Farber Electric & Plumbing Co. v. Professional Realty Corp.

85 P.R. 441
CourtSupreme Court of Puerto Rico
DecidedMay 21, 1962
DocketNo. 12600
StatusPublished

This text of 85 P.R. 441 (Farber Electric & Plumbing Co. v. Professional Realty Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farber Electric & Plumbing Co. v. Professional Realty Corp., 85 P.R. 441 (prsupreme 1962).

Opinion

;Per curiam.

.Farber Electric and Plumbing Co., Inc., hereinafter called Farber, contracted with Professional Realty Corporation, hereinafter called Professional, for the electric installation of a building which the latter was constructing. Upon completion of the work Farber sued Professional for recovery of a certain amount of money owed to it on account of such work. Professional counterclaimed.

The parties stipulated to submit the question to a special master, pursuant to the provisions of Rule 53 of the Rules of Civil Procedure of 1943 (Rule 41 of the Rules of 1958), for determination “of the amount actually spent in materials and labor.” Master Waymouth submitted a report from which it appears that Professional owed Farber the sum of $45,187.07. We copy from the report what Waymouth entitled “Summary”:

“Summary
“From the data shown in this report it appears that the total cost of the electric contract of ‘Professional Building’ was $188,514.86, as follows:
Total Adjusted “Extra”
Cost Original Work
Contract
Materials $85, 745. 94 $17, 373. 85 $68, 372. 09
Labor 31, 073. 54 4, 343. 46 26, 730. 08
Price Increases 7, 225. 21 7, 225. 21 -
Addition of 15%
■and 10% to thé.
materials ■ 18,.118,. 60 18,118. 60
[443]*443Supervision and
overhead 35,762.21 8,072.32 27,689.89
Profit 10,589.36 10,589.36 -
Totals $188, 514. 86 $47, 604. 20 $140, 910. 66>
“I have already mentioned that Professional Realty Corporation disbursed, in connection with the contract under-consideration, the sum of $143,347.79, so that, on the basis of the data contained in this report, it would owe the sum of' $45,167.07, in order to arrive at the total cost of $188,514.86.
“I have not included any profits from the ‘extra’ work: other than the profit in the materials, amounting to $18,118.60'.-Apparently, the plaintiff used very little capital of its own in the electric contract under consideration.
“Before closing, I wish to say to Your Honor that in those computations on which the evidence offered was not complete I attempted to make the computations on the most reasonable bases, in my judgment, for both parties.”

In rendering judgment sustaining the complaint and dismissing the counterclaim, the trial judge stated that:

“By order of July 15, 1955, the court approved the report of Special Master Sparrow, Waymouth & Co. as respects the exact amounts disbursed by the parties in the performance of the contract, which report is hereby made an integral part of our Findings of Fact.
“We conclude from the evidence before us that upon final completion of the work there had been spent the sum of $188,514.86, and that Professional Realty Corporation had disbursed $143,347.79 (see p. 2 of the report of Sparrow, Waymouth & Co.), leaving a difference or balance of $45,167.07 in order to arrive at its total cost.”

Professional appealed to this Court from the judgment ordering it to pay to Parber $45,167.07 and interest thereon, plus $3,000 for attorney’s fees.

The issue in this case stems from the changes made in the work at Professional’s request, as originally agreed upon. The question for decision is the manner in which [444]*444/such additional work should be liquidated. Professional maintains that the manner in which it was liquidated would •compel it to pay twice for the same account. In support of .its contention it alleges that the provisions of clause 8 of the •contract provide a method for liquidating the extra work, and that that was the method which should have been used in determining the value of such work. In incorporating in its judgment the full report of Master Waymouth, the trial court actually compensated the extra work on the basis of the provisions of clause 8 of the contract and also of clause 15 of the “General Conditions.” The contract signed between the parties incorporated in its provisions what is known as “The General Conditions of the Contract for the Construction of Buildings of American Institute of Architects,” but it was provided that in the case of conflict between the contract itself and the “General Conditions” incorporated therein the former would prevail.

Professional maintains that it is ordered to pay twice for the same account because clauses 8 and 15 are incompatible, and that according to the contract clause No. 8 should prevail.

Clause 8 provides as follows:1

“Where materials or equipment are changed with a resulting increase in the cost the amount of the change for materials alone shall be calculated on the difference in what would have been the June 14 cost to the Contractor for the materials and/ or equipment eliminated, and the actual cost at the time of delivery of the materials and/or equipment substituted plus 15% and 10%. If the substituted materials cost less the decrease in the contract price for the materials alone shall be the actual difference in cost as stated above.”

Article 15 of the General Conditions reads as follows:2

“The Owner, without invalidating the Contract, may order extra work or make changes by altering, adding to or deducting [445]*445from the work, the Contract Sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.
“In giving instructions, the Architect shall have authority to make minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the building, but otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order from the Owner signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or change, and no claim for an addition to the contract sum shall be valid unless so ordered.
“The value of any such extra work or change shall be determined in one or more of the following ways:
(a) By estimate and acceptance in a lump sum.
(b) By unit prices named in the contract or subsequently agreed upon.
(c) By cost and percentage or by cost and a fixed fee.
“If none of the above methods is agreed upon, the Contractor, provided he receives an order as above, shall proceed with the work. In such case and also under case (c), he shall keep and present in such form as the Architect may direct, a correct account of the cost, together with vouchers. In any case, the Architect shall certify to the amount, including reasonable allowance for overhead and profit, due to the Contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
85 P.R. 441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farber-electric-plumbing-co-v-professional-realty-corp-prsupreme-1962.