Farren v. Willard

245 P. 206, 76 Cal. App. 460, 1926 Cal. App. LEXIS 518
CourtCalifornia Court of Appeal
DecidedFebruary 5, 1926
DocketDocket No. 2721.
StatusPublished

This text of 245 P. 206 (Farren v. Willard) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farren v. Willard, 245 P. 206, 76 Cal. App. 460, 1926 Cal. App. LEXIS 518 (Cal. Ct. App. 1926).

Opinion

THE COURT.

On the thirtieth day of January, 1920, the defendant entered into a contract with the plaintiff Western Well Works, Incorporated, whereby the plaintiff agreed to furnish certain pumps, motors, and equipment and the defendant agreed to pay therefor the sum specified in said contract. This action is for a balance alleged to be due on account of the unpaid portion of the purchase price of said equipment. The defendant, by cross-complaint, alleged damages for failure on the part of the plaintiff, Western Well Works, Incorporated, to furnish the pumps, motors, and equipment according to the terms of said contract, the damages sought to be recovered being damages alleged to have been suffered by reason of such delay on the part of said plaintiff in fulfilling its contract. Upon the conclusion of the testimony, the court granted a nonsuit as to defendant’s cross-complaint and directed judgment for the plaintiff for the unpaid portion of the amount agreed to be paid by the defendant for the pumps, motors, etc. From this judgment the defendant appeals.

It appears from the testimony in this case that preceding the execution of the contract between the said Western Well Works, Incorporated, and the defendant Willard, certain agents of said plaintiff called upon said Willard and *463 negotiations were had, leading np to the execution of the contract for the purchase of the machinery and equipment mentioned therein; that the defendant refused to sign the printed form of the contract submitted to him by the agents of the plaintiff, unless provision were made therein for the immediate delivery of the articles about to be ordered. It further appears that the agent, not being authorized to make any change in the written form of the contract tendered to the defendant, communicated with the plaintiff at its home office and was instructed and authorized to arrange for delivery as required by the defendant, and thereupon there was inserted in said contract the following written clause: “Delivery: Shipment to be made of all three pumps at once.” It appears that the reason for desiring immediate delivery was that certain lands rented by the defendant were to be seeded to rice and that the pumps and equipment should be installed and in working order by the first day of May of the year 1920. The contract referred to contained, among other things, that the plaintiff, Western Well Works, Incorporated, would install the pumping machinery, and other conditions which we need not mention, and also had therein the following printed clause: “Responsibility: The time of delivery named above is contingent upon delays occasioned by strikes, civil or military authority, or other hindrance or calamities beyond our control, nor do we assume any liability for damage on account of delays, or for defective material furnished other than to make good such defects as may be proved to have existed when said material was furnished.” The transcript further shows that the Western Well Works, Incorporated, did not have on hand and was not a manufacturer of electrical motors, but these facts were not disclosed to the defendant. It also appears that notwithstanding the written portion of the contract to make delivery at once, the plaintiff, Western Well Works, Incorporated, did not order or make any effort to secure the electrical motors contracted to be delivered until on or about the fourteenth day of April, 1920, seventy-three days after the date of the contract first herein referred to. The answer of the plaintiff, Western Well Works, Incorporated, admits that sixty days was a reasonable time within which to furnish the machinery contracted to be delivered. It also appears that the motors ordered by the plaintiff, Western Well Works, Incorporated, *464 on the fourteenth day of April, 1920, were delivered within sixty days of the date of the order given therefor. No explanation appears of why seventy-three days were allowed to elapse between the date of receiving the order signed by the defendant and the date when the plaintiff, Western Well Works, Incorporated, ordered the motors in question contracted to be delivered by them.

It appears from the transcript that the defendant Willard had leased some two thousand five hundred acres of land to a tenant by the name of Marr to be seeded to rice; that all but two hundred acres of land were subject to irrigation by waters obtained from a canal company; that two hundred acres of the land in question were of such elevation that irrigation could not be had by water furnished through the canals of the irrigation district and therefore in the lease executed by the defendant to his tenant Marr there was inserted the following covenant: “It is further understood and agreed between the parties hereto that the party of the first part (the defendant herein) will at his own proper charge and expense drive down wells and install pumping plants or units in sufficient numbers with which to irrigate all that portion of land which lies above or is too high to be irrigated from the Main or Central canal, etc.” The lease in question also contained the following subdivision: “It being understood and agreed however, between the parties hereto that the party of the first part does not become the guarantor or the insurer that the whole or. any amount of said water shall be furnished at any time during the term of this lease, or any year thereof or that water will be furnished to said land that can be irrigated from said Main Canal, etc. ’ ’ Provision was further made in the lease for a rebate of rent upon failure of water furnished by the irrigation district through its canals. There does not appear in the lease any provision for rebate of rent on account of any failure of the lessor Willard to comply with his covenant. The lack of such a covenant, however, does not relieve him from the legal liability to perform his covenants as contained in the lease, and the argument to the contrary does not seem to us to require any consideration further than to state that performance within a reasonable time and at a time early enough to enable his tenant to use the water *465 when required is necessarily inferred from the covenant to sink the wells, install the pumps and machinery necessary to operate the same. It may be true that he did not guarantee that the wells would furnish sufficient water, but that does not in anywise relieve the lessor from the performance of his part of the covenants contained in the lease. It further appears from the transcript that the rental agreed to be paid for the leased land was the sum of forty dollars per acre and that promissory notes were executed therefor; that upon failure to furnish water for the two hundred acres in question, and which were not seeded by the tenant on account of the water not being furnished, the defendant Willard, as lessor, gave his tenant credit for the sum of eight thousand dollars, the rent covenanted to be paid for the two hundred acres in question. The testimony further shows that in order to properly cultivate the rice, the water should have been furnished by the first day of May; that the water was not furnished by reason of the failure of the plaintiff, Western Well Works, Incorporated, to furnish the equipment contracted for promptly, as specified in the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henne v. Summers
116 P. 86 (California Court of Appeal, 1911)
Bonslett v. Butte County Canal Co.
122 P. 821 (California Court of Appeal, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
245 P. 206, 76 Cal. App. 460, 1926 Cal. App. LEXIS 518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farren-v-willard-calctapp-1926.