Farmers Pawnee Canal Co. v. Pawnee Water Storage Co.

47 Colo. 239
CourtSupreme Court of Colorado
DecidedJanuary 15, 1910
DocketNo. 5813
StatusPublished
Cited by3 cases

This text of 47 Colo. 239 (Farmers Pawnee Canal Co. v. Pawnee Water Storage Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmers Pawnee Canal Co. v. Pawnee Water Storage Co., 47 Colo. 239 (Colo. 1910).

Opinion

Mr. Justice Campbell

delivered the opinion of the court:

The object of this action is to relieve against a threatened forfeiture of certain rights and privileges which plaintiff storage company claims it obtained as the result of a contract which it entered into with defendant canal company. The character of this contract, made December 5, 1898,' is disclosed, and its material provisions which gave rise to the pending controversy are embodied, in paragraphs 1, 2, 8 and 9, which are substantially as follows:

1. “That for and in consideration of $1 in hand paid by said Storage Company, to the said Canal Company, the receipt of which is hereby acknowledged, and in consideration of the premises and the undertakings herein set forth, to be kept and performed by the said Storage Company, the said Canal Company hereby grants to the said Storage Company, its successors and assigns, the right and privilege of using and enjoying its canal and headgates, for the purpose of conveying water to any and all reservoirs constructed along the line of said canal owned by the said Canal Company, * * * with the right to extend and enlarge the said canal, or any section of the same, to such extent as may be requisite to convey the waters of the South Platte river and its tributaries to the lands, canals and reservoirs now [242]*242owned or hereafter to he acquired by the Storage Company. ’ ’

2. “The Canal Company also grants to the Storage Company the privilege of building laterals, branches or extensions of the Canal Company’s canal, through which surplus, waste and seepage water might be conducted and delivered direct to purchasers from the Storage Company.”

8. “It is further agreed and understood that the said Storage Company shall complete a system of reservoirs along and under the line of said canal within five years from the time of the ensealing and delivery of these presents, and if at the termination of the said period the said Storage Company shall have failed to have used said canal for the purpose referred'to in this contract, then all of the rights and privileges herein mentioned and granted by the said Canal Company to the said Storage Company shall be waived, and this contract be void,- otherwise it shall 'remain in full force and effect. ’ ’

9. “It is hereby agreed by the parties hereto to co-operate to the end that the widest service of the canal and the storage system shall obtain, and the largest public utility result. ’ ’

Other clauses particularly define the reciprocal rights and duties of the parties, and the limitations, as to the nature, and length of time, of the use of the canal, to which they are subjected when the contract is fully performed.

The principal dispute concerns the eighth clause. The parties are not in accord as to its meaning or the proper construction of the contract as a whole. The plaintiff says that this clause is a mere covenant and the only remedy for its breach an action for damages; but if not a covenant, then it is a condition subsequent, which does not prevent the vesting of the estate which is the subject-matter of the contract, [243]*243but only defeats it in case of nonperformance. Defendant says that taking the contract, as should be done, in its entirety, clause eight constitutes a condition precedent; and while in the first clause the language is “hereby grants,” yet, since by a fair construction of the entire contract the use and enjoyment of the canal could not, in the nature of things, -be had until after the completion of the system of reservoirs, the vesting of the estate is necessarily deferred until full performance of the condition precedent; and as, confessedly, as will be seen later on, the condition was not fulfilled, plaintiff never acquired the rights under the contract which it would have obtained had the condition been performed. These contentions will be further referred to in an appropriate place in the opinion,- but we shall decide this case, as that is the most favorable view, in plaintiff’s favor, on the assumption that the clause in question is a covenant; or condition subsequent. It will be observed that by its terms the storage company was required to complete a system of reservoirs along the line -of defendant’s canal within five years from the time the contract went into effect, and there was to be a forfeiture by the storage company of its contract rights, if, at the end of the five years, it failed to use the canal for the purposes therein referred to. Notwithstanding the language of the first paragraph, which says that the consideration moving from the storage company is one dollar and the undertakings set forth in the contract itself, the storage company says that‘the principal, if not the only, consideration of value to defendant was a previous settlement of all controversies concerning their relative rights made by the original owner and builder of the canal, to whose rights the plaintiff-storage company here has succeeded, with its water consumers who are represented here by defendant [244]*244canal company. Although this claim is denied, in disposing of this case we may assume that that settlement constituted a part of such consideration. Until the contract itself is reformed the storage company, however, cannot be heard to say that it was not re'quired by this contract, among other things, to complete a system of reservoirs along and under the line of defendant’s canal as clause eight says. '

’ For about three years and a half after the date of the contract, plaintiff did practically nothing towards performing any of the conditions which were named as the consideration for the things granted to it. In the summer of 1902 it began preliminary surveys for the prescribed reservoirs and made filings under the statute. No actual work in the way of building reservoirs was then, or ever, done. The system along the line of defendant’s canal contemplated was for the storage of water by means of which government lands, and lands owned”by private individuals, favorably situated, might be irrigated. Some time during the summer of 1902 the United States government withdrew from entry its lands in this neighborhood, and it was publicly announced and generally understood in that part of the country that the government contemplated the building of a large reservoir with which to irrigate both public and private lands. Plaintiff company then entirely ceased all operations with the avowed intention of abandoning its enterprise, after having reached the conclusion that this project of the government, if consummated, would render commercially unprofitable the system of reservoirs and extension and enlargement of defendant’s canal which this contract contemplated on its part. Nothing further under the contract was done by plaintiff until some time in the spring or early summer of the year 1903. The United .States government abandoned its project in July, 1903. Plain[245]*245tiff’s president having obtained information of the proposed abandonment abont three months before it was publicly proclaimed, concluded to go on with a part'of the scheme contemplated by the contract. It began then, in March or April, 1903, the work of building a ditch below the end of defendant’s canal, twelve or fourteen miles long, which it proposed to connect therewith, nearly completed the same and lacked but a few feet of actually connecting it with defendant’s canal. It did not, however, finish this work within the limited period of five years, which was December 5, 1903, and never has done so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. McDavid
676 P.2d 714 (Colorado Court of Appeals, 1983)
Home Builders Co. v. Reddin
48 P.2d 800 (Supreme Court of Colorado, 1935)
Operative Service Corp. v. McIntyre Pump Co.
277 P. 773 (Supreme Court of Colorado, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
47 Colo. 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmers-pawnee-canal-co-v-pawnee-water-storage-co-colo-1910.