Fastrack Crushing Services, Inc. v. Abatement International/Advatex Associates, Inc.

893 A.2d 674, 153 N.H. 284, 2006 N.H. LEXIS 18
CourtSupreme Court of New Hampshire
DecidedFebruary 24, 2006
DocketNo. 2005-132
StatusPublished
Cited by3 cases

This text of 893 A.2d 674 (Fastrack Crushing Services, Inc. v. Abatement International/Advatex Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fastrack Crushing Services, Inc. v. Abatement International/Advatex Associates, Inc., 893 A.2d 674, 153 N.H. 284, 2006 N.H. LEXIS 18 (N.H. 2006).

Opinion

Broderick, C.J.

The defendants, Abatement International/Advatex Associates, Inc. (Advatex), and American Guarantee & Liability Insurance Co. (AGLIC), appeal an order of the Superior Court (Morrill, J.) denying their motion to dismiss the claim of the plaintiff, Fastrack Crushing Services, Inc. (Fastrack), and an order of the Superior Court (McHugh, J.) in favor of Fastrack on the parties’ cross-motions for summary judgment. Fastrack cross-appeals an order from the Superior Court (Morrill, J.) denying its motion to reconsider on the issue of attorney’s fees and late payment charges. We reverse the trial court’s ruling on the defendants’ motion to dismiss and therefore do not address the motions for summary judgment or attorney’s fees and late payment charges.

The record supports the following facts. Fastrack was a second-tier subcontractor on a public works project for which Advatex was the general contractor. Pursuant to RSA 447:16 (2002), Advatex obtained a payment bond on the project from AGLIC. The project was completed and accepted on June 15, 2000. Within ninety days, Fastrack notified Advatex and AGLIC that it had not been paid what it was owed under its contract with a first-tier subcontractor. Within one year of that notification, it filed suit in the superior court. The defendants moved to dismiss on the grounds that the notice did not comply with RSA 447:17 (2002) (amended 2004, 2005) because it was not filed with the clerk of the superior court. They further argued that, because of the defective notice, the suit was not timely filed within the one-year provision of RSA 447:18 (2002).

Fastrack prevailed on its claims in the superior court, but we reversed on the grounds that, although it had given actual notice to the defendants, [286]*286Fastrack failed to comply with the statutory notice requirements of RSA 447:17 and RSA 447:18. Fastrack Crushing Servs. v. Abatement Int’l/Advatex Assocs., 149 N.H. 661, 664-67 (2003). Within ninety days of that decision, but almost three and one-half years after the project’s completion and acceptance, Fastrack filed a statement of claim against the bond with the superior court clerk. Shortly thereafter it filed a new petition in the superior court to enforce the claim.

Advatex and AGLIC moved to dismiss the petition on two grounds: (1) Fastrack’s filings were untimely under sections 17 and 18 of RSA chapter 447; and (2) the petition itself was deficient as it did not, nor could it, “contain an allegation ... of the facts showing compliance by the claimant with the provisions of’ sections 17 and 18. Fastrack conceded that the section 17 notice was filed with the court clerk after the ninety-day time period, but contended that RSA 508:10 (1997) allowed it to file a second action. The superior court agreed and denied the motion to dismiss. This appeal followed.

Although this comes to us as an appeal from a motion to dismiss, we must interpret sections 17 and 18 to determine whether the ninety-day and one-year time periods included in those sections constitute preconditions to filing a claim on a statutory bond. Interpretation of a statute is a question of law that is reviewed de novo. See Crowley v. Frazier, 147 N.H. 387, 389 (2001).

We address the ninety-day requirement first. Section 17 states in relevant part:

To obtain the benefit of the bond, any person, firm or corporation having any claim for labor performed, materials, machinery, tools, or equipment furnished as aforesaid shall, within 90 days after the completion and acceptance of the project by the contracting party, file ... in the office of the clerk of the superior court for the county within which the contract shall be principally performed... a statement of the claim....

RSA 447:17. We have previously held that where statutes create claimants’ rights, those rights can only be enforced by the means specified in the statutes. See American Fidelity Co. v. Cray, 105 N.H. 132, 135 (1963). Our law is well settled that to give proper notice, the requirements of the statute must be strictly observed. Id. at 136.

The only situation in which we have allowed a claim to go forward despite a violation of the ninety-day rule was where the statutorily required notice was given before completion and acceptance of the job. See New Eng. Culvert Co. v. Williams Constr. Co., 105 N.H. 235, 238-39 (1963). Fastrack has previously asked us to extend the reasoning of New England [287]*287Culvert to this case, which we declined to do. Fastrack, 149 N.H. at 666-67. We stated:

[W]hereas the deficiency alleged in New England Culvert involved merely a premature delivery of proper notice, here [Fastrack] has failed to file any notice at all with the superior court clerk, the statutorily designated party. Premature notice is, if anything, more advantageous to the respondent than notice within the statutory time window. For this reason, premature notice that is “in form ... in strict compliance with the statute” is not fatal to the claim, even in cases where the underlying statute must be strictly construed. Aside from this special circumstance, however, we have not countenanced any violations of the letter of RSA 447:17.

Id. at 667 (citations omitted).

Compliance with time periods such as the ninety-day provision of section 17 are generally considered conditions precedent to the right to maintain a suit against statutory bonds. See 17 Am. Jur. 2d Contractors’ Bonds § 113 (2004). Such a rule has been adopted by federal courts interpreting similar provisions passed by Congress. See, e.g., United States, Etc. v. J. F. White Contracting, 649 F.2d 29, 31 (1st Cir. 1981) (construing Miller Act, 40 U.S.C. § 270b (1970)); American Build & Contract Supply v. Bradley Const., 960 F. Supp. 145, 147 (N.D. Ill. 1997) (same).

In light of the foregoing, we now hold that giving notice within the ninety-day time period as required by RSA 447:17 is a condition precedent to any claim against the bond. Accordingly, except where a petitioner files its notice before a job’s completion and acceptance, no cause of action against a bond’s principal or surety will arise until the claimant complies with the notice requirements of that section. This construction reflects the policy behind these types of statutes, permitting

the prime contractor, after waiting ninety days, safely to pay his subcontractors without fear of additional liability to sub-subcontractors or materialmen. The notice provision thus prevents both double payments by prime contractors and the alternative of interminable delay in settlements between contractors and subcontractors.

J. W. Bateson Co. v. Board of Trustees, 434 U.S. 586, 590 n.4 (1978) (citation and quotations omitted); see also 5 S.G.M. Stetn, CONSTRUCTION Law ¶ 17.03 [10] [e] (May 2004) (“These statutes are, typically, intended to protect prime contractors by allowing them to exercise retainage rights on [288]*288payments due and owing to subcontractors to ensure the prime contractor has some way to safeguard itself.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evan Gray v. P Chester L. Gray, III, Trustee
2023 DNH 146 (D. New Hampshire, 2023)
Gray v. Gray
D. New Hampshire, 2023
General Insulation Co. v. Eckman Construction
992 A.2d 613 (Supreme Court of New Hampshire, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
893 A.2d 674, 153 N.H. 284, 2006 N.H. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fastrack-crushing-services-inc-v-abatement-internationaladvatex-nh-2006.