Fairfield Development, Inc. v. J.D.I. Contractor & Supply, Inc.

782 F. Supp. 2d 1205, 2011 U.S. Dist. LEXIS 34887, 2011 WL 1045285
CourtDistrict Court, D. Colorado
DecidedMarch 18, 2011
DocketCivil Action 08-cv-02792-DME-KMT
StatusPublished
Cited by6 cases

This text of 782 F. Supp. 2d 1205 (Fairfield Development, Inc. v. J.D.I. Contractor & Supply, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairfield Development, Inc. v. J.D.I. Contractor & Supply, Inc., 782 F. Supp. 2d 1205, 2011 U.S. Dist. LEXIS 34887, 2011 WL 1045285 (D. Colo. 2011).

Opinion

ORDER RE PLAINTIFFS’ MOTION TO AMEND AND SUBSTITUTE (DOC. 161), DEFENDANT’S MOTION FOR RELIEF FROM STIPULATION (DOC. 160), AND DEFENDANT’S MOTION FOR JUDGMENT ON THE PLEADINGS, OR IN THE ALTERNATIVE, SUMMARY JUDGMENT (DOC. 159)

DAVID M. EBEL, Circuit Judge.

This matter comes before the court on (1) the motion of plaintiffs Fairfield Development, Inc. d/b/a Fairfield Development LP (“Development”) and Axis Surplus Insurance Company (“Axis”) (together, “Plaintiffs”) to amend the Amended Complaint to remove Development as a party plaintiff and substitute Fairfield Dry Creek Village LP (“Dry Creek”) (Doc. 161); (2) Defendant J.D.I. Contractor & Supply, Inc.’s (“JDI’s”) Motion for Relief from Stipulation (Doc. 160); and (3) JDI’s Motion for Judgment on the Pleadings, or in the Alternative, Summary Judgment (Doc. 159). For the reasons discussed below, the court GRANTS Plaintiffs’ Motion to Amend and Substitute, GRANTS JDI’s Motion for Relief from Stipulation, and DENIES JDI’s Motion for Judgment on the Pleadings, or in the Alternative, Summary Judgment.

I. Background

The following facts are undisputed: Development was the general contractor of an apartment complex development being *1207 constructed on Dry Creek Road in Englewood, Colorado. JDI was the drywall subcontractor on the project. On January 13, 2008, a fire broke out on the third floor of Building Six of the complex. JDI personnel had been working on the third floor of Building Six earlier in the day. The fire caused damage to the development.

Development and its putative property insurer, Axis, brought this action against JDI, alleging negligence and breach of contract. 1 Plaintiffs allege that JDI personnel were the only individuals in Building Six on the day of the fire and that they moved a portable propane heater too close to combustible materials, which caused the fire. JDI denies Plaintiffs’ claims and asserts the affirmative defenses of (1) comparative negligence (negligence per se), (2) comparative negligence (negligence of standard of care), (3) assumption of risk, and (4) comparative negligence of designated non-parties. JDI generally denies that its personnel moved the heaters, and contends that when its personnel arrived at the site on the day of the fire, several propane heaters had already been turned on in the middle of the hallway on the third floor of Building Six. JDI also alleges that the fire could have been caused by other work crews on site or by a propane leak from the connection between the propane tank and the heating unit.

On April 6, 2010, after the close of discovery, the court held a pretrial conference, at which the parties stipulated that Plaintiffs suffered total damages in the amount of $1,750,000. The court set a trial date of December 6, 2010. On December 1, 2010, the court held a Final Pretrial Conference, at which counsel for Plaintiffs informed the court that it had discovered, through discussions with its client, that the owner of the property destroyed by the fire was not Development, but rather another Fairfield entity, now identified as Dry Creek. 2 Following discussion among the parties and the court on how to proceed, this court ultimately vacated the trial date and set forth a briefing schedule for the motions now before it.

II. Analysis

A. Plaintiffs’ Motion to Amend the Amended Complaint to Remove Development and Substitute Dry Creek

“Motions to add or substitute parties are considered motions to amend and therefore must comply with Rule 15(a).” United States ex rel. Ritchie v. Lockheed Martin Corp., 558 F.3d 1161, 1166 (10th Cir.2009). Federal Rule of Civil Procedure 15(a) provides that, except for amendment as a matter of course (which is not relevant here), “a party may amend its pleading only with the opposing party’s written consent or the court’s leave.” Rule 15(a) also provides that “[t]he court should freely give leave when justice so requires.”

“The purpose of [Rule 15(a) ] is to provide litigants the maximum opportunity for each claim to be decided on its merits rather than on procedural niceties.” Minter v. Prime Equip. Co., 451 F.3d 1196, 1204 (10th Cir.2006) (internal quotation *1208 marks omitted). Thus, “district courts may withhold leave to amend only for reasons such as ‘undue delay, bad faith or dilatory motive on the part of the movant, repeated failure to cure deficiencies by amendments previously allowed, undue prejudice to the opposing party by virtue of allowance of the amendment, [or] futility of [the] amendment.’ ” Ritchie, 558 F.3d at 1166 (quoting Foman v. Davis, 371 U.S. 178, 182, 83 S.Ct. 227, 9 L.Ed.2d 222 (1962)); see also Bylin v. Billings, 568 F.3d 1224, 1229 (10th Cir.2009) (“Rule 15 ... was designed to facilitate the amendment of pleadings except where prejudice to the opposing party would result.” (quoting United States v. Hougham, 364 U.S. 310, 316, 81 S.Ct. 13, 5 L.Ed.2d 8 (1960))). “It is settled that the grant of leave to amend the pleadings pursuant to Rule 15(a) is within the discretion of the trial court.” Zenith Radio Corp. v. Hazeltine Research, Inc., 401 U.S. 321, 330, 91 S.Ct. 795, 28 L.Ed.2d 77 (1971).

The Tenth Circuit has recognized similar principles under Federal Rule of Civil Procedure 17(a), which relates to substitution of the real party in interest into an action. Rule 17(a) provides that a court “may not dismiss an action for failure to prosecute in the name of the real party in interest until, after an objection, a reasonable time has been allowed for the real party in interest to ratify, join, or be substituted into the action.” Fed.R.Civ.P. 17(a)(3). “After ratification, joinder, or substitution, the action proceeds as if it had been originally commenced by the real party in interest.” Id. “The purpose of [Rule 17(a) ] is to prevent forfeiture when determination of the proper party to sue is difficult or when an understandable mistake has been made.” Garcia v. Hall, 624 F.2d 150, 151 n. 3 (10th Cir.1980) (internal quotation marks omitted); see also Esposito v. United States, 368 F.3d 1271

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
782 F. Supp. 2d 1205, 2011 U.S. Dist. LEXIS 34887, 2011 WL 1045285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairfield-development-inc-v-jdi-contractor-supply-inc-cod-2011.