Fay v. Moore

104 A. 686, 261 Pa. 437, 1918 Pa. LEXIS 760
CourtSupreme Court of Pennsylvania
DecidedJune 3, 1918
DocketAppeal, No. 379
StatusPublished
Cited by4 cases

This text of 104 A. 686 (Fay v. Moore) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fay v. Moore, 104 A. 686, 261 Pa. 437, 1918 Pa. LEXIS 760 (Pa. 1918).

Opinion

Opinion by

Mr. Justice Frazer,

Plaintiff, a contractor, sues to recover from the owner a balance alleged to be due under a contract for the erection of a building. The defense is that plaintiff failed to complete the work in accordance with the specifications whereby defendant was obliged .to take possession of the building and finish it- at an expense beyond the contract price. Plaintiff having died while the action was pending, his wife was substituted on the record as administratrix of his estate. The case has been tried three times, the result of the last, trial being a verdict .and judgment- for plaintiff from which defendant appealed.

The first two assignments of error are to the refusal of the court below to give binding instructions and subsequently to enter judgment for defendant non obstante veredicto. The contract required payments to be made only upon the certificate of the architect. When the building was practically completed and a certificate for final payment requested, the architect notified plaintiff in writing that the work ivas not performed in accordance with the contract in certain specified particulars. Plaintiff contends the defects enumerated by the architect were rectified by him, while defendant avers such was not the case but, on the contrary, he was obliged to employ another contractor -to complete the work.

[441]*441The first objection is that corner beading was omitted. The specifications call for “wood corner beads on all exposed angles” but' failed to set forth the particular kind of beading to be used. Plaintiff’s son, who had charge of the construction work, testified beads were put on at exposed corners, and this does not seem to be denied, the contention being a different style of beading should have been supplied as appears in a subsequent letter from the architect, in which he states the owner “has instructed me to put on beads in accordance with his desire, although I have never seen that kind of bead which he desires, at the same time he states that nothing else [will] be accepted by him, so there is no other alternative, and therefore I am compelled to instruct you to make them different from what I would personally select.” In another. letter written a few days later, the architect says: “I am perfectly aware that the bead Mr.' Moore desires is impractical as well as impossible, but as Mr. Moore gave me no other alternative in the matter and the best I could do was to give his instructions verbatim to' you”; and in a third letter says he had again taken the matter up with the owner “and asked him to give me instructions for the regular old fashioned wood corner bead put on, which is the only thing that can be accomplished outside of the covered bead which you have at present and which Mr. Moore does not want.” Under these circumstances the jury were warranted ih finding the architect in condemning the bead used by plaintiff was not acting upon his-own impartial judgment as to the sufficiency of the work but at the dictation and to satisfy the whim of the owner.

Another objection is the window sashes were of chestnut instead of Avhite pine lumber as called for in the contract. With respect to this item, the testimony on behalf of plaintiff is to the effect the architect instructed him to use chestnut instead of pine, so as to conform to the interior finish of the house. The owner visited tlm work almost daily and with the architect made up lists [442]*442of matters to be attended to or corrected, among which appears a memorandum to the effect that the owner would consider the matter of using chestnut instead of white pine sash. While it is true the contract provides that no alterations should be made except on the written order of the architect, the parties had the right to waive the provision: Raff v. Isman, 235 Pa. 347; and this the verdict indicates they did. Furthermore, there is no attempt in this case to charge for extra work.

As to the various items of which complaint is made, the testimony on behalf of plaintiff is to the effect that portions of the work, the details of which were not mentioned in the specifications, were done under the direction of the architect, and that other variations and defects were remedied after complaint was received. The architect having persisted in refusing a certificate of completion, giving as an excuse for his action the owner’s dissatisfaction with the work, and the contractor continuing to claim a completion of the contract, the owner procured a bid and entered into a contract for the additional work on the house he deemed necessary to complete the contract according to specifications, paying therefor the sum of $819 and for other items the sum of $220, which amounts were deducted from the contract price, and the architect signed a certificate to the effect that, after deducting such items, a balance of $1,100 remained due the contractor.

While the testimony on behalf of plaintiff was contradicted by the architect and other witnesses for defendant, the case was necessarily for the jury to whom it was submitted by the trial judge with instructions to consider the decision of the architect conclusive, unless they found from the circumstances in the case, his decision was the result of collusion with the owner and not a fair and impartial one. The court also left to the jury to say whether the contractor faithfully, honestly and substantially complied with the provisions of his contract, and further charged, if they so found, and minor defects [443]*443or deficiencies existed, such defects would not prevent a recovery for the amount due under the contract, less a reasonable allowance for the cost of remedying,the imperfections.

The provision in the contract requiring the production of the certificate of the architect, showing completion of the work, is intended as a protection to the owner against unjust claims by the contractor and to see that the latter properly carries out his agreement, and in cases where the evidence establishes refusal of the architect to be. capricious, fraudulent or based 'on collusion with the owner, his withholding the certificate will not prevent the contractor from recovering the amount due him: Pittsburgh, Etc., Lumber Co. v. Sharp, 190 Pa. 256. There also being evidence in the case to support the conclusion of the jury that there was no wilful or intentional departure from the terms of the contract, the doctrine of substantial performance was applicable and was properly stated by the trial judge in accordance with the principles laid down in Morgan v; Gamble, 230 Pa. 165.

The remaining assignments of error present no cause, for reversal. The third is to the refusal of the court to strike out testimony. A witness for plaintiff who had charge of the work, in reply to the question “What did you do?” answered “I completed the work in accordance with the plans, specifications and contract, and the modifications by the architect.” This answer was a rather brief summary of what the witness did under the contract and by reason of its brevity the answer sounds like a legal conclusion rather than a statement of fact, yet the statement was directly responsive to the question and as the details of the work performed by the witness were given more fully in other parts of his testimony the discretion of the trial judge, in refusing to strike out the answer, is not an adequate cause for reversal: United States Telephone Co. v. Wenger, 55 Pa. 262.

The fourth assignment is to the refusal of the trial judge to strike out testimony to the effect that the change in the máterial used in window sashes was made upon

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. San Pedro
781 F. Supp. 761 (S.D. Florida, 1991)
Warner Co. v. North City Trust Co.
166 A. 230 (Supreme Court of Pennsylvania, 1933)
Evans, Inc. v. School District of Township of Darby
164 A. 826 (Superior Court of Pennsylvania, 1932)
Zimmerman v. Marymor
138 A. 824 (Supreme Court of Pennsylvania, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
104 A. 686, 261 Pa. 437, 1918 Pa. LEXIS 760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fay-v-moore-pa-1918.