Farrelly v. United States

159 F. 671, 86 C.C.A. 539, 1908 U.S. App. LEXIS 4114
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 7, 1908
DocketNos. 92, 93
StatusPublished
Cited by9 cases

This text of 159 F. 671 (Farrelly v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrelly v. United States, 159 F. 671, 86 C.C.A. 539, 1908 U.S. App. LEXIS 4114 (2d Cir. 1908).

Opinion

LACOMBE, Circuit Judge.

The contract was entered into November 16, 1899. By it the parties of the second part-agreed to furnish the necessary equipment and do all the work of dredging required in a certain part of Narragansett Bay, in accordance with specifications attached. In consideration of the parties of the second part performing the required work (removing about 2,056,491 cubic yards of material) the party of the first part agreed to pay at the rate of 10.8 cents per cubic yard. All materials and work, before acceptance, were to be subject to a rigid inspection, and the decision of the engineer officer in charge as to quality and quantity was to be final. It was provided that payments should be made monthly when funds are available, 10 per cent, being reserved; also that “the said Perkins & O’Brien shall commence work on or before the 1st day of March, 1899, and shall complete the work on or before the 1st day of July, 1902.”

Work was begun on March 1, 1899, and, although at the outset it was apparently pushed sufficiently to satisfy the engineer officer in charge, after several months the rate of progress was such that he repeatedly called upon the contractors to increase their monthly output, and finally, on December 31, 1900, sent a letter to each of the principals, and to the surety, formally notifying them that the work under the contract had not, in his judgment, been prosecuted faithfully and diligently, and that the contract “is hereby annulled.” At that time there had been 526,708 cubic yards in all removed, 13,406 in the current month. The engineer supposed there was about 1,500,000 yet to be taken out; but in reality there was only 1,300,000. It was, as the engineer testified, “a very possible thing, easily accomplished, for any one to have completed that contract within 18 months if they had the plant. * * * My judgment was that these men could not control sufficient plant to complete what remained to be done * * * in the remaining time.” Since the most important question in the case deals with the results of such annulment, it will be first considered.

The contract contains the following clause, which is found near the close of the document: .

“It is further understood and agreed that, In case of failure on the part of the party of the second part to complete this contract as specified and agreed upon, all sums due and percentage retained shall thereby be forfeited to the United States, and that the said United States shall also" have the right to re[673]*673cover any or all damages due to such failure in excess of the sums so forfeited, and also to recover from the party of the second part, as part of said damages, whatever sums may be expended by the party of the first part in completing the said contract, in excess of the price herein stipulated to be paid to the party of the second part for- completing the same.”

Earlier in the contract, and immediately after the clause providing for the beginning and completion of the work, is found the following clause:

“Tf, in any event, the party of the second part shall delay or fail to commence with the delivery of the material or the per formalice'of the work oil the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently (he work in accordance with the specifications and requirements of this contract, then, in either case, the party of the first part, or his successor legally appointed (i. e., (he engineer officer in charge), shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party (or parties, or either of them) of the second part; and upon the giving of such notice all money or reserved percentage due or to become due to the parly or parties of the second part by reason of this contract shall be and become forfeited to the United States; and the party of the first part shall be authorized, if an immediate performance of the work or delivery of the materials be in his opinion required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in section 3709 of the Revised Statutes of the United States.”

The section of the Revised Statutes referred to [U. S. Comp. St. 1901, p. 2484] provides that all purchases and contracts for supplies or services shall be made by advertising a sufficient time for proposals when the public exigencies do not require immediate delivery or performance, and that when the public exigency requires the same may be obtained by open purchase or contract without advertisement. The notice of annulment of this contract was given under the clause last above quoted.

It will be seen that, in the event oí a “failure to complete the contract as specified and agreed upon,” all sums due and percentage retained are forfeited, and the United States is also entitled to recover all damages in excess of such forfeiture due to such failure, including the excess cost of completion. Inasmuch as a stated time is given for completion, it would not ordinarily he possible to declare that there had been a failure to complete, until the time given for such completion had elapsed. It might frequently cause great embarrassment to the government if it should be required to wait till the day when the breach was complete, especially when the conduct of the contractor and the manner in which he was prosecuting the work indicated that he would not complete it on the day named. In order, therefore, to provide for such a contingency, the annulment clause was inserted, giving to the engineer officer the right to terminate the contract in advance of the time allowed for its fulfillment, whenever in his judgment the contractor may fail to prosecute the work faithfully and diligently. This clause, while no doubt necessary, is a drastic one. It allows the government to terminate the contract although — as was the case here- — the contractor could easily have fully completed the work in the time yet left, had he mended his ways and been allowed to continue. Moreover, while in one sense it may be said that a contractor who fails to prose[674]*674cute the work faithfully and diligently for part of the time allowed him is not doing what the contract impliedly requires him to do, nevertheless, where there is no clause in the contract directing that he shall perform some specified part of the work within some specified time, or even that he shall do some work each month, it can hardly be said that he has broken the contract just because he has been so slothful during the first half of the period allowed him that he will have to be very much'more diligent during the remainder of the period, in order to fully complete the work on time. Since this clause is thus drastic, and permits the government to terminate the contract while the contractor is still able to complete, and by such completion avoid a breach of its provisions, it might be expected that the damages to be assessed against him would not be so heavy as those provided for when he has actually failed to complete the contract as specified within the time allowed. Reference to the clause shows that it contains no words calling for damages arising from excess cost of completion. It reads merely:

Upon annulment “all money or reserved percentage due or to become due to the party or parties of the second part by reason of this contract shall be and become forfeited to the United States.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Gas & Fuel Co. v. Stern
15 F.2d 323 (Eighth Circuit, 1926)
California Prune & Apricot Growers, Inc. v. Baker
246 P. 1081 (California Court of Appeal, 1926)
Conway v. White
9 F.2d 863 (Second Circuit, 1925)
Davis v. Jointless Fire Brick Co.
300 F. 1 (Ninth Circuit, 1924)
Galban Lobo & Co. v. United States
285 F. 665 (S.D. New York, 1922)
Bunnell v. Traynor
133 N.E. 503 (Indiana Court of Appeals, 1922)
Robertson v. Garvan
270 F. 643 (S.D. New York, 1920)
United States v. O'BRIEN
220 U.S. 321 (Supreme Court, 1911)
United States v. Stone, Sand & Gravel Co.
177 F. 321 (Fifth Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
159 F. 671, 86 C.C.A. 539, 1908 U.S. App. LEXIS 4114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrelly-v-united-states-ca2-1908.