility.” Id. ANR then

2 Insignificant Waste Management Event Approval.

2 directed Fern Hill Farm to “submit a clean-up and disposal plan that complies with the Agency’s interpretation of the Judge’s [January 20, 2006 Order].” Id. 6. On October 31, 2006, Fern Hill Farm—through its consulting engineers—sent a letter to ANR, requesting reconsideration of the denial of the proposed Work Plan. Fern Hill Farm indicated that under its interpretation of the January 20, 2006 Order, “leaving waste in place may be an acceptable remedial action, based on proper scientific analysis, without the need to obtain a Solid Waste Certification.” Letter from Anthony Stout, Senior Planner, Heindel & Noyes, to P. Howard Flanders, Dir., Waste Mgmt. Div., ANR, at 1 (Oct. 31, 2006). 7. On December 22, 2006, in response to Fern Hill Farm’s request for reconsideration, ANR denied the request and reiterated its policy requiring all non-IWMEA eligible materials to be removed and disposed of at a certified disposal facility. 8. On January 17, 2007, Fern Hill Farm—through its consulting engineers—sent a letter to the Commissioner of the Department of Environmental Conservation (“DEC”) to serve as an informal appeal of the earlier decisions from the ANR Waste Management Division. The letter generally reiterated many of the same arguments that Fern Hill Farm posited previously. 9. On May 11, 2007, the DEC Deputy Commissioner responded to Fern Hill Farm’s letter by again rejecting its Work Plan, based on ANR policy. The Deputy Commissioner stated that “[t]he Solid Waste Program Compliance Procedure . . . requires that ‘[s]olid waste stored or disposed outside of a certified solid waste management facility shall be removed and disposed [of] at a certified facility, and evidence of disposal at an approved facility is required to be submitted.’” Letter from Justin Johnson, DEC Deputy Comm’r, to Anthony Stout, Senior Planner, Heindel & Noyes, at 1 (May 11, 2007). 10. Meanwhile, Fern Hill Farm had been working on completing the sensitive receptor investigation as described in the Work Plan. In March 2007, Fern Hill Farm’s consulting engineers presented their client with a report of the sensitive receptor investigation. The report described the methods used and data gathered on and around the farm dump and concluded that there were no current air quality or ground or surface water quality impacts from the farm dump.

Discussion Fern Hill Farm moved for summary judgment on all of the issues raised in its Statement of Questions, which generally asks whether ANR summarily denied the Work Plan without considering its merits, in contravention of the January 20, 2006 Order. The Agency opposed the

3 motion and asserted that the Work Plan was rejected because it failed to comply with ANR policy and the January 20, 2006 Order. In this de novo appeal, summary judgment under V.R.C.P. 56(c) is appropriate only “when there are no genuine issues of material fact and, viewing the evidence in a light most favorable to the non-moving party, the moving party is entitled to judgment as a matter of law.” In re Carter, 2004 VT 21, ¶ 6, 176 Vt. 322 (citing Sabia v. Neville, 165 Vt. 515, 523 (1996)). We review the pending motion in this light.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re T.C.
2007 VT 115 (Supreme Court of Vermont, 2007)
Trepanier v. Getting Organized, Inc.
583 A.2d 583 (Supreme Court of Vermont, 1990)
Sabia v. Neville
687 A.2d 469 (Supreme Court of Vermont, 1996)
Scott v. City of Newport
2004 VT 64 (Supreme Court of Vermont, 2004)
Agency of Natural Resources v. Towns
790 A.2d 450 (Supreme Court of Vermont, 2001)
In re Carter
2004 VT 21 (Supreme Court of Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Fern Hill Farm, Ltd, Work Plan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fern-hill-farm-ltd-work-plan-vtsuperct-2008.