Faulk & Coleman Construction Co. v. B. B. McCormick & Sons, Inc.

151 F. Supp. 206, 1957 U.S. Dist. LEXIS 3534
CourtDistrict Court, N.D. Florida
DecidedMay 2, 1957
DocketCiv. A. No. 577
StatusPublished
Cited by1 cases

This text of 151 F. Supp. 206 (Faulk & Coleman Construction Co. v. B. B. McCormick & Sons, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Faulk & Coleman Construction Co. v. B. B. McCormick & Sons, Inc., 151 F. Supp. 206, 1957 U.S. Dist. LEXIS 3534 (N.D. Fla. 1957).

Opinion

DE VANE, Chief Judge.

The several claims and cross-claims involved in this case were tried to the Court without a jury.

The Rea Construction Company had a contract with the Department of the Navy to make certain improvements and reconstruction at Corry Field, NAAS, Pensacola, Florida. Rea Construction Company subcontracted part of this work to B. B. McCormick & Sons, Inc. B. B. McCormick & Sons, Inc., in turn sub-subcontracted part of its work to Faulk & Coleman Construction Com[208]*208pany. The fourth-party defendant in this case, Aetna Casualty and Surety Company is the surety on Rea Construction Company’s performance bond. Neither B. B. McCormick & Sons, Inc., nor Faulk & Coleman Construction Company were bonded.

This litigation was precipitated by Faulk & Coleman Construction Company suing all the parties named in the caption above. The litigation involves contract disputes between Faulk & Coleman Construction Company and B. B. McCormick & Sons, Inc., on the one hand, and between Rea Construction Company and B. B. McCormick & Sons, Inc., on the other. , .

The Faulk & Coleman Controversy

Faulk & Coleman Construction Company claims in its suit against McCormick several items totaling $28,880.69. These several items are separately considered below.

The first item claimed is the amount of retainage held by McCormick under the contract in the amount of $15,836.-80. There is no controversy between- the parties as to this item.

As to the several- other items, the parties stipulated and agreed as to McCormick’s liability upon all of these, save one, in the total amount of $1,722.05. The one item remaining in controversy is the sum of $11,321.84, which represents a claim made by Faulk & Coleman for the hauling and disposal of a quantity of old pavement removed from drainage trenches by McCormick in the prosecution of its work under its part of the contract with Rea. Faulk & Coleman claim this as extra work beyond its contract with McCormick. On the other hand, McCormick claims that this item was included in the contract, or in the price agreed to be paid Faulk & Coleman for all the work it did.

Faulk & Coleman entered into a lump sum contract with McCormick, under which it agreed to do certain specified work listed in the contract for the lump sum price of $186,000. The contract specifies three types of work to be performed by Faulk & Coleman. The first two items specified in the contract are not in controversy, and the controversy arises out of Section 2, Item (C), which is as follows:

“Section 2.

“The sub-contractor and the sub-sub-contractor agree that the work to be done by the sub-sub-contractor is as follows * * *
“Item (C) all pavement removal except the sand-shell weep-holes.”

Laying aside at this point the testimony on the factual issues which are presented (and this testimony is in irreconcilable conflict), the Court finds and holds that this provision of the contract did not obligate Faulk & Coleman to remove the pavement cut by McCormick from the storm drainage ditches and piled along the edge of the runways. There' are two obvious reasons for this interpretation of the cold language of the contract. First, no one had any knowledge of the amount of pavement that would be cut and removed from the drainage ditches; and second, McCormick makes no claim against Faulk & Coleman for cutting and removing this pavement from the drainage ditches. The contract between the parties required Faulk & Coleman to cut all the pavement it was under obligation to remove from the runways. So to accept the interpretation placed upon this part of the contract by McCormick would entitle it to file in addition a claim against Faulk & Coleman for its cost in cutting and piling this concrete. The two items just do not match and for that reason, the Court is unable to find and hold that under the language of the contract, the removal of this pavement was included within the terms of Item (C) of the contract here in controversy.

It is the further contention of McCormick that before the contract was executed by the parties that the question of the removal of this particular concrete was discussed, and that Faulk & Coleman agreed to remove same without further compensation under its lump sum contract with McCormick. Faulk & Cole[209]*209man categorically deny this statement, and herein lies the serious conflict in the testimony. Mr. Coleman has two employees on his side of this controversy, who support him, and McCormick likewise has two employees on his side, who support his position in the matter. There is no way to reconcile this testimony and somebody has to be wrong.

The only matter in connection with this dispute that troubles the Court is that it developed at the trial that Faulk & Coleman in its estimate of the cost of the work it proposed to do for McCormick made a $10,000 error in its favor in its calculations, and if there was any evidence in the record that this error was known to the parties at the time the contract negotiations were concluded and the contract executed, it would be sufficient to satisfy this Court that the overall lump sum price included this work. It must be noted that the $10,000 error almost equals the amount here in dispute. But during the trial, it was admitted by all parties that none of them were aware of the error in Faulk & Coleman’s estimate when the contract was consummateu and executed. The evidence shows that Coleman used the estimate as his own guide during the negotiation, but that McCormick never saw it until after this litigation started. In the face of this evidence, the Court is unable to find and hold that this error played any part in the persuasion of Faulk & Coleman to include as an addition to its contract the removal of this concrete without additional compensation.

Upon all the testimony, the Court finds and holds that McCormick has failed to carry the burden of proof that the contract before its execution was orally amended to include this work.

McCormick further claims that in case the Court should find that Faulk & Coleman is entitled to be compensated for this work that the charges made for it are much too high. Again, we have conflicting testimony on the question, and again, the Court is forced to the conclusion that McCormick has failed to carry the burden of proof as to the unreasonableness of the charges made. These charges are in line with Coleman’s estimate of the cost of cutting and removing the estimated 76,000 square yards of pavement included in the contract. The Florida law governing the Court’s decision on this issue will be found fully set forth in Camichos v. Diana Stores Corporation, 157 Fla. 349, 25 So.2d 864, and case there cited.

McCormick filed in this case a counter-claim against Faulk & Coleman totaling $4,627.70. During the course of the trial, McCormick waived a $200 item and McCormick and Coleman agreed to split a $280 item between them. This reduces McCormick’s counter-claim to $4,-287.70. McCormick presented testimony fully supporting these items in the counter-claim and Faulk & Coleman offered no evidence contesting and disputing the claim. The counter-claim in the amount of $4,287.70 is allowed.

The Court recapitulates the allowed claim and counter-claim as follows:

Retainage due

Faulk & Coleman $15,836.90

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Miami v. Miami Dolphins, Ltd.