Fath Construction Co. v. Bausmerth

23 Ohio C.C. Dec. 382, 15 Ohio C.C. (n.s.) 150
CourtCuyahoga Circuit Court
DecidedDecember 16, 1911
StatusPublished

This text of 23 Ohio C.C. Dec. 382 (Fath Construction Co. v. Bausmerth) is published on Counsel Stack Legal Research, covering Cuyahoga Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fath Construction Co. v. Bausmerth, 23 Ohio C.C. Dec. 382, 15 Ohio C.C. (n.s.) 150 (Ohio Super. Ct. 1911).

Opinion

WINCH, J.

This is an action for wrongful death, under the Norris law, [385]*385so called, with verdict for the plaintiffs below in the sum of $6,000, which the court reduced to $4,000, entering judgment in the latter sum, the plaintiffs consenting to the remittitur.

At and before the time of the accident the deceased, Thomas Bausmerth, was working for the Construction Company in the erection of the Lorain Avenue Branch Library on the west side, in the city of Cleveland, for which erection the company had a contract. As the work progressed, certain steel I-beams were extended across the north wing of said building at a height of about twenty-five feet above the ground, to form the framework of the ceiling of the rooms below and the roof of said wing. These I-beams were placed at regular intervals of eight feet and six inches apart.

Some twelve or fifteen days before September 9, 1910, the day on which Bausmerth received his fatal injury, he and other workmen were directed by the foreman on the job to construct a scaffold, platform, staging of flooring upon said I-beams, and for this purpose were furnished planks sixteen feet long. The foreman superintended the construction of the platform, and it was so laid that the ends of the planks overlapped between the second and third I-beams, counting from the north wall. In this condition the platform was unsafe, for a weight superimposed upon these overlapping ends between the second and third I-beams would cause the planks to tip down and drop the weight through. This danger, however, was obviated by erecting a heavy derrick over the north end of the north row of planks and immediately over I-beam number one, the supporting timbers of the derrick extending east and west across said planks and timbers being spiked on top of and cross-wise of said planks, one on either side of and against the supporting timbers of the derrick. The derrick was used for hoisting up material from the outside of the building.

On the day in question, the walls of this wing being complete, except the laying of a few coping stones, the foreman had said derrick removed and the timber spiked to the planks tom up. This left a defective condition of the platform, for the [386]*386overlapping plank ends between I-beams two and three would not now sustain any heavy -weight. ,

The petition contains the following allegation:

“Plaintiffs say that said platform, scaffold, staging or flooring, constructed as hereinbefore described and for the purpose aforesaid and constituting a part of the ways, works, plant and appliances which were connected with and used in the business of the defendant, was negligently, carelessly and unlawfully left by said defendant in a weakened, defective and unsafe condition as aforesaid, which said weakened, defective and unsafe condition was fully known, observed and understood by said defendant through its foreman, Koenig, but wholly unknown, unnoticed and uncomprehended by said deceased.”
“Plaintiffs say that shortly after said platform had been converted from a safe into a dangerous place, as aforesaid, to-wit: at about 12:30 P. M. on September 9, 1910, the decedent was expressly ordered and commanded by said foreman, Koenig, to help him and five other of said workmen carry a large coping stone, weighing between 600 and 700 pounds, from the top of a ladder placed against the southerly side of I-beam number four across said platform to said north wall; that in compliance with said express order and command, the said decedent did then and there, with the aid of the six other men, including said foreman, take hold of said stone and lift it and proceeded to carry the said stone across said platform towards said north wall, all the while in the exercise of due care and without negligence on his part and under the express and direct commands and guidance of the said foreman, and had proceeded until he and they had reached a point on said platform directly over the center of the said space between said I-beam numbers two and three, when suddenly and unexpectedly and without warning of any kind to said decedent, said platform gave -way by reason of six or seven planks of each said row of planks tipping down because of so great a load imposed upon it, and caused said stone and said decedent together wdth four other of said men to fall through said space and down onto said floor I-beams and thence to the ground some thirty feet beneath, so crushing and mangling said [387]*387decedent that he died from said injuries the following morning. ”

It is, perhaps, unnecessary to quote further from the petition.

Several errors are alleged to have occurred at the trial:

First, it is claimed that no evidence should have been received under the petition, because it fails to contain an allegation that the decedent did not have equal means of knowing with the master, or, by the exercise of ordinary care, could not have discovered, the existence of the defect.

As the law stood until the adoption of the Norris law, April 30, 1910, 101 O. L. 195, the petition was defective in this respect.

Chicago & Ohio Coal & Car Co. v. Norman, 49 Ohio St. 598, 607 [32 N. E. Rep. 857].

This rule of pleading', however, was abrogated by the act referred to.

Section 6245 of said act provides:

“That in any such action (for personal injuries or wrongful death, as provided in section 6242) when it shall appear that the injury or death was caused in whole or’ in part by any of the following, to-wit: * * * any defective or unsafe condition in the ways, works, boats, wharves, plant, machinery, appliances or tools, except simple tools, in any way connected with or in any way used in the business of the employer, the fact that such employe continued in said employment with knowledge of such negligent omission or want of care, or such defective or unsafe condition shall not be a defense unless,” etc.

In conformity with the Norman ease, the legislature might have said: “It shall not be necessary for the employe to allege in his petition or prove on the trial that he did not continue in said employment with knowledge of such negligent omission or " want of care,” etc., but in common parlance “assumption of risk”' — and the matter here mentioned comes within the meaning of that expression — has always been spoken of as a defense. Evidently, with this idea in mind, the legislature said “it shall not be a defense.”

The manifest intention of the act was to take out of the [388]*388case the question of the employe’s actual or constructive knowledge of the defect complained of, and this we believe it does. Whether this part of the act is constitutional or not will be treated of later in a consideration of the charge.

It is said, however, that the temporary platform or scaffold described in the petition does not come within the meaning of the words 1 ‘ ways, works, boats, wharves, plant, machinery, appliances or tools,” as used in the statute, and the ease of Mason v. Ferguson, 31 O. C. C. 623 (12 N. S. 567), decided by the Hamilton county circuit court, sustains this proposition.

We are not in accord with that decision, nor do we think it sustainable upon the authorities therein cited, nor upon reason.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
23 Ohio C.C. Dec. 382, 15 Ohio C.C. (n.s.) 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fath-construction-co-v-bausmerth-ohcirctcuyahoga-1911.