Federal Terra Cotta Co. v. Potterton Bros.

172 A.D. 705, 159 N.Y.S. 121, 1916 N.Y. App. Div. LEXIS 6525

This text of 172 A.D. 705 (Federal Terra Cotta Co. v. Potterton Bros.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Terra Cotta Co. v. Potterton Bros., 172 A.D. 705, 159 N.Y.S. 121, 1916 N.Y. App. Div. LEXIS 6525 (N.Y. Ct. App. 1916).

Opinion

McLaughlin, J.:

Action to recover under a written contract $1,875 damages alleged to have been sustained by defendant’s failure to accept terra cotta manufactured for it by plaintiff. At the close of plaintiff’s case defendant moved for the dismissal of the complaint. The motion was denied. At the close of the whole case the plaintiff moved for the direction of a verdict, which was denied, and defendant then renewed its motion to dismiss the complaint, which was granted. Plaintiff duly excepted to these rulings and the exceptions were ordered to be heard in the first instance at the Appellate Division.

There is substantially no dispute as to the material facts involved. On April 15,1913, the parties entered into a written contract, dated April 11, 1913, by which the plaintiff agreed to manufacture certain terra, cotta according to plans and [707]*707specifications, and to deliver a portion thereof to the defendant within fifty-six days after receipt by plaintiff of its approved shop drawings, and the selection of the color or colors by defendant, and the balance thereof within eighty-four days after such receipt and selection. The defendant agreed to supply plaintiff with the original drawings from which the shop drawings were to he made, and also such further drawings and explanations as either party might consider necessary. These drawings and information were to he furnished on or before April sixteenth. The contract also provided that in case of strikes, accidents, or causes beyond the control of the plaintiff, the period of delay caused thereby should not be a part of the time allowed for delivery, but in such case plaintiff should complete the work within a reasonable time thereafter. The defendant agreed to accept the terra cotta and pay a specified price therefor. Within the time contemplated by the contract the defendant supplied the original drawings, and from them shop drawings were prepared by plaintiff and submitted to defendant, who approved and returned the same on April eighteenth. It is fairly to be inferred that the selection of the color had been made prior to that time, although the testimony is not very conclusive upon that point. But it is not asserted by plaintiff that the defendant failed to perform its duty in this respect. Under the. terms of the contract, therefore, plaintiff was obligated to deliver the first installment of terra cotta within fifty-six days from April eighteenth, viz., June thirteenth. Before plaintiff, however, could complete the requisite paodels and moulds and proceed with the actual manufacture, it was necessary for the defendant to select the kind of surface to be put on the terra cotta. This had not been done on April eighteenth, and in fact was not done until about April twenty-fifth. A fair construction of the contract, therefore, requires that this latter date rather than April eighteenth should be deemed the starting point of the fifty-six days within which delivery of the first installment was to be made. If this be dope, then the first delivery was due June twentieth.

The plaintiff urges that inasmuch as defendant did not approve and return the shop drawings until April eighteenth, [708]*708and did not inform, plaintiff of the kind of surface selected, it was thereby relieved of its obligation to make the first delivery within fifty-six days of either of those dates — its contention being in this respect that defendant was bound to perform these acts prior to April sixteenth, as a condition precedent to setting plaintiff’s time of performance running, and by reason of defendant’s delays, other work undertaken in the meantime by plaintiff took precedence over defendant’s order and the delay caused thereby is chargeable not to the plaintiff but to the defendant.

I am unable to appreciate the force of this contention. The fallacy of it, as it seems to me, lies in the assumption that plaintiff’s obligation to make the first delivery within fifty-six days was contingent upon defendant’s furnishing all information called for prior to April sixteenth. The contract contains no such provision. Under its terms the only significance of this date is that prior thereto defendant was to furnish such information as would enable plaintiff to prepare its shop drawings. The defendant did not agree to approve and return these drawings at any particular time. It merely agreed to supply the original drawings before April sixteenth, and there is no evidence that it did not do so. As to the selection of the surface, it is perfectly obvious that this was not a part of the information necessary for the preparation of the shop drawings, for they were made by plaintiff and returned, approved by defendant, at least a week before the surface was chosen.

But even if it be assumed that defendant was bound to furnish all information called for prior to April sixteenth, its failure to do so until April twenty-fifth did not excuse plaintiff’s delay or default in thereafter completing the contract within the specified time. Under the contract the plaintiff agreed to make delivery of the first installment of terra cotta, not within fifty-six days from April sixteenth, but within fifty-six days from the receipt of its approved shop drawings and other necessary information. It was not relieved from this obligation by the fact that it saw fit, before the drawings and necessary information were received, to take other work which prevented its performing its contract with the defendant. If it had desired to be relieved upon that ground, then such a pro[709]*709vision should have been inserted in the contract. It is quite obvious that plaintiff’s default was due solely to its failure to , prosecute the work with diligence after April twenty-fifth.

As already indicated, a fair construction of the contract required the plaintiff to deliver the first installment on'June twentieth. On June fourteenth plaintiff advised defendant, by letter, that it expected “ to start shipments ” about June twenty-eighth. On receipt of this letter, the defendant wrote the plaintiff, insisting that it make the shipments as required by the contract, and at the same time informed it that “We are under penalty for completion of this work and shall hold you responsible for any damage caused by your delay.” Plaintiff answered on June nineteenth, reiterating that the earliest delivery of the first shipment it could make would be on June twenty-eighth. On June twenty-third a partial strike occurred at plaintiff’s factory, which became general on the following day, and defendant was so advised by letter dated June twenty-fifth, in which notice was given that plaintiff would claim an extension of the time of shipments under the strike provision in the' contract. This letter was not received by defendant until June twenty-eighth, on which day it answered, calling attention to the fact that plaintiff had been in default for several days before the strike occurred. This letter, as well as the defendant’s letter of June sixteenth, clearly indicates that defendant intended to stand upon the strict terms of the contract, and there is nothing in either of them which supports the contention of the plaintiff that defendant waived performance on the part of the plaintiff. There is no evidence of a waiver by defendant of the time within which the terra cotta had to be delivered, unless it be found in the testimony of George A. Potterton, defendant’s treasurer, in which he stated that if the terra cotta had been received at any time prior to July first, it could have been used; or in the two letters written by defendant to plaintiff on July first and third respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wittwer v. . Hurwitz
110 N.E. 433 (New York Court of Appeals, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
172 A.D. 705, 159 N.Y.S. 121, 1916 N.Y. App. Div. LEXIS 6525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-terra-cotta-co-v-potterton-bros-nyappdiv-1916.