Faith Technologies v. Horizon Construction

CourtSuperior Court of Pennsylvania
DecidedOctober 19, 2017
Docket777 EDA 2017
StatusUnpublished

This text of Faith Technologies v. Horizon Construction (Faith Technologies v. Horizon Construction) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Faith Technologies v. Horizon Construction, (Pa. Ct. App. 2017).

Opinion

J-A23034-17, J-A23035-17, J-A23036-17

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

FAITH TECHNOLOGIES, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : HORIZON CONSTRUCTION GROUP, : INC. AND LIBERTY MUTUAL GROUP, : INC. A/K/A LIBERTY MUTUAL : No. 777 EDA 2017 INSURANCE COMPANY : : Appellants :

Appeal from the Order Entered February 2, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 5097-CV-2016

GEORGE J. HAYDEN, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : FAITH TECHNOLOGIES, INC. AND : CASUALTY COMPANY : : No. 784 EDA 2017 : v. : : : HORIZON CONSTRUCTION GROUP, : INC. AND LIBERTY MUTUAL : GROUP, INC. A/K/A LIBERTY : MUTUAL INSURANCE COMPANY : : Appellants :

Appeal from the Order Entered February 21, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 4689CV-2016 J-A23034-17, J-A23035-17, J-A23036-17

FAITH TECHNOLOGIES, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : CBK LODGE, LP, AND EPT SKI : PROPERTIES, INC. : : No. 785 EDA 2017 Appellants :

Appeal from the Order Entered February 2, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 7162-CV-2016

BEFORE: PANELLA, DUBOW, and FITZGERALD,* JJ

MEMORANDUM BY FITZGERALD, J.: FILED OCTOBER 19, 2017

These three related appeals1 arise from a dispute between several

parties to a construction project. In 777 EDA 2017 and 784 EDA 2017,

Horizon Construction Group, Inc. (“Horizon”) and Liberty Mutual Group, Inc.

(“Liberty Mutual”), appeal from orders overruling their preliminary objections

seeking enforcement of an agreement for alternative dispute resolution. In

785 EDA 2017, CBK Lodge, LP (“CBK”) and EPT, Ski Properties, Inc. (“EPT”),

appeal from an order overruling their preliminary objections to stay a

____________________________________________

* Former Justice specially assigned to the Superior Court. 1 For purposes of disposition, we consolidate these appeals. See Pa.R.A.P. 513 (“where the same question is involved in two or more appeals in different cases, the appellate court may, in its discretion, order them to be argued together in all particulars as if but a single appeal”).

-2- J-A23034-17, J-A23035-17, J-A23036-17

mechanic’s lien action pending the outcome of alternative dispute resolution

proceedings between Horizon and Appellee, Faith Technologies, Inc.

(“Faith”). For the reasons provided below, we (1) affirm in part, reverse in

part, and quash in part in 777 EDA 2017, (2) affirm in 784 EDA 2017, and

(3) quash in 785 EDA 2017.

FACTUAL AND PROCEDURAL HISTORY

1. Horizon Becomes General Contractor On The Construction Project

In October 2013, Horizon entered into a contract with CBK and EPT as

general contractor for the construction of a resort hotel and a waterpark

known as the “Camelback Mountain Resort” (the “Project”). R.R. at 21a-

98a2 (Horizon’s contract with CBK and EPT).

2. Horizon Obtains Payment Bonds From Liberty Mutual

Horizon entered into two payment bonds with Liberty Mutual which

provide that every defined claimant may sue on the payment bonds,

prosecute the suit to final judgment for such sum or sums as may be justly

due claimant, and have execution thereon. The payment bonds state:

No suit or action shall be commenced hereunder by any claimant . . .

Other than in a state court of competent jurisdiction in and for the county or other political subdivision of the state in which the Project, or any party thereof, is situated, or in

2 For the parties’ convenience, we refer to the reproduced record.

-3- J-A23034-17, J-A23035-17, J-A23036-17

the United States District Court for the district in which the Project, or any part thereof, is situated, and not elsewhere.

R.R. at 237a, 246a. The payment bonds do not provide for arbitration of

bond claims. Id. The payment bonds incorporated by reference Horizon’s

contract with CBK and EPT but did not incorporate the subcontract with Faith

discussed below. Id. at 236a, 245a.

3. Horizon Subcontracts Electrical Work To Faith

During 2014, Horizon and Faith entered into two subcontract

agreements for Faith to perform labor and furnish materials for electrical

installation on the hotel and waterpark portions of the Project (“Faith

Subcontracts”). The Faith Subcontracts provide, at Horizon’s option, for

arbitration of any disputes arising out of or relating to the Faith Subcontracts

or Faith’s work on the Project, as follows:

Any dispute or claim between [Faith] and [Horizon] arising out of or relating to this Subcontract or the work shall be decided, at the option of [Horizon], by arbitration in accordance with the latest version of the American Arbitration Association rules for Construction Industry proceedings. Written notice of the demand for arbitration shall be delivered to the American Arbitration Association and the other party in accordance with time limits in the Subcontract and within the time for institution of legal proceedings according to applicable statutes of limitations.

R.R. at 106a.

4. Faith Obtains Payment Bonds From Continental

Faith entered into two payment bonds with its surety, Continental,

which provide that every defined claimant may sue on the payment bonds,

-4- J-A23034-17, J-A23035-17, J-A23036-17

prosecute the suit to final judgment for such sum or sums as may be justly

due claimant, and have execution thereon. The Continental payment bonds

did not provide for arbitration of bond claims. R.R. at 412a-414a.

5. Faith Sub-subcontracts Electrical Work To Hayden

On February 15, 2014, Faith entered into sub-subcontract agreements

with George J. Hayden, Inc. (“Hayden”), a local electrical contractor, for

Hayden to perform electrical installation work in connection with Faith’s

subcontract work on the hotel portion and waterpark portions of the Project

(the “Hayden Sub-subcontracts”). The Hayden Sub-subcontracts provide, at

Faith’s option, for arbitration of any disputes arising out of the Hayden Sub-

subcontracts, as follows:

[Faith], in its sole discretion, may demand arbitration with [Hayden] to resolve any dispute or claim arising under this Agreement. Such arbitration shall be conducted in accordance with the rules of the American Arbitration Association, as applicable to the construction industry.

R.R. at 423a.

6. Disputes Arise During The Project

Disputes arose between Faith and Horizon during the Project. Horizon

claimed that Faith fraudulently modified its labor mark-up to inflate amounts

owed for additional work performed by Faith on the Project. R.R. at 7a-11a

(Faith’s complaint against Horizon). Faith claimed that Horizon failed to pay

Faith for the original scope of the work as well as for additional work it was

required to perform. Id.

-5- J-A23034-17, J-A23035-17, J-A23036-17

Disputes also arose between Faith and Hayden. Hayden alleged that

Faith failed to pay monies that it owed for Hayden’s work and that Faith

constantly interrupted Hayden’s work schedule. Id. at 359a-386a (Hayden’s

complaint against Faith). Faith contended that Horizon was to blame for the

delays as the general contractor for the Project. Id. atb7a-11a (Faith’s

complaint against Horizon).

7. Action I (Faith v. Horizon and Liberty Mutual)

In July 2016, Faith filed a writ of summons against Horizon and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geniviva v. Frisk
725 A.2d 1209 (Supreme Court of Pennsylvania, 1999)
Salvino Steel & Iron Works, Inc. v. Fletcher & Sons, Inc.
580 A.2d 853 (Supreme Court of Pennsylvania, 1990)
Messa v. State Farm Insurance
641 A.2d 1167 (Superior Court of Pennsylvania, 1994)
Cumberland-Perry Area Vocational-Technical School Authority v. Bogar & Bink
396 A.2d 433 (Superior Court of Pennsylvania, 1978)
Pennsy Supply, Inc. v. Mumma
921 A.2d 1184 (Superior Court of Pennsylvania, 2007)
Jacksonian v. Temple University Health System Foundation
862 A.2d 1275 (Superior Court of Pennsylvania, 2004)
Taylor v. Extendicare Health Facilities, Inc.
147 A.3d 490 (Supreme Court of Pennsylvania, 2016)
Fellerman, S. v. PECO Energy Co.
159 A.3d 22 (Superior Court of Pennsylvania, 2017)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Walton v. Johnson
66 A.3d 782 (Superior Court of Pennsylvania, 2013)
Berks Products Corp. v. Arch Insurance Co.
72 A.3d 315 (Commonwealth Court of Pennsylvania, 2013)
Pisano v. Extendicare Homes, Inc.
77 A.3d 651 (Superior Court of Pennsylvania, 2013)
Cardinal v. Kindred Healthcare, Inc.
155 A.3d 46 (Superior Court of Pennsylvania, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Faith Technologies v. Horizon Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/faith-technologies-v-horizon-construction-pasuperct-2017.