Fairmech Industries v. Tisdale Company, Inc.

Court of Appeals of Texas·Decided November 25, 2015·No. 09-13-00529-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-13-00529-CV

FAIRMECH INDUSTRIES, Appellant V.

TISDALE COMPANY, INC., Appellee

On Appeal from the 284th District Court Montgomery County, Texas

Trial Cause No. 98-09-03267-CV

MEMORANDUM OPINION

This appeal arises out of a suit for breach of contract. Fairmech Industries sued Tisdale Company, Inc. for breach of contract. The jury found Tisdale failed to comply with the agreement in which the parties entered, but Tisdale’s failure was excused. The trial court entered a take nothing judgment. In two issues, Fairmech, appellant herein, contends the evidence is legally and factually insufficient to support the jury’s finding that Tisdale’s performance was excused. We affirm the trial court’s judgment.

I. Background

Tisdale assembles heating, ventilation, and air conditioning systems (“HVAC”) for offshore oil and gas platforms. Jerry Hill, a Tisdale employee, supervised the assembly of pre-commissioned 1 units and commissioned 2 the systems on the various offshore platforms. Tisdale contracted to build and install HVAC units on various platforms for Daewoo and Hyundai, two Korean offshore ship builders. Tisdale contracted to do two projects for Hyundai (NPQ and NPC) and two projects for Daewoo (SHW and SHG). The HVAC systems were pre- commissioned onshore in Korea then sent offshore to the various platforms for the commissioning work. Pre-commissioning work did not require the use of skilled laborers, whereas, commissioning work did.

Fairmech sent Tisdale a proposal to provide laborers to commission Tisdale’s HVAC systems at the Daewoo and Hyundai platforms. Tisdale accepted

1 Pre-commissioning involves inspecting the equipment, the control panels, the water lines, and the welds of the HVAC system to determine whether the system arrived safely. Daewoo and Hyundai employees installed the piping and pulled the wires through the control panel. Pre-commissioning also required inspecting this work to ensure it was done properly.

2 Commissioning requires inspection of the piping, the control panel, the wiring, the HVAC system, and the waterlines. The person commissioning the equipment is required to integrate the HVAC control panel and the chilling equipment so that one system responds to the other. According to the testimony at trial, it takes on average thirty days to properly commission an HVAC system.

the terms of Fairmech’s proposal (hereinafter referred to as the “Agreement”). Under the General Provisions of the Agreement that Fairmech drafted, Fairmech agreed to provide Tisdale with “competent and skilled technical personnel, qualified to undertake commissioning work.” Fairmech agreed that the commissioning team it sent would “carry all necessary tools and other equipment to accomplish commissioning.” The Agreement indicated that Fairmech’s commissioning team would work under the direction of Hill or any other supervisors Tisdale assigned. In paragraph twelve of the General Provisions, Fairmech agreed that at the end of each day, Fairmech-designated personnel would present a logbook for verification of time. The Agreement provides that “Tisdale’s supervisor or any other personnel assigned by Tisdale shall promptly verify the time and append his signatures.” The payment provision of the Agreement states, “Payment shall be made within 10 days of presentation by invoices supported by log-sheets.” The Agreement also established a rate of pay for two levels of laborers: “Engineer (Qualified Degree Holder)” and “Skilled and Certified Technical personnel: Mechanical/Electrical/Instrumentation[.]”

At issue in this case are three invoices Fairmech submitted to Tisdale. The first invoice charged $13,333 for work performed at the Hyundai project, the second invoice charged $28,180 for work performed at the Daewoo project, and

the third invoice charged $13,676 for pre-commissioning work at an unspecified project. Tisdale did not pay the invoices. Eventually, Fairmech sued Tisdale for breach of the Agreement seeking to recover the amounts owed and for attorney’s fees.

Trial was to a jury. In response to Question 1, the breach of contract question, the jury found Tisdale failed to comply with the Agreement. Having answered “yes” to Question 1, the jury was instructed to answer Question 2, which asked whether Tisdale’s failure to comply was excused. The jury was instructed that “[f]ailure to comply by [Tisdale] is excused by [Fairmech’s] previous failure to comply with a material obligation of the same agreement.” The jury answered, “yes[.]” The court accepted the verdict of the jury and based on the jury’s findings, entered final judgment that Fairmech take nothing by its suit. Fairmech filed a motion for new trial wherein it argued the evidence was legally and factually insufficient to support the jury’s answer to Question 2. Fairmech’s motion for new trial was denied by operation of law. Fairmech timely appealed.

II. Burden of Proof and Standards of Review The jury found that Tisdale’s failure to comply with the Agreement was excused by Fairmech’s previous failure to comply with a material obligation of the Agreement. Fairmech had the burden of proof on its breach of contract claim. See

Associated Indem. Corp. v. CAT Contracting, Inc., 964 S.W.2d 276, 283 (Tex. 1998). Tisdale, as the party asserting that it should not be held liable for breach of contract, had the burden to plead and prove the elements of a prior material breach. See Compass Bank v. MFP Fin. Servs., Inc., 152 S.W.3d 844, 852 (Tex. App.— Dallas 2005, pet. denied).

In a legal sufficiency challenge, we examine the record in the light most favorable to the judgment and consider whether the evidence at trial would enable a reasonable and fair-minded jury to reach the verdict under review. City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005). When a party challenges the legal sufficiency of the evidence relative to an adverse finding on which it did not have the burden of proof, the party must demonstrate that there is no evidence to support the adverse finding. See Exxon Corp. v. Emerald Oil & Gas Co., L.C., 348 S.W.3d 194, 215 (Tex. 2011). We will sustain a party’s legal sufficiency challenge only if the record demonstrates that (1) there is a complete absence of evidence of a vital fact; (2) the court is barred by the rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact; (3) the evidence to prove a vital fact is no more than a scintilla; or (4) the evidence established conclusively the opposite of the vital fact. City of Keller, 168 S.W.3d at 810. The fact finder is the sole judge of witness credibility and the weight to give witness testimony. Id. at

819. We credit favorable evidence if reasonable jurors could, and disregard contrary evidence unless reasonable jurors could not. Id. at 807, 827.

When considering circumstantial evidence that favors the verdict, we review each piece of circumstantial evidence in light of all known circumstances and not in isolation. Ford Motor Co. v. Castillo, 444 S.W.3d 616, 621 (Tex. 2014). If the circumstantial evidence, when viewed in light of all the known circumstances, is equally consistent with either of two facts, then neither fact may be inferred; however, if the circumstantial evidence is not equally consistent with either of two facts, and the jury’s inference is within the “zone of reasonable disagreement,” we cannot substitute our judgment for that of the trier of fact. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Fairmech Industries v. Tisdale Company, Inc., (Tex. Ct. App. 2015).

Fairmech Industries v. Tisdale Company, Inc. (Fairmech Industries v. Tisdale Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Exxon Corp. v. Emerald Oil & Gas Co., LC
348 S.W.3d 194 (Texas Supreme Court, 2011)
Compass Bank v. MFP Financial Services, Inc.
152 S.W.3d 844 (Court of Appeals of Texas, 2005)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
Mays v. Pierce
203 S.W.3d 564 (Court of Appeals of Texas, 2006)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
City of Austin v. Chandler
428 S.W.3d 398 (Court of Appeals of Texas, 2014)
Ford Motor Co. v. Castillo
444 S.W.3d 616 (Texas Supreme Court, 2014)