Feeley Construction Permits

CourtVermont Superior Court
DecidedJune 16, 2010
Docket4-1-10 Vtec
StatusPublished

This text of Feeley Construction Permits (Feeley Construction Permits) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Feeley Construction Permits, (Vt. Ct. App. 2010).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Feeley Construction Permits } Nos. 19687 & 21006 } Docket Nos. 4-1-10 Vtec & 5-1-10 Vtec (Appeals of Doane) } }

Decision and Order on Motion for Summary Judgment to Dismiss as Untimely

In January of 2010, Appellants Frederick and Heike Doane (Appellants) filed the

above-captioned appeals from two concurrently issued decisions of the Development

Review Board (DRB) of the Town of Colchester, ruling that Appellants’ attempted

appeals of two zoning permits issued to Appellees Richard and Theresa Feeley

(Appellees) were untimely. In Docket No. 4-1-10, Appellants seek to appeal the DRB’s

decision regarding permit #19687, issued on August 15, 2005, which authorized

Appellees to construct a replacement shed, replacement set of stairs, and new decks on

their property. In Docket No. 5-1-10, Appellants seek to appeal the DRB’s decision

regarding permit #21006, issued on June 26, 2008, which authorized Appellees to

construct a second replacement deck and set of stairs on their property.

Appellants are represented by Robert T. Gaston, Esq.; Appellees are represented

by Matthew T. Daly, Esq.; and the Town is represented by Thomas G. Walsh, Esq.

Appellees have moved to dismiss the appeal as untimely, or in the alternative

have moved for summary judgment. Although Appellees initially moved to dismiss

under V.R.C.P. 12(b), which allows parties to move for judgment on the pleadings

alone, both Appellants and Appellees have submitted affidavits and other evidence for

the Court to consider. Therefore, as provided in V.R.C.P. 12(c), the present motion will

be treated only as one for summary judgment under V.R.C.P. 56, as “matters outside the 1 pleadings have been presented to and not excluded by the court.” V.R.C.P. 12(c); see

also, e.g., In re UVM Construction and Landscape Permit, No. 169-8-08 Vtec, slip op. at

1 (Vt. Envtl. Ct. Mar. 12, 2009) (Wright, J.). A grant of “summary judgment is

appropriate when, giving the benefit of all reasonable doubts and inferences to the

nonmoving party, there are no genuine issues of material fact and the moving party is

entitled to judgment as a matter of law.” Gade v. Chittenden Solid Waste Dist., 2009 VT

107, ¶ 7 (citing Mooney v. Town of Stowe, 2008 VT 19, ¶ 5, 183 Vt. 600 (mem.); V.R.C.P.

56(c)). The facts stated in this decision are undisputed unless otherwise noted.

Factual and Procedural Background

Appellees own a parcel of property located at 73 Irish Cove in Colchester, which

contains a seasonal dwelling or camp structure that Appellees use during the summer

months. The property is located on the shoreline of Lake Champlain in the Shoreland

zoning district. Access to the property is by a private, dead-end road marked “Irish

Cove,” which leads from the nearest public right-of-way, Marble Island Road.

Appellants currently own a parcel of property with the address of 1021 Marble

Island Road that is adjacent to Appellees’ parcel, also with frontage on the shoreline of

Lake Champlain. Access to Appellants’ property is directly from Marble Island Road.

Appellants previously owned a condominium located at 1067 Marble Island

Road, which they acquired in June of 2005. They were regularly present at the

condominium during its remodeling from June of 2005 through January of 2006.

During the summer of 2008, they were residing at the condominium at 1067 Marble

Island Road during the construction of their current residence at 1021 Marble Island

Road.

2 2005 Zoning Application & Permit

On August 11, 2005, Appellees submitted zoning permit application #19687 (the

2005 Application), which sought approval to do the following work on their property:

to replace an existing set of stairs leading from the road down to the camp building; to

replace an existing 6’ x 7’ shed with a new 8’ x 10’ shed adjacent to the stair landing; to

construct an 8’ x 10’ deck over the new shed; and to construct a new 10’ x 17’ deck

adjacent to the camp building down near the elevation of the lake. Appellees attached

five diagrams or drawings to the 2005 Application form: one diagram depicting the

existing layout of the property; two diagrams depicting plan views of the proposed

layout, setbacks, and construction; one drawing showing the west or lake side elevation

of the proposed new shed and stairs; and one drawing showing the south side elevation

of the whole property from the road down to the lake, including the new stairs, the new

shed, the new decks, and the existing camp building. Appellees’ signatures appear on

the 2005 Application below the statement that “[w]e certify that all information,

including attachments, in this application are complete, true and accurate.”

The Zoning Administrator approved the 2005 Application on August 15, 2005,

granting Appellees zoning permit #19687 (the 2005 Zoning Permit). The approval,

which is noted on the application form itself, also shows the following requirement in

the area on the form marked for “Development Review Board Stipulations”: “no further

encroachment toward lake.” No party suggests that the DRB in fact issued any decision

regarding the 2005 Zoning Permit.

Upon receiving the 2005 Zoning Permit on August 15, 2005, Appellees were

required by statute to post “a notice of permit . . . within view from the public right-of-

way most nearly adjacent to the subject property until the time for appeal . . . has

3 passed.” 24 V.S.A. § 4449(b).1 Appellants assert that Appellees either failed to post the

notice of permit at all, or failed to post notice within view from the public right-of-way

of Marble Island Road. Appellants’ Objection to Appellees’ Motion to Dismiss or for

Summary Judgment, at 4–6 (Mar. 4, 2010) [hereinafter Appellants’ Objection to

Appellees’ Motion].

The 2005 Zoning Permit stated that “[c]onstruction shall not commence before

8/30/05,” that is, fifteen days after the issuance of the permit. This fifteen-day period

represents the period during which interested persons could appeal the Zoning

Administrator’s action to the DRB, as provided in 24 V.S.A. § 4465(a).2 Interested

persons seeking to appeal the Zoning Administrator’s issuance of the 2005 Zoning

Permit therefore had from August 15, 2005, through August 30, 2005, to file a timely

appeal with the DRB; no such appeal was filed within the fifteen-day period.

After receiving the 2005 Zoning Permit, at some time prior to October 11, 2005,

Appellees completed the proposed work. At no time during construction did any party

seek to take a late appeal of the 2005 Zoning Permit to the DRB, nor did any party raise

the issue at that time that the posting of the notice of permit was deficient.

On October 11, 2005, the Zoning Administrator inspected the completed work

and issued a Certificate of Occupancy/Compliance to Appellees.3 No party appealed to

1 In addition, “[w]ithin three days following the issuance of a permit,” the Administrative Officer was required by statute to “[p]ost a copy of the permit in at least one public place in the municipality until the expiration of 15 days from the date of issuance of the permit.” Id. § 4449(b)(2). No party suggests that the Administrative Officer failed to properly post the 2005 Permit in accordance with 24 V.S.A. § 4449(b)(2). 2 See 24 V.S.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mullane v. Central Hanover Bank & Trust Co.
339 U.S. 306 (Supreme Court, 1950)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Memphis Light, Gas & Water Division v. Craft
436 U.S. 1 (Supreme Court, 1978)
Gade v. Chittenden Solid Waste District
2009 VT 107 (Supreme Court of Vermont, 2009)
In Re Charlotte Farm & Mills
779 A.2d 684 (Supreme Court of Vermont, 2001)
Town of Randolph v. Estate of White
693 A.2d 694 (Supreme Court of Vermont, 1997)
Nash v. Warren Zoning Board of Adjustment
569 A.2d 447 (Supreme Court of Vermont, 1989)
In Re Appeal of Hignite
2003 VT 111 (Supreme Court of Vermont, 2003)
Harvey v. Town of Waitsfield
401 A.2d 900 (Supreme Court of Vermont, 1979)
In Re Appeal of Sardi
751 A.2d 772 (Supreme Court of Vermont, 2000)
Town of Charlotte v. Richmond
609 A.2d 638 (Supreme Court of Vermont, 1992)
In Re Maple Tree Place
594 A.2d 404 (Supreme Court of Vermont, 1991)
In Re Appeal of Gulli
816 A.2d 485 (Supreme Court of Vermont, 2002)
Boutwell v. Town of Fair Haven
527 A.2d 225 (Supreme Court of Vermont, 1987)
Levy v. Town of St. Albans Zoning Board of Adjustment
564 A.2d 1361 (Supreme Court of Vermont, 1989)
In re Glen M.
575 A.2d 193 (Supreme Court of Vermont, 1990)
In re Taft Corners Associates
650 A.2d 520 (Supreme Court of Vermont, 1994)
City of South Burlington v. Department of Corrections
762 A.2d 1229 (Supreme Court of Vermont, 2000)
In re Appeal of Tekram Partners
2005 VT 92 (Supreme Court of Vermont, 2005)
Mooney v. Town of Stowe
2008 VT 19 (Supreme Court of Vermont, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Feeley Construction Permits, Counsel Stack Legal Research, https://law.counselstack.com/opinion/feeley-construction-permits-vtsuperct-2010.