Feibus & Co. v. Godley Construction Co.

260 S.E.2d 665, 44 N.C. App. 133, 1979 N.C. App. LEXIS 3180
CourtCourt of Appeals of North Carolina
DecidedDecember 4, 1979
DocketNo. 7926SC233
StatusPublished
Cited by1 cases

This text of 260 S.E.2d 665 (Feibus & Co. v. Godley Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Feibus & Co. v. Godley Construction Co., 260 S.E.2d 665, 44 N.C. App. 133, 1979 N.C. App. LEXIS 3180 (N.C. Ct. App. 1979).

Opinion

HILL, Judge.

The record, together with the briefs, presents to this Court a lengthy set of documents for consideration. However, although three causes of action are alleged and eight questions presented for consideration, the conclusions of law follow well accepted principles.

The defendant moved for summary judgment under Rule 56, together with a motion to strike portions of plaintiff’s affidavits. The motion was denied by Judge Robert Kirby, who directed plaintiff’s counsel to reduce the denial to a written order and address it to his home in Cherryville for signature. The session of court was then adjourned on that day.

Defendants excepted to the executed order of Judge Kirby, contending that it was invalid because signed out of term and out of district without defendant’s consent.

Rule 6(c) of the North Carolina Rules of Civil Procedure clearly permits such acts to be done. Judge Kirby did not hear the motion out of term and district. He gave his decision in term and simply documented his decision by signing the order and mailing it to the clerk of court after the term had expired. Hence, the objection of the defendants is groundless.

Plaintiff’s evidence tended to show that on 29 June 1964, Robert T. Godley acting on behalf of Godley Construction Company, wrote a letter to the corporate predecessor of the plaintiff stating, among other things, that:

[136]*136Specialists handle all details — planning, site selection, design and specs, financing, and construction. This service frees the business owner from tedious details.

As a result of the letter, the plaintiff and defendant began negotiations for a warehouse. Two contracts were signed: one with the individual defendants for an exchange of real estate, and a second for construction of a building by the corporate defendant on the exchanged land.

Lionel Feibus, an officer of the plaintiff corporation, testified that he did not remember whether he became aware of the drain line traversing the property before or after the contracts were signed. However, he testified that plaintiff’s attorney wrote him a letter dated 2 March 1965 stating that:

[TJhere is a buried 60-inch concrete drain extending through the center of the property . . . and will lie under the contemplated building. We are advised by the surveyor that this pipe is buried 40 feet in the ground and would, therefore, not constitute any objection to the contemplated use of the property.

Feibus contacted F. O. Godley who advised him substantially as follows:

[D]on’t worry about it. Every city in the world is run with the same kind of culverts, and nothing happens. This [pipe] is very deep in the ground and concrete and there is nothing to be concerned about.

Subsequently, F. O. Godley told plaintiff’s agents the pipe was of reinforced concrete and 60 inches in diameter. On other occasions the pipe was represented to be 40 inches in diameter. One time it was stated that the pipe had been installed for three or four years, another time twelve years. It was represented that the property had never flooded; that the water had not been high enough where you could tell it; that very little water flowed through the pipe; that the soil was compacted, would not settle, and as good as virgin soil.

Surveys of the property showed the pipe traversed the property under the site of the proposed building; that the pipe was not 40 feet below the surface, but only 27 feet; and that the land [137]*137conveyed to plaintiff contained five acres and not seven (adjustment in construction cost of the building offset the shortage in acreage).

Plaintiff contends that he relied on the statements by Mr. F. O. Oodley and proceeded with the construction. Financing was arranged with Liberty Life Insurance Company which raised a question concerning the location of the drain line. A core drilling of the area revealed that the fill consisted of sand, mixed silt, and some organic material. Thereafter, the loan for permanent construction was closed with Liberty Life. The building was constructed over the drain line and could not be located elsewhere because of a railroad siding.

In June, 1975, a portion of the building’s floor collapsed, at which time it was discovered that the drain line consisted of a 36-inch and 48-inch metal corrugated pipe, rather than a 60-inch concrete pipe.

Plaintiff’s testimony showed that the metal pipe was improperly installed. No bedding had been provided, and the fill dirt on top of the pipe consisted of silt, sand, organic material, and some clay. The sections of the pipe were joined by belting, not by collars. As a result of the weight of the soil above the pipe and the manner in which the pipe was installed, the pipe flattened, creating cracks in the joints, and permitting the soil to ravel (erode) above the pipe and into it. Over the years the cavity above the pipe became increasingly larger. Finally, the floor of the building collapsed.

Plaintiff’s expert witness testified that the cave-in would not have been avoided by the use of concrete pipe instead of metal pipe. He testified, “It wouldn’t have made any difference, the critical thing was the way it was installed.”

The representations as to the character of the fill were alleged to be in three parts:

(1) that the pipe had been installed as few as three years or as many as twelve years earlier;
(2) that the fill was compacted; and
(3) that it was as good as virgin soil.

[138]*138Although the exact time that the pipe was installed is uncertain, this is not material. There was no evidence that the statement concerning the compaction of the soil was false. The third statement is obviously a statement of opinion.

There was other testimony concerning the case, all of which has been considered, but the foregoing gives us the basis for decision. We must decide if there was sufficient evidence of fraud to withstand the defendant’s motion for a directed verdict on the first cause of action. We hold that there was not.

While the broad outlines of fraud have been indicated by regarding it as including any cunning, deception, or artifice used, in violation of a legal or equitable duty, to circumvent, cheat, or deceive another, the forms it may assume and the means by which it may be practiced are as multifarious as human ingenuity can devise, and the courts consider it unwise or impossible to formulate an exact, definite and all inclusive definition thereof. 37 C.J.S. Fraud § 1, p. 204.

Various statements of the elements of actionable fraud have been made, the most comprehensive one including the making, falsity, and materiality of a representation, the speaker’s knowledge of its falsity or ignorance of its truth, his intent that it should be acted on by the person and in the manner reasonably contemplated, the hearer’s ignorance of its falsity, his rightful reliance on its truth, and his consequent and proximate injury. 37 C.J.S. Fraud § 3, p. 215.

Justice Adams in Electric Co. v. Morrison, 194 N.C. 316, 317, 139 S.E. 455 (1927), defined fraud as follows:

The essential elements of actionable fraud or deceit are the representation, its falsity, scienter, deception, and injury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feibus & Co., Inc. v. Godley Const. Co., Inc.
271 S.E.2d 385 (Supreme Court of North Carolina, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
260 S.E.2d 665, 44 N.C. App. 133, 1979 N.C. App. LEXIS 3180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/feibus-co-v-godley-construction-co-ncctapp-1979.