Fairbanks, Morse & Co. v. Wills

159 Ill. App. 241, 1910 Ill. App. LEXIS 50
CourtAppellate Court of Illinois
DecidedDecember 1, 1910
StatusPublished

This text of 159 Ill. App. 241 (Fairbanks, Morse & Co. v. Wills) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairbanks, Morse & Co. v. Wills, 159 Ill. App. 241, 1910 Ill. App. LEXIS 50 (Ill. Ct. App. 1910).

Opinion

Mr. Justice Philbrick

delivered the opinion of the court.

This is an action brought by appellant to recover for the contract price of a certain boiler purchased by appellees from appellant. The trial below resulted in a verdict and judgment for the defendants and against the plaintiff for costs; to reverse that judgment this appeal is prosecuted.

There are four questions raised on the record. The first is upon the admission of the evidence under the condition of the pleadings. At the time of the offering of the evidence, the declaration consisted of only the common counts. The only plea filed was the general issue, and with the pleadings in this condition, the cause was heard by the court without a jury.

Upon the hearing appellees offered evidence showing special damages by reason of a failure to deliver the boiler. Appellant insists that this evidence was incompetent under the state of the pleadings at that time and that no evidence of special damages was proper, but that in order to admit such evidence it was necessary to have filed a special plea. The court heard this evidence over objections of appellant, but subject to their objection. After the argument commenced, the question was again raised by motion to exclude , this evidence. The court then held that the evidence was not proper under general issue. Appellee asked leave to file a special plea. During the course of the argument this plea was prepared and upon presentation to the court, before the argument was finished, the court granted leave to file the plea over objection by appellant. Upon the granting of this motion over objection, appellant was given by the court leave either to reopen the cause and submit evidence upon the question of special damages, or to have the cause continued until the next term of court, with permission to appellant at that time to offer any evidence desired. Appellant declined to either offer any evidence or to request a continuance, but elected to stand upon its objections to the filing of this plea.

The second question is that the permission to file the special plea at that time was an abuse of the discretion of the court.

The third question raised is that although there may have been delay in the shipping of the boiler, appellees accepted the boiler at the time of its delivery without, at that time, specifically demanding or claiming any special damage, and that by so doing, although special damage may have been caused, all claim thereto was waived by the acceptance of the boiler without specifically claiming special damages.

The fourth question is whether the contract of purchase required a shipment in thirty days or within a reasonable time.

The evidence in this case discloses that appellees purchased from appellant a sixty-horse-power boiler; that the negotiations therefor consummated in the purchase of the boiler on the twenty-third day of May; that appellees were under a large dredging contract in Bates county, Missouri, for the construction of a dredge ditch; that in order to perform this work it became necessary for appellees to purchase a sixty-horse-power boiler to pump water into the ditch for the purpose of floating the dredge-boat, so that it might proceed with its work; that without sufficient water to float it the dredge-boat could not work.

There was a time limit for the completion of the dredge contract; and appellees contend that under their contract for the purchase of the boiler, it was to be shipped to them within thirty days. This is denied by appellant, who claims there was no time limit when the boiler should be shipped. At the end of thirty days appellees were prepared to proceed with their work upon the dredge contract, but for lack of water the boat could not be floated and for this reason they were unable to continue their work. They remained idle until about the first of the following October. The boiler was shipped to them on September 11th. By reason of the failure to receive the boiler, the dredge-boat was compelled to lie idle at a loss of from one thousand to fifteen hundred dollars per month.

Soon after the purchase of the boiler by appellees, they asked and received from appellant the dimensions and fittings of the boiler. Appellant was informed this information was necessary for use in constructing the foundation for this special boiler, and was furnished by appellant. From about June 15th until September 11th, a continuous correspondence was kept up by appellees concerning the delivery of the boiler; on several occasions they were informed that the boiler would be shipped speedily, and without further delay; on other occasions they were informed that the boiler had been shipped, and would be received within a few days, and'upon the continual assurance by appellant that the boiler would be delivered without further delay, and would be received in due time by appellees, they continued to wait for its shipment. Their labor hire alone during the time they were waiting for this boiler amounted to five hundred dollars per month.

That the boiler was not shipped within thirty days is not questioned and upon the contention of appellant that there was no specific time when the delivery should be made, conceding there was no time limit, the law implies an agreement to ship within a reasonable time. Before the expiration of the thirty days, appellant informed appellees it would be shipped within a day or two, thereby conceding that thirty days was a reasonable time within which to prepare the boiler for shipment, and no evidence was offered, and no suggestion or claim made, that thirty days was net a sufficient time within which to build and ship the boiler.

Appellant insists, however, that there is no direct evidence that the delay was unreasonable, that no witness testified thereto. It was unnecessary that any witness should specifically state such fact; it was a question to be determined from all the evidence and from all the facts concerning the case, whether it was shipped within a reasonable time, and the trial court found that it was not, and it was fully warranted in making such finding. There can be no question from this record, that the boiler was not shipped within a reasonable time, neither can there be any question about appellees having been damaged far in excess of the purchase price of the boiler.

The record further discloses, from the correspondence had between appellees and appellant, that appellees were continually claiming that they were being damaged beyond recompense by the unusual and extraordinary delay in delivering the boiler and appellant does not contend or suggest that they have been, at any time, surprised at this claim for damages, or that it was a new matter to them; it is very evident from this record that they were expecting such a claim would be made.

Under the Statute of Amendments and Jeofails it was not error for the court to permit the special plea to be filed at the time such leave was granted, and the court fully offered to protect all rights of appellant, by reopening the cause or continuing it, at its request, both of which were declined by appellant, and conceding it was a question of discretion there was no abuse of discretion in permitting this plea to be filed at that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooke v. Preble
80 Ill. 381 (Illinois Supreme Court, 1875)
Ramsey v. Tully
12 Ill. App. 463 (Appellate Court of Illinois, 1883)
Mayer v. C. H. Mitchell & Co.
59 Ill. App. 26 (Appellate Court of Illinois, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
159 Ill. App. 241, 1910 Ill. App. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairbanks-morse-co-v-wills-illappct-1910.