Falcone v. Ragonese

505 B.R. 605
CourtBankruptcy Appellate Panel of the First Circuit
DecidedFebruary 26, 2014
DocketBAP No. MW 13-036; Bankruptcy No. 11-42867-MSH; Adversary No. 11-04138-MSH
StatusPublished
Cited by5 cases

This text of 505 B.R. 605 (Falcone v. Ragonese) is published on Counsel Stack Legal Research, covering Bankruptcy Appellate Panel of the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Falcone v. Ragonese, 505 B.R. 605 (bap1 2014).

Opinion

TESTER, Bankruptcy Judge.

The debtor, Alfio J. Ragonese, appeals from a bankruptcy court judgment excepting a portion of the claim of Richard and Mary Falcone (collectively the “Faleones”) from discharge, pursuant to § 523(a)(2)(A).1 For the reasons set forth below, we AFFIRM the judgment.

BACKGROUND

The facts are undisputed.2 At all times relevant, the Faleones resided in Texas and owned vacation property in Wakefield, New Hampshire. In January 2007, Mrs. Falcone, using a pseudonym, posted an internet solicitation for bids to construct a home on the property. Mr. Ragonese, a Massachusetts resident doing business as RACO Construction Corp. or RACO Development Corp. (collectively “RACO”), responded to the solicitation. In the spring of 2007, after a number of discussions, the Faleones hired him for the project. In March and June 2007, the Faleones paid RACO a total of $60,000.00 to demolish the existing house on their New Hampshire property and to prepare the site for construction. They also supplied Mr. Rago-nese with a set of architectural plans for their new home prepared by the Reitmann Design Group.

On June 15, 2007, Mr. Ragonese presented the Faleones with a document on RACO letterhead which appeared to be a contract for the project (the “June 2007 construction summary”). The June 2007 construction summary was “amateurishly drafted,” with numerous typographical errors. In re Ragonese, 2013 WL 3379537, at *1. For example, the document contained the following window description:

All windows will be Harvey Windows. I am sure you have recognized their name on TV a [sic] one of the largest manufacturers of windows and exterior doors. Their product is clearly high quality as I have always used them and have never had any complaints or problems.

Id. The June 2007 construction summary called for the demolition of the existing structure on the property, site work, and construction of the new home according to the Reitmann plans for $615,000.00. Mr. Falcone signed the document, after making certain handwritten changes, including the addition of items totaling $20,000.00 and the deletion of the requirement that change orders be in writing. Neither the original nor amended construction summary were signed by Mrs. Falcone, Mr. Ragonese, or RACO. Despite the absence of a signed contract, the Faleones paid RACO $100,000.00 on July 26, 2007.

“The project did not proceed smoothly.” Id. at *2. Initially, the town building inspector refused to issue a building permit because the architectural plans were deficient. This resulted in the hiring of a structural engineer to revise the Reitmann plans. The resulting changes to the project increased construction costs. Because [608]*608the parties did not memorialize the changes in a signed writing, there was confusion regarding the changes and who would bear their cost. As fall approached, “there was little visible progress at the building site.” Id.

In September 2007, Mr. Ragonese requested additional money to continue construction. Mr. Falcone responded, “I’ve already paid you $160,000[.00],” which “elicited a lecture by Mr. Ragonese on the intricacies of house building in New Hampshire.” Id. Mr. Falcone told Mr. Ragonese that the house needed to be framed and made weather-tight and the septic system installed prior to the onset of winter. Mr. Ragonese responded that he needed money in order to do this. On September 6, 2007, the Falcones paid RACO another $100,000.00.

On September 23, 2007, Mr. Ragonese called Mr. Falcone, who was in Texas, and requested a $75,000.00 payment to continue work on the house. Mr. Falcone complied on September 25, 2007. Construction of the house continued through October.

On November 2, 2007, Mr. Ragonese called Mr. Falcone, requesting another $100,000.00 payment. The house was not yet weather-tight. On November 9, 2007, the Falcones paid RACO another $100,000.00, bringing the total payments to $435,000.00. However, up to this time, there had never been a formal construction progress schedule, written or verbal, for the Falcones’ project.

In mid-November, Mr. Ragonese again requested more money. Mr. Falcone, concerned about the lack of progress on the job, for the first time asked Ragonese for a construction schedule. “On November 18, 2007, Mr. Ragonese emailed to Mr. Fal-cone an ‘estimated’ construction schedule for the period from November 19 through December 10, 2007.” Id. at *2. The schedule included exterior work on siding, septic, and underground utilities and interior work on rough electrical, HVAC, and rough plumbing. “In the email, Mr. Rago-nese stated that starting November 19, 2007, T will be exclusively on this project.’ He also asked Mr. Falcone for $125,000.00 plus $55,000.00 for certain extras that Mr. Falcone had requested.” Id.

Also in mid-November, the Falcones received a written demand from Ossipee Aggregate Corp., one of RACO’s subcontractors or suppliers, for payment of $31,000.00 for goods or services supplied to their project. Mr. Falcone expressed to Mr. Ragonese his concern that RACO and Mr. Ragonese were not devoting the Fal-cones’ payments exclusively to their project and his fear that Ossipee Aggregate Corp. would place a lien on their property.

In a lengthy email to Mr. Falcone dated November 24, 2007, Mr. Ragonese attempted to justify the project delays. He again asked for more money and stated “all your monies are going on your project.” Id. at *3. In a subsequent email dated November 27, 2007, Gina Ragonese, Mr. Ragonese’s wife and RACO’s bookkeeper, assured the Falcones: “[Y]our house will NOT HAVE ANY LIENS ON IT.” Id. (internal quotations omitted).

On November 30, 2007, the Falcones paid RACO another $100,000.00, bringing the total payments to $535,000.00. On December 19, 2007, Mr. Ragonese sent the Falcones an email updating them on the status of the project and again asking for more money. According to the email, siding, HVAC, interior electric, and plumbing remained incomplete.

On January 4, 2008, Mr. Falcone paid RACO $28,000.00 for certain extras requested by the Falcones. The evidence was unclear whether this amount incorporated the $20,000.00 added by Mr. Falcone [609]*609to the June 2007 construction summary or was in addition to that sum. There was no dispute, however, that the payment was for extra work not contemplated in the original draft of the June 2007 construction summary.

On January 26, 2008, the Ragoneses and Falcones toured the construction project together and discussed the remaining work. Mr. Ragonese sent the Falcones an email a few days later which contained a two-page summary dated January 22, 2008, outlining 18 extra items that Mr. Ragonese claimed were not within the project’s scope as described in the June 2007 construction summary. Mr. Ragonese estimated that the additional cost would be $99,700.00.

At the end of January 2008, Mr. Falcone informed Mr. Ragonese that progress on the project was inadequate, and that he would make no further payments until the project was further along. Mr. Ragonese disagreed, and told the Falcones that he would not continue the project without additional payment.

“The parties were at loggerheads.” Id. The project halted. Mr. Ragonese and RACO never worked on it again. The parties dispute whether the work was 50 percent or 75 percent complete at this time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cassouto-Noff & Co. v. Diamond
D. Massachusetts, 2024
Stewart v. Stewart
592 B.R. 414 (First Circuit, 2018)
Reed v. Zak (In re Zak)
573 B.R. 13 (D. Massachusetts, 2017)
Zutrau v. Zutrau (In re Zutrau)
563 B.R. 431 (First Circuit, 2017)
Sega Auto Sales, Inc. v. Flores (In re Flores)
535 B.R. 468 (D. Massachusetts, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
505 B.R. 605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/falcone-v-ragonese-bap1-2014.