Farelly Lake Levee District v. McGeorge

289 S.W. 753, 172 Ark. 460, 1926 Ark. LEXIS 90
CourtSupreme Court of Arkansas
DecidedDecember 20, 1926
StatusPublished
Cited by2 cases

This text of 289 S.W. 753 (Farelly Lake Levee District v. McGeorge) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farelly Lake Levee District v. McGeorge, 289 S.W. 753, 172 Ark. 460, 1926 Ark. LEXIS 90 (Ark. 1926).

Opinion

McCulloch, C. J.

Appellant district was created as a local improvement district for the purpose of constructing through Jefferson and Arkansas counties a levee along the bank of the Arkansas River, and also to construct necessary ditches, spillways and floodgates. It was deemed necessary to construct two floodgates, one across the mouth of the stream known as Little Bayou Meto. The levee had been built across the mouth of the bayou, and it was considered necessary to put in the floodgate so that the water would be prevented from flowing into the bayou from the Arkansas River in times of overflow and to permit the water to flow out of the bayou in times of normal stages of water in the river. The work was to be done by cutting a gap through the levee fifty feet wide and constructing concrete walls, wings and flooring and two heavy steel gates reaching to the height of the levee and the two walls on each side, thus closing the aperture when necessary.

Appellees entered into a written contract with the district to furnish the material and construct the floodgates for the schedule of prices on the unit basis. The contract was executed on April 22, 1921, and provided that the work should be completed within six months from that date. There was long delay in completing the work, and it was not formally accepted by the engineers as complete until October 1, 1924.

The sum of $112,413.28 was paid to appellees by the district during the progress of the work, and there is a conceded balance due in the sum of $17,817.60 according to the schedule of prices in the contract. There are, however, numerous other items claimed by appellees, but disputed by the district, and the latter also brings forward a claim against appellees for liquidated damages on account of delay in completion of the work according to the terms of the contract. Appellant also claims other items as credits on the balance due appellees for work under the contract. The total amount of balance claimed by appellees is about $32,000, and this action was commenced against appellant to recover that' amount. Appellant filed a cross-complaint asking for recovery of liquidated damages in the sum of $25,342.79 and other credits claimed, running the amount up to $33,834.27, and, after conceding liability to appellees in the sum of $18,865.60, prayed for judgment over against appellees for the difference between the two claims, $14,968.67. The cause was tried in the chancery court of Jefferson County, without objection, and, after hearing the evidence, the court rendered a decree in favor of appellees against appellant for the recovery of $25,698.21, made up of the following items (less a credit of $17.23, unpaid on rental):

(1) Amount of final estimate..............................$17,817.60
(2) Item 15: Preparing sub-base, north end .................................................................................... 227.52
(3) Item 18: Preparing sub-base, L. L. section ................................ 6.43
(4) Item 20: Removing old concrete S. W. corner.......................*................................... 76.41
(5) Item 24: High water Feb., 1923............ 76.41
(6) Item 25: Creosoted seal timbers............ 512.29
(7) Item 26: High water, May and June, 1923 .................................................-........... 662.96
(8) Shortage and gravel............................................. 5,286.75
(9) Riprap stone.................................................................. 948.00
(10) Rent of concrete mixer....................................... 100.00
$25,715.44

The most important part of the controversy relates to appellant’s claim against appellees for recovery of liquidated damages on account of the delay in completion of the work. The contract between the parties contained a clause providing for liquidated damages, which reads as follows:

“In case of default in completing the whole work to be done under this contract within the time specified, including such extensions as may have been granted, the contractor hereby agrees to pay to the party of the first part as liquidated damages for such default: First, a sum sufficient to compensate said first party for the cost and expense of employing engineers, inspectors and employees to the extent that their services are reasonably required during the period of default by the work of this contract; and, second, a sum equal to one per cent, on all moneys that have been paid the contractor under this contract for each calendar month or part thereof that the completion of the whole work under this contract is delayed. The party of the first part shall have the right to deduct such liquidated damages from any moneys due or to become due the contractor, and the amount, if any, still owing after such deduction shall be paid on demand by the contractor or his surety. Payment of such liquidated damages shall not relieve the contractor or his sureties from any other obligations under this contract.”

According to the contract, appellees were to begin work on June 15,1921, and. the testimony shows that they began work a few days before that time. The work was to be completed, as we have already seen, on December 15, 1921, but it was not so completed, and in February, 1922, the commissioners of the district, by resolution duly passed, granted an extension to appellees to complete the work on or before November 15, 1922; and on March 15, 1924, the work not having been accepted, another extension to September 21,1924, was granted by the commissioners, and, as before stated, there was a formal acceptance on October 1,1924.

Testimony adduced by appellees tends to show that the gates were completed and swung in October, 1923, and were complete, except the painting and a slight defect about their working smoothly when being raised or lowered, and were used by the district from that time on, though there was no formal acceptance until October, 1924. There was a short delay in the early part of the work on account of high water, and there was a delay also during the summer and fall of 1921 on account of the inability of the district to make payments for the work as it was done. The district sold bonds in the sum of $1,100,000, the money to be advanced by the bond purchaser in installments, and there was a default in these advancements, which caused considerable delay in the work. Appellees also introduced testimony to the effect that there were numerous other delays resulting from causes beyond their control, and, in most instances, the delays were caused by the officers and agents of the district itself. In other words, there was testimony adduced by appellees tending to excuse themselves from fault with respect to the delay in completion of the work, but there is a conflict in the testimony, and, under the view we take of the case, it becomes unnecessary to settle this conflict. The clauses of the contract which are material to the decision of this point in the case are as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haskins Law Firm v. American National Property & Casualty Co.
804 S.W.2d 714 (Supreme Court of Arkansas, 1991)
Hicks v. Norsworthy
4 S.W.2d 897 (Supreme Court of Arkansas, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
289 S.W. 753, 172 Ark. 460, 1926 Ark. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farelly-lake-levee-district-v-mcgeorge-ark-1926.