Feitler v. Springfield Enterprises, Inc.
This text of 981 N.E.2d 155 (Feitler v. Springfield Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
OPINION ON REHEARING
In our original opinion in this case, we concluded, inter alia, that the trial court erred in concluding that Appellee JM Woodworking could hold a mechanic’s lien against the property of Appellants. JM failed to issue a pre-lien notice, which we concluded it was required to do if it wished to hold a mechanic’s lien. JM now seeks rehearing, and we grant for the limited purpose of revising our previous disposition of this question. JM contends, and Appellants concede, that a pre-lien notice is required only if work is provided to someone “other than the owner or the owner’s legal representatives!)]” Indiana Code § 32-28-3-1®. Having already concluded that the undisputed designated evidence established that JM entered into a separate agreement with the Feitlers and that the Feitlers are “owners” within the meaning of the mechanic’s lien statute, we now conclude that JM was not required to issue a pre-lien notice in order to hold a mechanic’s lien, and therefore now affirm the trial court on this point. That said, we also deny Appellee J. Laurie’s rehearing [156]*156petition in full and reaffirm our original opinion in all other respects.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
981 N.E.2d 155, 2013 Ind. App. LEXIS 25, 2013 WL 244655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/feitler-v-springfield-enterprises-inc-indctapp-2013.