Feland v. Placid Oil Company

171 N.W.2d 829
CourtNorth Dakota Supreme Court
DecidedOctober 30, 1969
DocketCiv. 8548
StatusPublished
Cited by28 cases

This text of 171 N.W.2d 829 (Feland v. Placid Oil Company) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Feland v. Placid Oil Company, 171 N.W.2d 829 (N.D. 1969).

Opinion

TEIGEN, Chief Justice.

The question to be resolved in this case is: What is the effect of a shut-in for a period of nine months of a producing oil well under a clause in the lease, commonly referred to as a “thereafter” clause, which provides that after the primary term has expired the lease shall continue in effect “as long thereafter as oil, gas, casinghead gas, casinghead gasoline or any of them is produced from said leased premises, * * *»?

The oil well in question was shut in for the reason that the salt water disposal pit was filled and the operator claims it was not reasonable, under the circumstances of this case, to make other arrangements for salt water disposal during the shut-in period.

The well produced about seventy-six per cent salt water and twenty-four per cent oil. The salt water was separated from the oil at the well site and allowed to run into the salt water disposal pit. The well was completed on September 10, 1961, and was operated with only temporary shut-ins until August 1964 when it was shut in for a period of nine months because the salt water disposal pit had filled. Production was resumed in June of 1965 when the level of the water in the salt water disposal pit had lowered by the process of evaporation to a point where production could be resumed. The well was in production at the time of trial.

The lessors by this action seek a declaration of termination of the lease and a judgment quieting the title to the land. The trial court found for the lessors and the operator has appealed.

The record establishes the lessors had refused permission to dig another pit upon their land for the disposal of salt water and the evidence establishes it was not economically feasible for the operator to connect to a salt water disposal system located about one and one-half miles distant from the well.

The position taken by the lessors is that the shut-in for a period of nine months was not reasonable. They admit the existing salt water pit was filled and that additional salt water disposal facilities were necessary if production was to be continued. They did not argue the operator was required to convert to the salt water dis *832 posal systems located some distance away. The thrust of their argument is that the operator, in spite of the refusal of the lessors to give consent, should have prepared another salt water disposal pit upon the lessors’ land. They cite Bell v. Cardinal Drilling Co. (N.D.1957), 85 N.W.2d 246, in support of their argument. Bell is of no help here. In Bell the lessor was seeking damages for a breach of (an oil and gas lease) contract for the destruction of crops and damage to his land resulting from drilling operations. The lease provided the driller had the right to use so much of the land as was reasonably necessary in drilling a test well and the court found that there was no allegation in the complaint and no proof that the operator had used more land than was reasonably necessary for the purpose intended and reversed a jury verdict for damages.

We are concerned here with a producing well and not exploration. The lease in the instant case grants exclusive right to the lessee to use the described land for the purpose of:

“operating for and producing therefrom oil, gas, casinghead gas, casinghead gasoline, and laying pipelines, telephone and telegraph lines, and building tanks, powers, stations, gasoline plants, ponds, roadways and structures thereon to produce, save and take care of said products, and the exclusive right of injecting water, brine and other fluids into subsurface strata, and housing and boarding employees and any and all other rights and privileges necessary, incident to, or convenient for the economical operation alone, or conjointly with neighboring land, for the production, saving, and taking care of oil, gas, casinghead gas, cas-inghead gasoline and the injection of water, brine and other fluids into subsurface strata, * * *

The Industrial Commission of North Dakota, under the authority granted by Section 38-08-04(2) (e), N.D.C.C., promulgated the following rule relative to salt water disposal:

“All salt water liquids or brines produced with oil and natural gas shall be disposed of without pollution of fresh water supplies. Disposal shall be in accordance with an order of the Commission, after hearing, as prescribed in Rule 701.
“Pending the order of the Commission, salt water liquids or brines may be impounded in excavated earthen pits provided that the level of the liquid in the pits shall at no time be permitted to rise above the lowest point of the ground surface level. All pits shall have a continuous embankment surrounding them sufficiently above the level of the surface to prevent surface water from running into the pit. Such embankments shall not be used to impound salt water or brine.
“At no time shall salt water liquids or brines be allowed to flow over the surface of the land or into streams.
“Pits shall not be constructed within natural surface drainage channels and, before any salt water liquid or brine is placed in the pit, any pit which is bottomed in permeable materials, such as sand or gravel, shall be lined with an impermeable material.
“The Commission shall have the authority to condemn any pit which does not properly impound such water.”

It appears the salt water disposal pit conformed to the requirements of the rule and apparently was adequate for the purpose intended until August of 1964.

We find under the grant that the operator, as lessee, was entitled to construct an additional salt water disposal pit on the land if it was necessary, incident to or convenient for the economical operation for the production of oil from the land. The questions then arise: (1) Was this right and privilege abrogated by the lessors’ refusal, upon the operator’s oral request, to construct another salt water dis *833 posal pit upon the land; (2) If not, does the refusal of the lessors absolve the lessee, as operator, of its responsibility to the lessors to exercise reasonable diligence and good faith in restoring production within a reasonable period of time; (3) If we answer both questions in the negative, was the failure to construct another salt water disposal pit reasonable and in the exercise of good faith; and, finally, (4) Was nine months a reasonable time in which to resume production under the circumstances?

The request for permission to construct an additional salt water disposal pit, we believe, establishes a decision on the part of the operator-lessee that the construction of this pit was necessary, incident to or convenient for the economical continued operation of the well for the production of oil. The alternative apparently was to keep the well shut in until enough salt water evaporated from the existing pit for the resumption of production. No other plan is submitted and it is undisputed that it would not be economically feasible to connect to the disposal well located one and one-half miles away.

This is a case of first impression in this state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bang, et al. v. Continental Resources
2025 ND 131 (North Dakota Supreme Court, 2025)
N.D. Energy Services v. Lime Rock Resources III-A
2024 ND 159 (North Dakota Supreme Court, 2024)
N.D. Energy Services v. Lime Rock Resources III-A, et al.
2024 ND 159 (North Dakota Supreme Court, 2024)
Twin City Technical LLC v. Williams County
2019 ND 128 (North Dakota Supreme Court, 2019)
Krenz v. XTO Energy, Inc.
2017 ND 19 (North Dakota Supreme Court, 2017)
Horob v. Zavanna, LLC
2016 ND 168 (North Dakota Supreme Court, 2016)
Fleck v. Missouri River Royalty Corp.
2015 ND 287 (North Dakota Supreme Court, 2015)
Mosser v. Denbury Resources, Inc.
112 F. Supp. 3d 906 (D. North Dakota, 2015)
Kartch v. EOG Resources, Inc.
845 F. Supp. 2d 995 (D. North Dakota, 2012)
Buchholz v. BURLINGTON RESOURCES OIL AND GAS COMPANY LP
2008 ND 173 (North Dakota Supreme Court, 2008)
State v. Krogen
2008 ND 169 (North Dakota Supreme Court, 2008)
Greenfield v. Thill
521 N.W.2d 87 (North Dakota Supreme Court, 1994)
Colburn v. Parker & Parsley Development Co.
842 P.2d 321 (Court of Appeals of Kansas, 1992)
Smith v. Duncan
595 N.E.2d 645 (Appellate Court of Illinois, 1992)
Slaaten v. Amerada Hess Corp.
459 N.W.2d 765 (North Dakota Supreme Court, 1990)
Johnson v. Hamill
392 N.W.2d 55 (North Dakota Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.W.2d 829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/feland-v-placid-oil-company-nd-1969.