Federal Contracting Co. v. Coal Creek Drainage & Levee District

166 Ill. App. 369, 1911 Ill. App. LEXIS 76
CourtAppellate Court of Illinois
DecidedDecember 13, 1911
StatusPublished
Cited by1 cases

This text of 166 Ill. App. 369 (Federal Contracting Co. v. Coal Creek Drainage & Levee District) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Contracting Co. v. Coal Creek Drainage & Levee District, 166 Ill. App. 369, 1911 Ill. App. LEXIS 76 (Ill. Ct. App. 1911).

Opinion

Per Curiam.

This is an action of assumpsit brought in the Circuit Court of Schuyler County by the Federal Contracting Company, a corporation, upon a written contract entered into between it and the Coal Creek Drainage and Levee District, defendant, by which plaintiff undertook to do certain work of excavation and construction for the defendant. A trial before the court without a jury resulted in a finding and judgment in favor of plaintiff for $6,351.31 and costs, to which finding and judgment defendant excepted and has appealed to this.court.

The events leading up to the execution of the contract in question were as follows: The defendant drainage district was organized in 1896 under the levee act, and embraces about 6,700 acres of land, 4,900 acres of which are owned, by George B. Christie and Jesse Lowe. Frank J. Trout, Thomas K. Condit, John Schultz and T. J. Hodgson were some of the other landowners in the district. Several attempts were made to protect the land in the district from the overflow waters of the Illinois Biver, and in 1898 the district contracted with Christie & Lowe to build a levee about the same and to construct, certain interior ditches, F. 'J. Trout acting as manager of the work. Again in 1900 the district let a contract to Christie & Lowe to build the “Bluff Ditch,” the purpose being to intercept the bluff waters and conduct them around the district to avoid the pumping thereof. The interior ditches soon began to fill up, as there was no current for their drainage except that created by pumping the water, and the Bluff Ditch proved wholly insufficient for the purpose intended, so that the bluff waters continued to come down over the district and flood the lands. In 1908, Mr. Trout, then sole commissioner, at the instance of Christie & Lowe, took steps to further improve the district, with a view to the successful reclamation of the lands. Jacob A. Harmon, a civil engineer of Peoria, Illinois, was called into conference and requested to submit plans for the excavation of the old ditches and .the construction of new ones, under some method which would insure success. Harmon submitted a new scheme by which a series of settling basins were to be built in connection with the Bluff Ditch to receive the water and all soil deposits in times of heavy rain fall, and thus make the ditch care for the water and prevent its filling by deposit. T. J. Schweer, J. H. Coleman and George Hanna were then appointed commissioners in conformity with a decision of the Supreme Court that landowners within the district could not make an assessment for the improvements. The new commissioners advertised for bids, and the contract- for the entire work was awarded to the Federal Contracting Company of Beardstown, Illinois, a corporation having three stockholders, of which, as shown by the evidence, F. J. Trout is the manager and principal owner and who did all the-work.

The contract called for the re-excavation and improvement of Bluff Ditch, the construction of settling basins or reservoirs and the erection of levees at certain places on the lower side of said ditch; also the re-excavation of a ditch known as the Coal Creek Main Ditch, and the construction of three other ditches known as the “West Lateral,” the “East Lateral” and “Branch A of the East Lateral.” The plaintiff was also required to clear the right of way.

The specifications divided the work into two sections, section 1 being the Bluff Ditch and involving the movement of approximately 156,500 cubic yards of earth; and section 2, the -other ditches, called the open ditches, involving the movement of approximately 259,600 cubic yards.

The declaration consists of four counts. The first count, after setting out the contract in full, avers that plaintiff proceeded to do the work according to the profiles and specifications, but was unable to finish the work, known as Bluff Ditch, by January 1, 1909, and the balance of the work by April 1, 1909, as provided by the contract; that it was unable to complete and finish the contract until October 17, 1909; that the delay was not the fault of plaintiff, but was caused wholly by defendant; that the causes of the delay were, (1) because plaintiff was ordered to construct the Bluff Ditch to the height of 20 7-10 feet for the distance of three-quarters of a mile instead of 13 2-10 feet, as originally planned and constructed; (2) because the location of the channel of the Bluff Ditch was changed for one mile or more, requiring more difficult and prolonged work and handling of much earth; and (3) because the commissioners wrongfully caused the water to be pumped from the main ditch of the district to so shallow a depth that the plaintiff could not proceed with the work of dredging; that on October 17, 1909, it had fully completed all the work it had contracted to do in substantial compliance with its said' contract and with the plans, profiles and specifications therefor; and that on that date and ever since'that time has been entitled to a certificate of the completion of said work done to be executed by the engineer and commissioners, as provided by the contract, but that just before the work was finished, to-wit, on October 14, 1909, it was notified in writing by defendant that Jacob A. Harmon, the engineer of the district, was no longer the engineer in charge; that later the commissioners refused to give plaintiff a certificate of completion or to make a final estimate of the amount due it, presenting as a reason for its refusal a letter of one C. W. Brown, who claimed to be the engineer of the district; that the removal of Harmon and the appointment of Brown was part of a wrongful and fraudulent design on the part of two of the commissioners of the district, to prevent the issuance of the certificate, which said Harmon was ready and willing to issue; that the sum of $33,633.18 has already been paid plaintiff, but that there is still due and unpaid to it the sum of $5,738.45.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
166 Ill. App. 369, 1911 Ill. App. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-contracting-co-v-coal-creek-drainage-levee-district-illappct-1911.