Federal Heating Co. v. City of Buffalo

182 A.D. 128, 170 N.Y.S. 515, 1918 N.Y. App. Div. LEXIS 5062
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 20, 1918
StatusPublished
Cited by3 cases

This text of 182 A.D. 128 (Federal Heating Co. v. City of Buffalo) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Heating Co. v. City of Buffalo, 182 A.D. 128, 170 N.Y.S. 515, 1918 N.Y. App. Div. LEXIS 5062 (N.Y. Ct. App. 1918).

Opinion

Lambert, J.:

This action seeks equitable adjustment of the financial relations of the many parties thereto, arising out of and in connection with the construction of children’s pavilions at the J. N. Adam Memorial Hospital located at Perrysburg, N. Y. In August, 1914, the city of Buffalo, the owner of such hospital, entered into a construction contract with Hager & George, Inc., for the erection and completion of such pavilions for the sum of $96,360.22. The defendant Charles A. Hager was the treasurer and' general manager of the contractor.

By January, 1915, the contractor had found it necessary to procure financial assistance pending payments by the city, and it then entered into general arrangements with the defendant Bank of North Collins to that end. The scheme adopted was for the contractor to file with the city comptroller assignments from time to time of moneys to become due to it from the city under the construction contract. In return therefor the city, in each instance, issued a certificate of the fact that such an assignment had been made and filed. This assignment was then taken to the Bank of North Collins and treated as a draft or order for the payment of money. The bank discounted such, advancing funds against it.

At the time of the commencement of such relations the defendant Charles A. Hager had in said bank a small [132]*132personal account. It seems to have been arranged that the proceeds of the certificates discounted as above should be passed to this account and used as a disbursing account of the moneys. This plan was followed. At the time of the commencement of such arrangements Hager deposited in this account from other sources than this contract approximately $3,000.

Again, in March, 1915, the contractor filed another assignment to the defendant bank for the sum of $7,000, receiving from the city comptroller the usual certificate, and delivered it to the bank. There was then passed to the Hager account, as against such certificates, the sum of $3,500, and the balance was advanced at subsequent dates and in. varying amounts down to and including April twenty-second.

On April 3, 1915, there remainded unexpended of the total contract for such construction upwards of $41,000, which, after deducting the $7,000 assignment held by the defendant bank, left a balance applicable to the completion of the contract of upwards of $34,000. And on said date the various liens of the plaintiffs aggregated $13,875.45.

On this date the contractor had become further financially involved, and in an effort to carry the work of construction to completion, to the end that those advancing money might not lose their advancements, the following arrangement was entered into.

The contractor executed to one John M. Hoen a general assignment of all moneys due and to become due upon such construction contract. The assignment designated Hoen as a trustee and authorized and directed him to receive and receipt for all treasury warrants issued by the city on account of the contract, and also to receive for the benefit of the creditors $6,500 to be paid out of the moneys received by the defendant bank under the $7,000 assignment above mentioned. At that time there had been advanced as against that assignment the sum of $3,500.

The assignment to Hoen provided in great detail for the disposition of the moneys so to be received by him. He was first directed that the $6,500 from the bank on account .of said $7,000 assignment should be by him applied in extinguishment of certain liens and payment to materialmen [133]*133who had not filed liens, all definitely therein identified. It was next provided that upwards of $15,000 of such moneys should be paid to certain parties, including the plaintiffs, who, coincidentally therewith, agreed to furnish further material to that amount for the completion of the construction, contract.

It was further provided that Hoen might pay upon the payroll of the contractor upon this job not to exceed $500 a month for each of three specified months, and that for two of such months he might also pay not to exceed $500 each for current material .bills, other than .those therein before provided for.

He was next to apply the balance of the moneys in extinguishment of the liens of the plaintiffs in the order of their priority. After the extinguishment of same he was next to pay upon material and labor creditors of the contractor pro rata, and, lastly, if any balance remained, it was to be turned over to Hager & George, Inc.

1 It will be observed that this trust agreement ratifies, rather vthan attacks, the relationship of the defendant bank to this . contract and the validity and propriety of the assignments .made by the city up to that time.

This formal and detailed trust agreement was acquiesced in by the plaintiffs in this action and was filed with the city comptroller. At about the same time, upon one of the usual blanks provided for such purpose, a short form of assignment , to Hoen as trustee was likewise made and filed. Both these assignments were evidently intended to cover the same situation, the one being in more detail than the other. :

- At about the time that these assignments were filed with the city comptroller and apparently in aid of the contemplated -.completion of the contract under Hoen’s financial guidance,, the plaintiffs all satisfied their liens of record. ,

But Hoen, as trustee, had progressed his work but a short' time when it again became essential to anticipate payments , to be made by the city, and hence to obtain discounts and financial advancements from some source. Such accommodation was requested of and granted by the bank and evidenced as follows. The contractor, Hager & George, Inc., again executed formal assignment, from time to time, to the bank [134]*134of specified sums out of moneys to become, due upon the construction contract. Upon such assignments, Hoen, as trustee, indorsed a consent and a waiver of his previous assignment. Upon the 'filing of such with the comptroller, the city again issued its certificates to the effect that formal assignment to the bank had been made, and again these certificates continued to be used as vouchers or drafts, and were accepted and discounted by the bank. Under this arrangement the bank accepted and discounted upwards of $12,000 of these certificates, accompanied by the express waiver and consent of Hoen as trustee. The defendant city has paid to the bank on assignment certificates $11,450 upon maturing payments under the construction contract.

As moneys were advanced by the bank upon the above plan, the same were passed to the credit of the Hager account, and were actually disbursed through that account. On June 21, 1915, the bank refused to accept a still further certificate for discount, whereupon Hoen avowed his purpose to prevent repayment to that bank of the $2,150 then unpaid upon certificates. To make good the threat, Hoen then filed with the comptroller of the city of Buffalo a renunciation and withdrawal of his account and waiver upon all assignments theretofore filed, charging fraud and bad faith on the part of the defendant bank. The city then ceased payments to the defendant bank.

In July, 1915, the contractors ceased work upon the construction contract. The city thereupon gave notice to the contractor, as provided in its contract, that unless performance of the contract was progressed, the city could take over the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Jacobs
304 F. Supp. 613 (S.D. New York, 1969)
In re the Estate of Gauthier
143 Misc. 788 (New York Surrogate's Court, 1932)
Merchants National Bank v. Long
113 Misc. 84 (New York Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
182 A.D. 128, 170 N.Y.S. 515, 1918 N.Y. App. Div. LEXIS 5062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-heating-co-v-city-of-buffalo-nyappdiv-1918.