Faulkner v. Dinobile, Wm 1996-188 (2000)

Superior Court of Rhode Island·Decided May 10, 2000·No. C.A. No. WM 1996-188·Published

Opinion

DECISION
The genesis of the instant lawsuit was a petition to enforce a mechanic's lien filed by William B. Faulkner against the respondents, Charlene and Joseph DiNobile. Petitioner alleged that Mr. and Mrs. DiNobile owed him $49,000 for services and materials expended with reference to the DiNobile's South Kingstown home. Mr. and Mrs. DiNobile not only deny the debt, but assert in a counterclaim that petitioner's work was defective; that they were fraudulently induced to contract with petitioner; and, that they were forced to spend large sums to rectify petitioner's substandard work. It must be noted that the Court has been to the house for a view — inside and out — with all parties and counsel present.

The parties entered into a construction agreement on June 22, 1995 obligating Mr. Faulkner to build a home for the DiNobiles according to the contractor's specifications (Exh. 11). The purchase price, to be paid in installments, was $149,600. Mr. Faulkner also provided a general specification sheet (Exh. 10) setting forth the types and amounts of materials and items to be utilized, and providing for certain allowances. Any variances from said specifications were to be placed in writing and agreed to by all parties.

Mr. Faulkner, a life-long South County resident, started building homes under his own name in 1985. Prior to that he had gained experience in carpentry, doing framing and remodeling.

Since 1985, he has constructed 26 to 30 homes usually in the range of 1500 to 2000 square feet. With reference to the DiNobile home, Mr. Faulkner had been approached by Art Boyce of ReMax South Shore Realty, who presented Mr. Faulkner with a sketch for a proposed structure and asked for a price. Mr. Boyce balked at the estimate of $250,000 and requested a revised estimate after changing certain specifications. Among the latter alterations were the elimination of a garage, the deletion of oak for flooring, the reduction of square footage and a change in the type of siding from wood to vinyl. Realtor Boyce expressed that the lowered price, $175,000 would still be too high for his clients. Eventually the price was reduced to $149,600 as reflected in the contract.

Per Paragraph 8 of the agreement Mr. Faulkner was to commence construction "as soon as notified by Owners to do so" and to "complete same within a period not to exceed 120 days." The building permit, applied for by Mr. DiNobile, was issued on July 21, 1995. The construction to be allowed was for a 24x30 two story dwelling with attached garage.

The DiNobile lot had been surveyed in April, 1995 by Jeffrey Balch, a registered land surveyor of Frisella Engineering. After the lot was "staked", however, the orientation of the proposed structure and the location of the forms looked "funny" to both Mr. Faulkner and Mr. DiNobile. The latter then telephoned Mr. Balch who then returned to the site on August 10, 1995 and testified that [his] "mistake was very obvious." A ten-foot error necessitated the restaking of the lot and the moving of concrete forms. The remedial work was performed on August 21, 1995, costing Mr. Faulkner, according to his testimony, twelve construction days. After construction commenced, Mr. Faulkner claims that Mr. DiNobile made requests for items which went beyond the contract specifications, costing the contractor time and money. These items included an intercom system, a wall heater in the bathroom, Fagan garage doors, extra windows, designer siding, Andersen sliders, plaster in the garage, underground utility lines, angling the third floor deck for south side view to the ocean, the addition of a rubber roof over the rolled roof. Mr. Faulkner cites the total cost of extras to be $8,565.

After the windows were installed, problems of leakage occurred. Although Mr. Faulkner attempted to remedy the situation and called in a factory representative, the "cure" was nor to the homeowner's satisfaction. This, and other problems, caused the DiNobiles to engage counsel to set forth their complaints and concerns about the project.

On November 25, 1995 Mr. Faulkner was notified by Attorney Foster in a letter (Exh. 29) that no final decision had been made as to whether to terminate Mr. Faulkner. By December 1, 1995, however, that decision was made and Mr. Faulkner was literally ordered off the property and instructed not to return. (Exh. 30).

Mr. Faulkner responded on December 15, 1995 (Exh. 31) requesting payment of $47,500, which when added to the DiNobile's payment of $75,600 would represent payment up to the third advance in the disbursement schedule. The third advance was due when the following had been installed: interior door frames, well (drilled and connected), wall and floor tile, floors, sheetrock, trim work and septic tank (connected).

The live testimony of Mr. Faulkner regarding "reasonable cost to complete" the project after December 1, 1995 coincides with Exhibit 32 and need not be repeated.

The respondents assert that at the point of termination of the house shell was constructed but the interior work had not commenced. The plumbing was roughed-in, the electrical system installed and the walls insulated and plastered. The alleged deficiencies in workmanship at the point of termination involve the slab, heating system, decks, insulation, shingles, and the propane gas line.

Respondent, Joseph L. DiNobile, Jr. of Lincoln, Rhode Island, testified that he and his wife, Laura, met petitioner through realtor Art Boyce in June of 1995. Mr. DiNobile was expecting to have a "turnkey" house completed by October. Essentially, Mr. and Mrs. DiNobile were to concern themselves with the selection of color schemes.

Free access — add to your briefcase to read the full text and ask questions with AI

Faulkner v. Dinobile, Wm 1996-188 (2000), (R.I. Ct. App. 2000).

Faulkner v. Dinobile, Wm 1996-188 (2000) (Faulkner v. Dinobile, Wm 1996-188 (2000)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.