Fagan v. Gnade

61 S.W.3d 76, 2001 Tex. App. LEXIS 6469, 2001 WL 1107956
CourtCourt of Appeals of Texas
DecidedSeptember 19, 2001
DocketNos. 10-01-068-CV, 10-01-117-CV
StatusPublished

This text of 61 S.W.3d 76 (Fagan v. Gnade) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fagan v. Gnade, 61 S.W.3d 76, 2001 Tex. App. LEXIS 6469, 2001 WL 1107956 (Tex. Ct. App. 2001).

Opinion

DAVIS, Chief Justice.

OPINION

Appellees1 filed suit against Texas Department of Transportation employees Rondell Fagan, Oscar Chavez, John Ward (collectively, “Appellants”) and others for injuries and fatalities suffered as a result of vehicular accidents which occurred in a construction zone along an interstate highway. Appellants filed a motion for summary judgment premised on official immunity. They appeal the court’s denial of their summary judgment motion. See Tex. Civ. PRAC. & Rem.Code Ann. § 51.014(a)(5) (Vernon Supp.2001). They claim in two issues that they established official immunity as a matter of law because: (1) the acts of which Appellees complain were acts of governmental discretion; and (2) the complained-of acts were performed in good faith.

BACKGROUND2

The Project

In 1997, Texas Department of Transportation (“TxDOT”) engineers developed plans for “pavement rehabilitation and shoulder repair” to a 5-mile segment of Interstate Highway 35W in northern Tar-rant County from U.S. Highway 287 to the Denton County line. The original plans called for the contractor to mill the “one [78]*78course surface treatment” from the shoulders.3 The contractor would then scarify the underlying flexible base to a depth of 101 millimeters;4 recompact the flexible base with additional materials; replace the milled one course surface treatment; and apply a 50-millimeter-deep layer of asphalt across the traffic lanes and shoulders.5 A cross-section of the original plans appears as follows:

[[Image here]]

The original plans also included traffic safety proposals to be employed during the course of the project. The original plans called for a 1.219-meter-wide “buffer zone” on the shoulder-side of the traffic lane in areas where the contractor removed surface materials from the shoulder to depths of between 50 and 600 millimeters.6 The contractor was to mark off the buffer zone with 100-millimeter-wide white or yellow pavement marking (stripes) and orange- and white-striped plastic barrels with warning lights atop. A schematic of these safety proposals appears as follows:

[79]*79[[Image here]]

The local TxDOT engineer who drew up the plans forwarded them through the area, district, and state offices for administrative approval. This administrative review resulted in three pertinent modifications to the original plans: (1) a narrowing of the proposed “buffer zone” from 1.219 to 0.620 meters accompanied by a requirement that the contractor “shoulder up” against the pavement edge at the end of each day, which would allow the use of vertical panels as warning devices and create a wider traffic lane;7 (2) a requirement that the contractor work on only one side of the highway at a time; and (3) a requirement that the contractor replace the one course surface treatment on the finished flexible base shoulder before detouring traffic to the lane adjacent to the shoulder.8 The engineer who drafted the original plans incorporated these modifications as recommended. He included the first modification in Sheet 14 of the plans. The latter two appear in Sheet 3D. A schematic of the modified safety proposals in Sheet 14 appears as follows:

TxDOT executed a contract with Champagne-Webber, Inc. (“C-W”) to implement these plans. C-W engaged Dustrol, Inc. as a subcontractor to mill the shoulder surfaces. Dustrol began milling the shoulder surfaces on April 23, 1998. Dustrol began with the inside (median) shoulder on [80]*80the southbound-side of the interstate, removing the one course surface treatment to a depth of approximately ½ inch (12.7 millimeters). On April 24, Dustrol completed the milling of the inside, southbound shoulder and began milling the outside, southbound shoulder.

In one area of this outside shoulder, Dustrol removed asphalt to a depth of about 4 inches (101.6 millimeters) for a length of 800 feet near Park Glen Boulevard.9 Before commencing the milling of this portion of the shoulder, Hidalgo discussed some safety concerns with TxDOT inspector John Ward and C-W project superintendent Tim Champagne. Hidalgo asked whether they should shoulder-up this segment of the shoulder. Ward told Hidalgo that this was unnecessary. Champagne told Hidalgo he would place warning signs and cones along this drop-off. Champagne directed Hidalgo not to shoulder-up this section of the roadway. Dissatisfied with this response, Hidalgo discussed the matter with his Dustrol supervisor. The supervisor advised Hidalgo to make sure that the warning signs were set out and that there was “some form of delineation” to indicate the location of the drop-off.

According to Hidalgo, C-W placed warning signs and cones along the shoulder before this milling took place. The 4-inch drop-off near Park Glen Boulevard remained for “five [or] six days.” At that point, Dustrol milled 2 inches (50.8 millimeters) of asphalt from the surface of the adjoining southbound traffic lane, reducing the shoulder drop-off to 2 inches (50.8 millimeters).

Hidalgo encountered a similar situation (4-inch depth) along a 100-foot section of the inside, northbound shoulder near Westport Parkway. C-W placed warning signs and cones along the shoulder before Dustrol milled this portion of the shoulder as well. So long as Hidalgo was involved in the milling operation, the 4-inch drop-off remained along this portion of the interstate.

At some point in late April 1998, acting District Engineer Rondell Fagan discovered that the contract price for the project was $1.2 million less than the funds available for the project. He sought to determine whether these unallocated funds were available to add an additional layer of asphalt across the traffic lanes and shoulders. Fagan contacted Assistant Area Engineer Oscar Chavez, who was the engineer in charge of the project. When Chavez reviewed the plans and Fagan’s proposal, he discovered that the quantity of materials needed to complete the original contract had been substantially underestimated. The cost of the necessary additional materials was about $1.2 million.

At about the same time, Fagan reviewed the plans and decided that they were not designed as he had envisioned. He directed Chavez to implement a second change in the project which would require the contractor to remove 50 millimeters of the flexible base from the shoulders and replace it with asphalt, rather than scarifying and reworking the flexible base. Fa-gan testified that he made this change in an effort to inhibit water infiltration into the joints between the concrete traffic lanes and the shoulders, thus retarding deterioration of both.10

[81]*81Before directing Chavez to prepare the necessary paperwork to implement these modifications, Fagan contacted TxDOT’s Executive Director Charles Wesley Heald on or about April 30 to obtain verbal approval for the proposed modifications.11 Heald gave verbal approval to Fagan’s proposals.

According to Chavez, Fagan then instructed him to direct C-W to begin implementation of the proposed modifications. Chavez passed this directive along to C-W project manager Carl Kortes on May 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fletcher v. Edwards
26 S.W.3d 66 (Court of Appeals of Texas, 2000)
Rucker v. Bank One Texas, N.A.
36 S.W.3d 649 (Court of Appeals of Texas, 2000)
City of Dallas v. Mitchell
870 S.W.2d 21 (Texas Supreme Court, 1994)
State v. Miguel
2 S.W.3d 249 (Texas Supreme Court, 1999)
State v. Terrell
588 S.W.2d 784 (Texas Supreme Court, 1979)
Russell v. Texas Department of Human Resources
746 S.W.2d 510 (Court of Appeals of Texas, 1988)
City of Lancaster v. Chambers
883 S.W.2d 650 (Texas Supreme Court, 1994)
Mitchell v. City of Dallas
855 S.W.2d 741 (Court of Appeals of Texas, 1993)
Kassen v. Hatley
887 S.W.2d 4 (Texas Supreme Court, 1994)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
University of Houston v. Clark
38 S.W.3d 578 (Texas Supreme Court, 2000)
Coleman v. Cintas Sales Corp.
40 S.W.3d 544 (Court of Appeals of Texas, 2001)
MacIas v. Rylander
40 S.W.3d 679 (Court of Appeals of Texas, 2001)
American Tobacco Co., Inc. v. Grinnell
951 S.W.2d 420 (Texas Supreme Court, 1997)
Albright v. Texas Department of Human Services
859 S.W.2d 575 (Court of Appeals of Texas, 1993)
McClure v. Reed
997 S.W.2d 753 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
61 S.W.3d 76, 2001 Tex. App. LEXIS 6469, 2001 WL 1107956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fagan-v-gnade-texapp-2001.