Fenestra, Inc. v. Merle Patnode Co.

162 N.W.2d 23, 40 Wis. 2d 453, 1968 Wisc. LEXIS 1084
CourtWisconsin Supreme Court
DecidedOctober 29, 1968
Docket13
StatusPublished

This text of 162 N.W.2d 23 (Fenestra, Inc. v. Merle Patnode Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fenestra, Inc. v. Merle Patnode Co., 162 N.W.2d 23, 40 Wis. 2d 453, 1968 Wisc. LEXIS 1084 (Wis. 1968).

Opinion

Wilkie, J.

Two issues are presented on this appeal:

(1) Whether the findings of the lower court were against the great weight and clear preponderance of the evidence.

(2) Whether the parol-evidence rule required the exclusion of the letter of June 9,1966.

The contract involved is the purchase order of defendant-appellant to the plaintiff-respondent. Appellant contends that the trial court should have dismissed the complaint of the plaintiff because it did not comply with the above contract.

The purchase order reads, “Fenestra ‘D’ Panel as per plans and specifications Roof Decking.” Thus the plans *456 and specifications were sufficiently identified on the purchase order to incorporate them into that contract. The plans and specifications represent the contract between defendant-appellant (the general contractor), and the G. S. A.

The section of the specifications with which this case is concerned is as follows: Section 11, Steel Roof Deck, which provides, in part, that:

“11-1. General:
“a. New steel roof deck units shall match existing steel roof deck units used in present marquise as to manufacturer, size, gage and installation unless otherwise specified herein.
“11-2. Shop Drawings
“a. Shop drawings, including erection layouts, shall be submitted to the Service for approval.”

Shop drawings are governed by subsection 1-20 of Section 1, General Conditions. It reads, in part, as follows:

“(f) The approval [by G. S. A.] of drawings and schedules will be general, but approval shall not be construed: (1) As permitting any departure from the contract requirements; (2) as relieving the Contractor of the responsibility for any errors, including details, dimensions, materials, etc.; (3) as approving departures from full-size details furnished by the Contracting Officer, except as otherwise provided herein.”

The term “contractor” refers to the general contractor, the defendant-appellant. This is made clear by Section 1, General Conditions, under 1-1. Definitions, which defines “contractor”:

“(e) The term ‘Contractor’ as used in the specifications shall mean the individual, partnership, or corporation that agrees to provide all labor, material and services required in the contract.”

The general notes on the blueprints (also part of the contract) provide that:

*457 “1. Contractor shall verify all lines, dimensions, grades, and conditions at site before starting any part of work.
“2. All new work shall match existing sound similar work when new unless otherwise specified or noted.”

Appellant argues that since the plans and specifications are part of the contract, the plaintiff-respondent assumed the obligation of the defendant general contractor with regard to the work to be performed as to the roof decking. Appellant relies on Corpus Juris Secun-dum, 1 which states that:

“. . . Where the subcontractor undertakes to perform a portion of the contract work according to plans and specifications binding on the general contractor, such plans and specifications become a part of his contract, and he assumes the obligation of the general contractor in relation to the particular part of the work to be performed.
“The subcontractor, however, is not bound by any part of the specifications which is not applicable to his subcontract and the purposes thereof; nor is he bound by specifications furnished for the guidance of bidders for the original contract, but which are not found in a subcontractor’s specifications and contract, and not specifically referred to therein.”

Thus appellant submits that plaintiff assumed the obligation of the defendant to match the roof deck in question with existing roof deck and also, according to the general note on the blueprint, to verify all dimensions at the site before starting any work. The substance of appellant’s argument is that the plaintiff should have had measurements verified by on-site inspections. Assuming, without deciding, that appellant’s contentions are correct, did the plaintiff meet this obligation?

After Charles Ackley got the blueprints and specifications from defendant he constructed shop drawings from these blueprints. The blueprints clearly showed that the *458 length of the panel to be furnished was 17 feet plus the distance that the panel projected into the wall. The blueprints showed that the wall was eight inches thick and the panel appeared to go halfway into the wall. Therefore, Charles Ackley concluded that the total length of the panel should be 17 feet four inches as indicated in the shop drawings. Thereafter he sent six copies of the shop drawings to the defendant who sent them on to the G. S. A. for approval in accordance with the subsection on shop drawings, supra. (Approval of G. S. A. not binding as to dimensions.) However, in plaintiff’s letter to defendant at that time, plaintiff specifically asked that the defendant general contractor “verify the cut length of the panels and all dimensions shown on the drawings.”

Although the specifications and plans had not yet become a part of the contract between the parties by incorporation in the purchase order, they had been used and relied on by the plaintiff. Plaintiff obviously recognized that the dimensions on the shop drawings had to be verified — as required in the specifications and plans that subsequently became part of the contract. Mr. Ack-ley testified at the trial that it was not the general practice in the construction field for a material supplier to go to a jobsite at a considerable distance from his place of business.

In view of the distance involved, the amount of money involved in the purchase, and the custom in the trade, it was reasonable that the plaintiff-materialman wrote to the general contractor to verify the dimensions. It was reasonable for the plaintiff to conclude that the general contractor would have someone on the job who could make the on-site measurements. Also, it should be noted that the specifications and plans did not require any particular party to make the actual measurement, they only required that the measurement be made.

*459 John Skiffington, regional manager for the plaintiff, testified as to the practice in the trade with regard to on-site measurements:

“A. The general custom is to make a shop drawing and have the general contractor check them. It’s always been as far as I know.
“Q. All right. Now, what about is there any general custom with regard to a material supplier making measurements on site? A. If you were to attempt to make measurements on site, you would have to wait for the construction to be completed to that phase, and then it would be possible to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Air Power Equipment Corp. v. Telemark Co.
150 N.W.2d 457 (Wisconsin Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
162 N.W.2d 23, 40 Wis. 2d 453, 1968 Wisc. LEXIS 1084, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fenestra-inc-v-merle-patnode-co-wis-1968.