Faith Technologies v. Horizon Construction

Superior Court of Pennsylvania·Decided October 19, 2017·No. 777 EDA 2017·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

FAITH TECHNOLOGIES, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

HORIZON CONSTRUCTION GROUP, : INC. AND LIBERTY MUTUAL GROUP, : INC. A/K/A LIBERTY MUTUAL : No. 777 EDA 2017 INSURANCE COMPANY :

:

Appellants :

Appeal from the Order Entered February 2, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 5097-CV-2016

GEORGE J. HAYDEN, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

FAITH TECHNOLOGIES, INC. AND :

CASUALTY COMPANY :

: No. 784 EDA 2017

:

v. :

:

:

HORIZON CONSTRUCTION GROUP, :

INC. AND LIBERTY MUTUAL :

GROUP, INC. A/K/A LIBERTY :

MUTUAL INSURANCE COMPANY :

:

Appellants :

Appeal from the Order Entered February 21, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 4689CV-2016

FAITH TECHNOLOGIES, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

CBK LODGE, LP, AND EPT SKI :

PROPERTIES, INC. :

: No. 785 EDA 2017

Appellants :

Appeal from the Order Entered February 2, 2017 In the Court of Common Pleas of Monroe County Civil Division at No(s): 7162-CV-2016

BEFORE: PANELLA, DUBOW, and FITZGERALD,* JJ MEMORANDUM BY FITZGERALD, J.: FILED OCTOBER 19, 2017 These three related appeals1 arise from a dispute between several parties to a construction project. In 777 EDA 2017 and 784 EDA 2017, Horizon Construction Group, Inc. (“Horizon”) and Liberty Mutual Group, Inc. (“Liberty Mutual”), appeal from orders overruling their preliminary objections seeking enforcement of an agreement for alternative dispute resolution. In 785 EDA 2017, CBK Lodge, LP (“CBK”) and EPT, Ski Properties, Inc. (“EPT”), appeal from an order overruling their preliminary objections to stay a

* Former Justice specially assigned to the Superior Court. 1 For purposes of disposition, we consolidate these appeals. See Pa.R.A.P. 513 (“where the same question is involved in two or more appeals in different cases, the appellate court may, in its discretion, order them to be argued together in all particulars as if but a single appeal”).

mechanic’s lien action pending the outcome of alternative dispute resolution proceedings between Horizon and Appellee, Faith Technologies, Inc. (“Faith”). For the reasons provided below, we (1) affirm in part, reverse in part, and quash in part in 777 EDA 2017, (2) affirm in 784 EDA 2017, and (3) quash in 785 EDA 2017.

FACTUAL AND PROCEDURAL HISTORY

1. Horizon Becomes General Contractor On The Construction Project

In October 2013, Horizon entered into a contract with CBK and EPT as general contractor for the construction of a resort hotel and a waterpark known as the “Camelback Mountain Resort” (the “Project”). R.R. at 21a- 98a2 (Horizon’s contract with CBK and EPT).

2. Horizon Obtains Payment Bonds From Liberty Mutual Horizon entered into two payment bonds with Liberty Mutual which provide that every defined claimant may sue on the payment bonds, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The payment bonds state:

No suit or action shall be commenced hereunder by any claimant . . .

Other than in a state court of competent jurisdiction in and for the county or other political subdivision of the state in which the Project, or any party thereof, is situated, or in

2 For the parties’ convenience, we refer to the reproduced record.

the United States District Court for the district in which the Project, or any part thereof, is situated, and not elsewhere.

R.R. at 237a, 246a. The payment bonds do not provide for arbitration of bond claims. Id. The payment bonds incorporated by reference Horizon’s contract with CBK and EPT but did not incorporate the subcontract with Faith discussed below. Id. at 236a, 245a.

3. Horizon Subcontracts Electrical Work To Faith During 2014, Horizon and Faith entered into two subcontract agreements for Faith to perform labor and furnish materials for electrical installation on the hotel and waterpark portions of the Project (“Faith Subcontracts”). The Faith Subcontracts provide, at Horizon’s option, for arbitration of any disputes arising out of or relating to the Faith Subcontracts or Faith’s work on the Project, as follows:

Any dispute or claim between [Faith] and [Horizon] arising out of or relating to this Subcontract or the work shall be decided, at the option of [Horizon], by arbitration in accordance with the latest version of the American Arbitration Association rules for Construction Industry proceedings. Written notice of the demand for arbitration shall be delivered to the American Arbitration Association and the other party in accordance with time limits in the Subcontract and within the time for institution of legal proceedings according to applicable statutes of limitations.

R.R. at 106a.

4. Faith Obtains Payment Bonds From Continental Faith entered into two payment bonds with its surety, Continental, which provide that every defined claimant may sue on the payment bonds,

prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Continental payment bonds did not provide for arbitration of bond claims. R.R. at 412a-414a.

5. Faith Sub-subcontracts Electrical Work To Hayden On February 15, 2014, Faith entered into sub-subcontract agreements with George J. Hayden, Inc. (“Hayden”), a local electrical contractor, for Hayden to perform electrical installation work in connection with Faith’s subcontract work on the hotel portion and waterpark portions of the Project (the “Hayden Sub-subcontracts”). The Hayden Sub-subcontracts provide, at Faith’s option, for arbitration of any disputes arising out of the Hayden Sub- subcontracts, as follows:

[Faith], in its sole discretion, may demand arbitration with [Hayden] to resolve any dispute or claim arising under this Agreement. Such arbitration shall be conducted in accordance with the rules of the American Arbitration Association, as applicable to the construction industry.

R.R. at 423a.

6. Disputes Arise During The Project Disputes arose between Faith and Horizon during the Project. Horizon claimed that Faith fraudulently modified its labor mark-up to inflate amounts owed for additional work performed by Faith on the Project. R.R. at 7a-11a (Faith’s complaint against Horizon). Faith claimed that Horizon failed to pay Faith for the original scope of the work as well as for additional work it was required to perform. Id.

Disputes also arose between Faith and Hayden. Hayden alleged that Faith failed to pay monies that it owed for Hayden’s work and that Faith constantly interrupted Hayden’s work schedule. Id. at 359a-386a (Hayden’s complaint against Faith). Faith contended that Horizon was to blame for the delays as the general contractor for the Project. Id. atb7a-11a (Faith’s complaint against Horizon).

7. Action I (Faith v. Horizon and Liberty Mutual)

In July 2016, Faith filed a writ of summons against Horizon and Continental at 5097 Civil 2016. Faith subsequently filed a complaint against Horizon and Liberty Mutual. Five counts of the complaint allege claims against Horizon for breach of contract, conversion and violation of the Contractor and Subcontractor Payment Act (“CASPA”), 73 P.S. §§ 501-516. R.R. at 5a-16a. One count alleges a claim against Liberty Mutual for breach of its payment bond. Id. at 14a-15a. In accordance with the arbitration provisions in the Faith Subcontracts, Horizon elected to arbitrate Faith’s claims. Id. at 267a-268a (Horizon’s preliminary objections in Action I). In addition, Liberty Mutual purported to consent to arbitration, despite the lack of an arbitration clause in its payment bonds. Trial Ct. Op. (Action I), 2/2/17, at 4.

8. Action II (Hayden v. Faith and Continental v. Horizon and Liberty Mutual)

In July 2016, Hayden filed a writ of summons against Faith at No.

Free access — add to your briefcase to read the full text and ask questions with AI

Faith Technologies v. Horizon Construction, (Pa. Ct. App. 2017).

Faith Technologies v. Horizon Construction (Faith Technologies v. Horizon Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Geniviva v. Frisk
725 A.2d 1209 (Supreme Court of Pennsylvania, 1999)
Salvino Steel & Iron Works, Inc. v. Fletcher & Sons, Inc.
580 A.2d 853 (Supreme Court of Pennsylvania, 1990)
Messa v. State Farm Insurance
641 A.2d 1167 (Superior Court of Pennsylvania, 1994)
Cumberland-Perry Area Vocational-Technical School Authority v. Bogar & Bink
396 A.2d 433 (Superior Court of Pennsylvania, 1978)
Pennsy Supply, Inc. v. Mumma
921 A.2d 1184 (Superior Court of Pennsylvania, 2007)
Jacksonian v. Temple University Health System Foundation
862 A.2d 1275 (Superior Court of Pennsylvania, 2004)
Taylor v. Extendicare Health Facilities, Inc.
147 A.3d 490 (Supreme Court of Pennsylvania, 2016)
Fellerman, S. v. PECO Energy Co.
159 A.3d 22 (Superior Court of Pennsylvania, 2017)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Walton v. Johnson
66 A.3d 782 (Superior Court of Pennsylvania, 2013)
Berks Products Corp. v. Arch Insurance Co.
72 A.3d 315 (Commonwealth Court of Pennsylvania, 2013)
Pisano v. Extendicare Homes, Inc.
77 A.3d 651 (Superior Court of Pennsylvania, 2013)
Cardinal v. Kindred Healthcare, Inc.
155 A.3d 46 (Superior Court of Pennsylvania, 2017)