This text of 109 N.Y.S. 740 (Fagan Iron Works v. Dawson Realty Co.) is published on Counsel Stack Legal Research, covering Appellate Terms of the Supreme Court of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fagan Iron Works v. Dawson Realty Co., 109 N.Y.S. 740 (N.Y. Ct. App. 1908).

Opinion

PER CURIAM.

The facts are substantially as follows, viz.: Defendant was erecting five houses on its premises at Wales avenue and 155th street, and it entered into a written contract with the Municipal Iron Works, a corporation, for the erection of the architectural and ornamental iron work. In order to carry into effect this contract the Municipal Iron Works ordered from plaintiff nine iron columns, a part of the iron necessary for the completion of the contract. These nine columns were duly delivered at the premises, and three of them actually put into the building. The Municipal Iron Works failed to pay for six columns, and finally, being unable to pay for the same, authorized plaintiff to take back the six columns. Plaintiff gave defendant an option to pay plaintiff for the columns, which defendant refused to do, and also refused to allow plaintiff to take away the columns. Plaintiff brought this action in replevin, and obtained judgment in its favor. Defendant appeals.

Replevin is a possessory action, and in order to maintain the action plaintiff must have title to and right to possession of the chattels. In the case at bar plaintiff conveyed title to the Municipal Iron Works, but the latter attempted thereafter to reinvest plaintiff with title by authorizing plaintiff to take back the chattels. The evidence, however, shows that the Municipal Iron Works had previously divested itself of title by virtue of its contract with defendant, and could not reinvest plaintiff with title to the chattels. By its contract with defendant the Municipal Iron Works were to furnish certain iron to be paid for at different stages of the work. The iron in question was so furnished by the Municipal Iron Works, which had received therefor more than it was entitled to receive at that stage of the construction, including the iron in suit. Inasmuch as the testimony herein shows that the plaintiff has lost title to the chattels, this action in replevin cannot be maintained, and the judgment must be reversed. As there is a possibility, however, that plaintiff, upon another trial, may present testimony tending to show a somewhat different state of facts, a new trial will be granted.

Judgment reversed, and new trial granted, with costs to appellant to abide the event.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
109 N.Y.S. 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fagan-iron-works-v-dawson-realty-co-nyappterm-1908.