Fairmech Industries v. Tisdale Company, Inc.

CourtCourt of Appeals of Texas
DecidedNovember 25, 2015
Docket09-13-00529-CV
StatusPublished

This text of Fairmech Industries v. Tisdale Company, Inc. (Fairmech Industries v. Tisdale Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairmech Industries v. Tisdale Company, Inc., (Tex. Ct. App. 2015).

Opinion

In The

Court of Appeals Ninth District of Texas at Beaumont _________________ NO. 09-13-00529-CV _________________

FAIRMECH INDUSTRIES, Appellant

V.

TISDALE COMPANY, INC., Appellee ________________________________________________________________________

On Appeal from the 284th District Court Montgomery County, Texas Trial Cause No. 98-09-03267-CV ________________________________________________________________________

MEMORANDUM OPINION

This appeal arises out of a suit for breach of contract. Fairmech Industries

sued Tisdale Company, Inc. for breach of contract. The jury found Tisdale failed to

comply with the agreement in which the parties entered, but Tisdale’s failure was

excused. The trial court entered a take nothing judgment. In two issues, Fairmech,

appellant herein, contends the evidence is legally and factually insufficient to

support the jury’s finding that Tisdale’s performance was excused. We affirm the

trial court’s judgment. 1 I. Background

Tisdale assembles heating, ventilation, and air conditioning systems

(“HVAC”) for offshore oil and gas platforms. Jerry Hill, a Tisdale employee,

supervised the assembly of pre-commissioned 1 units and commissioned 2 the

systems on the various offshore platforms. Tisdale contracted to build and install

HVAC units on various platforms for Daewoo and Hyundai, two Korean offshore

ship builders. Tisdale contracted to do two projects for Hyundai (NPQ and NPC)

and two projects for Daewoo (SHW and SHG). The HVAC systems were pre-

commissioned onshore in Korea then sent offshore to the various platforms for the

commissioning work. Pre-commissioning work did not require the use of skilled

laborers, whereas, commissioning work did.

Fairmech sent Tisdale a proposal to provide laborers to commission

Tisdale’s HVAC systems at the Daewoo and Hyundai platforms. Tisdale accepted

1 Pre-commissioning involves inspecting the equipment, the control panels, the water lines, and the welds of the HVAC system to determine whether the system arrived safely. Daewoo and Hyundai employees installed the piping and pulled the wires through the control panel. Pre-commissioning also required inspecting this work to ensure it was done properly. 2 Commissioning requires inspection of the piping, the control panel, the wiring, the HVAC system, and the waterlines. The person commissioning the equipment is required to integrate the HVAC control panel and the chilling equipment so that one system responds to the other. According to the testimony at trial, it takes on average thirty days to properly commission an HVAC system. 2 the terms of Fairmech’s proposal (hereinafter referred to as the “Agreement”).

Under the General Provisions of the Agreement that Fairmech drafted, Fairmech

agreed to provide Tisdale with “competent and skilled technical personnel,

qualified to undertake commissioning work.” Fairmech agreed that the

commissioning team it sent would “carry all necessary tools and other equipment

to accomplish commissioning.” The Agreement indicated that Fairmech’s

commissioning team would work under the direction of Hill or any other

supervisors Tisdale assigned. In paragraph twelve of the General Provisions,

Fairmech agreed that at the end of each day, Fairmech-designated personnel would

present a logbook for verification of time. The Agreement provides that “Tisdale’s

supervisor or any other personnel assigned by Tisdale shall promptly verify the

time and append his signatures.” The payment provision of the Agreement states,

“Payment shall be made within 10 days of presentation by invoices supported by

log-sheets.” The Agreement also established a rate of pay for two levels of

laborers: “Engineer (Qualified Degree Holder)” and “Skilled and Certified

Technical personnel: Mechanical/Electrical/Instrumentation[.]”

At issue in this case are three invoices Fairmech submitted to Tisdale. The

first invoice charged $13,333 for work performed at the Hyundai project, the

second invoice charged $28,180 for work performed at the Daewoo project, and

3 the third invoice charged $13,676 for pre-commissioning work at an unspecified

project. Tisdale did not pay the invoices. Eventually, Fairmech sued Tisdale for

breach of the Agreement seeking to recover the amounts owed and for attorney’s

fees.

Trial was to a jury. In response to Question 1, the breach of contract

question, the jury found Tisdale failed to comply with the Agreement. Having

answered “yes” to Question 1, the jury was instructed to answer Question 2, which

asked whether Tisdale’s failure to comply was excused. The jury was instructed

that “[f]ailure to comply by [Tisdale] is excused by [Fairmech’s] previous failure

to comply with a material obligation of the same agreement.” The jury answered,

“yes[.]” The court accepted the verdict of the jury and based on the jury’s findings,

entered final judgment that Fairmech take nothing by its suit. Fairmech filed a

motion for new trial wherein it argued the evidence was legally and factually

insufficient to support the jury’s answer to Question 2. Fairmech’s motion for new

trial was denied by operation of law. Fairmech timely appealed.

II. Burden of Proof and Standards of Review

The jury found that Tisdale’s failure to comply with the Agreement was

excused by Fairmech’s previous failure to comply with a material obligation of the

Agreement. Fairmech had the burden of proof on its breach of contract claim. See

4 Associated Indem. Corp. v. CAT Contracting, Inc., 964 S.W.2d 276, 283 (Tex.

1998). Tisdale, as the party asserting that it should not be held liable for breach of

contract, had the burden to plead and prove the elements of a prior material breach.

See Compass Bank v. MFP Fin. Servs., Inc., 152 S.W.3d 844, 852 (Tex. App.—

Dallas 2005, pet. denied).

In a legal sufficiency challenge, we examine the record in the light most

favorable to the judgment and consider whether the evidence at trial would enable

a reasonable and fair-minded jury to reach the verdict under review. City of Keller

v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005). When a party challenges the legal

sufficiency of the evidence relative to an adverse finding on which it did not have

the burden of proof, the party must demonstrate that there is no evidence to support

the adverse finding. See Exxon Corp. v. Emerald Oil & Gas Co., L.C., 348 S.W.3d

194, 215 (Tex. 2011). We will sustain a party’s legal sufficiency challenge only if

the record demonstrates that (1) there is a complete absence of evidence of a vital

fact; (2) the court is barred by the rules of law or of evidence from giving weight to

the only evidence offered to prove a vital fact; (3) the evidence to prove a vital fact

is no more than a scintilla; or (4) the evidence established conclusively the

opposite of the vital fact. City of Keller, 168 S.W.3d at 810. The fact finder is the

sole judge of witness credibility and the weight to give witness testimony. Id. at

5 819. We credit favorable evidence if reasonable jurors could, and disregard

contrary evidence unless reasonable jurors could not. Id. at 807, 827.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Exxon Corp. v. Emerald Oil & Gas Co., LC
348 S.W.3d 194 (Texas Supreme Court, 2011)
Compass Bank v. MFP Financial Services, Inc.
152 S.W.3d 844 (Court of Appeals of Texas, 2005)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
Mays v. Pierce
203 S.W.3d 564 (Court of Appeals of Texas, 2006)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
City of Austin v. Chandler
428 S.W.3d 398 (Court of Appeals of Texas, 2014)
Ford Motor Co. v. Castillo
444 S.W.3d 616 (Texas Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Fairmech Industries v. Tisdale Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairmech-industries-v-tisdale-company-inc-texapp-2015.