Federal Insurance Company and Brewery Works, Inc. v. Grunau Project Development, Inc.

721 N.W.2d 157, 295 Wis. 2d 840
CourtCourt of Appeals of Wisconsin
DecidedJune 6, 2006
Docket2005AP267
StatusPublished

This text of 721 N.W.2d 157 (Federal Insurance Company and Brewery Works, Inc. v. Grunau Project Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Insurance Company and Brewery Works, Inc. v. Grunau Project Development, Inc., 721 N.W.2d 157, 295 Wis. 2d 840 (Wis. Ct. App. 2006).

Opinion

Federal Insurance Company and The Brewery Works, Inc., Plaintiffs-Appellants,
v.
Grunau Project Development, Inc., SCS of Wisconsin, Arnold & O'Sheridan and Central States Construction Management, Inc., Defendants-Respondents.

No. 2005AP267.

Court of Appeals of Wisconsin, District I.

June 6, 2006.

Before Wedemeyer, P.J., Fine and Kessler, JJ.

¶1 WEDEMEYER, P.J.

Federal Insurance Company and The Brewery Works, Inc. appeal from judgments entered after the trial court granted summary judgment in favor of Grunau Project Development, Inc., SCS of Wisconsin, Arnold & O'Sheridan and Central States Construction Management, Inc. Federal and Brewery Works claim the trial court erred in granting summary judgment for the following reasons: (1) the trial court's determination that oral contracts did not exist was erroneous or at least presented an issue of material fact; (2) even if the sham affidavit rule applies to this case, other evidence creates an issue of material fact; (3) the trial court erred in concluding that Brewery Works accepted the terms of the proposed, but unsigned, standard industry written contract; (4) the economic loss doctrine does not apply because the contract was for services and/or the damage to other property exception applies; and (5) the trial court erred in ruling that Wisconsin does not recognize implied warranties in construction contracts. Because we resolve each contention in favor of upholding the judgments, we affirm.

BACKGROUND

¶2 Brewery Works owns most of Schlitz Park. Gary Grunau, who also owns Grunau Project Development, and Scott Sampson, who also owns T-3 (an architectural firm), also are partial owners of Schlitz Park. Brewery Works needed to completely renovate an old bottling house in Schlitz Park, which had most recently been used as commercial office space by Time Warner Cable. A new tenant, Fortis Health, was moving into the building.

¶3 Samuel Denny was the treasurer and assistant secretary of Brewery Works. Denny was also the person who negotiated and entered into contracts on behalf of Brewery Works. In early 2001, Denny hired T-3 to be the architect for the project. T-3, in turn, contracted with Arnold & O'Sheridan to perform structural engineering services for the renovation project. At the same time, Denny hired Grunau Project as the general contractor for the project and authorized it, without restriction, to hire subcontractors. Brewery Works had a long history of using Grunau Project as its construction manager for renovation and construction projects. Grunau Project contracted with SCS and Central States.

¶4 The principal contract governing the project, often called the "prime contract" was between Brewery Works and Grunau Project. It was an AIA A111-1997 Standard Form of Agreement between owner and contractor. This contract was dated June 1, 2001, and incorporated by reference the terms contained in an ancillary document titled AIA A201-1997 General Conditions of the Contract for Construction. The A201 required Brewery Works, as the owner, to obtain appropriate all-risk insurance for the project. Brewery Works complied with this provision by obtaining insurance from Federal. The contract contained the standard waiver of subrogation rights provision. The A201 stated that Brewery Works' sole recourse in the event of a covered loss was against its own insurance carrier. Grunau prepared and signed the contract and submitted it to Denny. Denny did not immediately sign the contract. It was Denny's apparent practice to allow work to occur without signing the contract. Consistent with this practice, the document involved here remained on his desk for weeks as the project progressed.

¶5 Grunau Project, in turn, contracted with SCS and Central States, among others, to perform renovation work. Each of these contracts contained a waiver of the subrogation clause, which was prevalent in the construction industry. The subcontractor contracts also referenced the "prime contract," stated that it was available for inspection, that Brewery Works had obtained "all-risk" insurance to cover the project and that the owner, contractor and subcontractors all agreed to waive any claims against each other for such covered losses.

¶6 Brewery Works also entered into a written contract with T-3, which was the American Institute of Architects Standard Form Agreement Between Owner and Architect. This contract was proposed by Brewery Works, modified by Denny with the assistance of Brewery Works' attorney, and delivered by messenger to T-3 on September 27, 2001, for execution. This contract also contained a waiver of subrogation clause, whereby the parties mutually agreed that they would not seek recourse from the other in the event of damage to the project. Although many revisions were made to this contract before finalization, the waiver of subrogation clause was never modified.[1]

¶7 Work commenced in May/June 2001, and was supposed to be completed by December 2001. During this time, Grunau Project submitted applications for payment on standard AIA form documents; Brewery Works made progress payments to Grunau Project for the work being performed on the project, as required by AIA A111, Article 12; Grunau Project supervised, directed and coordinated the work on the project as required by AIA A201, Article 3.3.1; and the parties submitted and approved change orders under the contract, specifically referencing the existence of the standard form agreement between Brewery Works and Grunau Project. Denny signed and authorized change orders for work done by Grunau Project and the subcontractors, which specifically referred to the existence of an agreement between Brewery Works and Grunau Project for the renovation.

¶8 In other words, the work on the project was proceeding exactly according to the standard industry contracts, with all parties acting as if the written AIA A111 contract governed the renovation, until September 29, 2001. It was on that date that a load-bearing wall was demolished which, in turn, caused a partial collapse of the building. The collapse resulted in $900,000 worth of damage. The claim for the damage was submitted to Brewery Works' "all-risk" insurer, Federal, who processed and paid the claim. During the adjustment of the claim, Federal asked Brewery Works to sign a statement to the effect that there never was an AIA contract between Brewery Works and Grunau Project. Denny signed a statement dated November 5, 2001, which in relevant part provided:

Although the negotiations had been initiated, at no time did I or, to the best of my knowledge, any authorized representative of The Brewery Works, Inc., execute a written agreement, or come to a meeting of the minds, with Grunau Project Development concerning the terms and conditions for the renovation and remodeling work to be performed at this location except that Grunau Project Development would perform and be paid for the work.
This statement in no way is meant as an indication that Grunau Project Development is not entitled to payment for services rendered in connection with the renovation and remodeling work in an equitable dollar amount.

¶9 This statement, however, was not immediately disclosed to the other parties to this lawsuit. Rather, work continued on the renovation project. In fact, four months after Denny signed the above-referenced statement, subcontractors were induced to sign a Contractor Change Order with Grunau Project, which constituted a compromise agreement where the subcontractor would accept certain "backcharges" assessed against it, in exchange for payment for "extras" it was entitled to receive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Bydalek Ex Rel. Bydalek v. Metropolitan Life Insurance
584 N.W.2d 164 (Court of Appeals of Wisconsin, 1998)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)
Chudnow Construction Corp. v. Commercial Discount Corp.
180 N.W.2d 697 (Wisconsin Supreme Court, 1970)
Green Spring Farms v. Kersten
401 N.W.2d 816 (Wisconsin Supreme Court, 1987)
Insurance Co. of North America v. Cease Electric Inc.
2004 WI 139 (Wisconsin Supreme Court, 2004)
Yahnke v. Carson
2000 WI 74 (Wisconsin Supreme Court, 2000)
Beers v. Atlas Assurance Co.
253 N.W. 584 (Wisconsin Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
721 N.W.2d 157, 295 Wis. 2d 840, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-insurance-company-and-brewery-works-inc-v--wisctapp-2006.