Fehr Construction Co. v. Postl System of Health Building

124 N.E. 315, 288 Ill. 634
CourtIllinois Supreme Court
DecidedJune 18, 1919
DocketNo. 12101
StatusPublished
Cited by23 cases

This text of 124 N.E. 315 (Fehr Construction Co. v. Postl System of Health Building) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fehr Construction Co. v. Postl System of Health Building, 124 N.E. 315, 288 Ill. 634 (Ill. 1919).

Opinion

Mr. Justice Duncan

delivered the opinion of the court:

Defendant in error the Fehr Construction Company, as contractor, filed its bill in the circuit court of Cook county on May 8, 1912, to enforce a claim for a mechanic’s lien against plaintiff in error, Chapin & Gore, a corporation, and the Postl System of Health Building, and their property known as Nos. 61-69 Fast Adams street. Thereafter leave was given by the court to the Harty Bros. & Harty Company, as a sub-contractor under the contract of the Fehr Construction Company, and to E. J. Pickett and A. G. Eelden, co-partners, James H. Roche, the Davidson Bros. Marble Company and Benjamin F. Hanson, as contractors, to hie intervening petitions to establish their claims for mechanics’ liens against said owners and their property. The Postl System of Health Building and the Central Trust Company, its trustee in bankruptcy, made default. Plaintiff in error filed its answer to the bill and the petitions. The causes were referred to the master in chancery, who made his report finding in favor of the lienors. Objections were filed by plaintiff in error to the master’s report and findings, which were overruled by the court, and exceptions were then filed and overruled and decrees were entered in accordance with the master’s report and for sale of the property. On appeal the Appellate Court for the First District affirmed the decrees in favor of the Davidson Bros. Marble Company and Benjamin F. Hanson, and those decrees are not pending in this court for review. The decrees in favor of the other defendants in error were all reversed by the Appellate Court and the causes were remanded, solely for the reason that in all the claims there were lienable and nonlienable items, the values of which were not disclosed either by the contracts or the record evidence. Thereafter the causes were re-docketed in the lower court and referred to the master in chancery, and he heard and reported the evidence as to the reasonable and customary value of the non-lienable items in the several contracts, and the court entered its decrees for liens in favor of the defendants in error for the other items held to be lienable. On the second appeal to the Appellate Court that court entered its order affirming the decrees. The causes are brought to this court for review on a petition for certiorari.

The first decision of the Appellate Court is reported as Fehr Construction Co. v. Postl System of Health Building, 189 Ill. App. 519, to which reference is made for a more complete statement of the facts and holdings of that court.

•The court’s decree in favor of the Fehr Construction Company is for $743.95 and interest from March 22, 1912, to the date of the decree, July 8, 1916, of which principal sum the Harty Bros. & Harty Company, as sub-contractor, is decreed $346.05 and interest. The decree in favor of E. J. Pickett and A. G. Felden is for the sum of $240 and interest for the same. These contracts were entered into with Chapin & Gore’s lessee, the Postl System of Health Building, the former being for the material and the construction of office partitions from floor to ceiling on the seventh floor of said building, with doors and lockers for the same, side partition to be tiled in part and plastered in part with two coats of plaster, and also for the material and the construction of twenty-three, lockers and partitions seven feet high, including birch doors for lockers and locks, and an oak railing with two gates, all according to certain plans. The total contract price for said work and materials was for one lump sum, $989, without specifying the price of any part of the work or material. There were extras amounting to $204.95, itemized as follows:

Picture moulding, top of lockers........................ $4.50
Rack for letter file.................................... 16.00
Furnishing and laying muslin.......................... 1.75
Replacing handles on filing cabinet, repairing doors...... 5.90
Two shelves, stenographer’s desk....................... 3.50
Oak shelf, visitor’s register............................ 4.00
Changing door and partition........................... 9.50
Cutting and fitting around columns..................... 6.50
Shelves in lockers........................■............ 8.90
Difference in price of hardware....'.................... 22.75
Plastering, patching in tailor shop...................... 1.80
Shelving in buffet kitchen............................. 6.55
Installing hooks.....................................■. 12.00
Installing keyboard .................................. 2.50
Boarding up around urinal............................ 2.50
Putting three shelves in locker No. 2................... 1.00
For contract completed......°____.,...................... 989.00
Total.................................... $1,098.65

There was a general payment made on this contract of $350 by the Postl System of Health Building. The contract of Pickett & Felden was for furnishing the material ‘ and painting, enameling, varnishing and decorating the walls, partitions, woodwork, lockers, etc., on said floor, and was for one lump sum, $365, including extras, $40, and no price was specified for any individual part of the work or materials.

The basis of the claim of the contractors and the subcontractor for liens against plaintiff in error and its property is the charge that the plaintiff in error authorized or knowingly permitted its lessee to contract for or to make said improvements, and that they are permanent fixtures.

The court heard evidence as to the value of the work and materials employed in the construction of the twenty-three lockers and of a number of the other items of work and material furnished by the Fehr Construction Company under its contract which the court found to be non-lienable and that the aggregate value thereof was less than the general payment on the contract of $350, and applied the payment first upon those items in order to give the contractor its mechanic’s lien for the other articles found to be lien-able, after deducting the remainder of the payment from the value thus found of the lienable articles. The court also found that Pickett & Felden were not entitled to a lien for a portion of the work and materials furnished by them under their contract, which finding included the work and materials employed in painting and varnishing the lockers, and it appears also to include other items that are not identified by the record or-by the briefs and arguments of counsel. The total value of such articles was found to be less than the general payment of $125, and these contractors were therefore given a lien for the other items found by the court to be lienable, for the total contract price less said payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Browning-Ferris, Inc. v. Rockford Enterprises, Inc.
642 A.2d 820 (Superior Court of Delaware, 1993)
Flader Plumbing & Heating Co. v. Callas
524 N.E.2d 1097 (Appellate Court of Illinois, 1988)
Kupferschmid, Inc. v. Rodeghero
488 N.E.2d 305 (Appellate Court of Illinois, 1986)
Crane Erectors & Riggers, Inc. v. La Salle National Bank
466 N.E.2d 397 (Appellate Court of Illinois, 1984)
V & v Cement Contractors, Inc. v. La Salle National Bank
456 N.E.2d 655 (Appellate Court of Illinois, 1983)
Protestant Hospital Builders Club v. Goedde
424 N.E.2d 1302 (Appellate Court of Illinois, 1981)
Wingler v. Niblack
374 N.E.2d 252 (Appellate Court of Illinois, 1978)
Miller v. Reed
302 N.E.2d 131 (Appellate Court of Illinois, 1973)
Wing v. Lederer
222 N.E.2d 535 (Appellate Court of Illinois, 1966)
Kruse Metals Manufacturing Co. v. Utility Trailer Manufacturing Co.
206 Cal. App. 2d 176 (California Court of Appeal, 1962)
Antosz v. Goss Motors, Inc.
39 N.E.2d 322 (Illinois Supreme Court, 1942)
Southern Cotton Oil Co. v. Lowery
163 So. 629 (Supreme Court of Alabama, 1935)
Bradley Supply Co. v. Ames
194 N.E. 272 (Illinois Supreme Court, 1934)
Johns-Manville Corp. v. La Tour D'Argent Corp.
277 Ill. App. 503 (Appellate Court of Illinois, 1934)
Westphal v. Berthold
273 Ill. App. 266 (Appellate Court of Illinois, 1934)
R. Barcroft & Sons Co. v. Cullen
20 P.2d 665 (California Supreme Court, 1933)
Missouri State Life Insurance v. Estate of Kohl
265 Ill. App. 428 (Appellate Court of Illinois, 1932)
McConnell v. Frost
45 S.W.2d 777 (Court of Appeals of Texas, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
124 N.E. 315, 288 Ill. 634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fehr-construction-co-v-postl-system-of-health-building-ill-1919.