Fabrizi Recycling, Inc. v. Cleveland

2022 Ohio 1395
CourtOhio Court of Appeals
DecidedApril 28, 2022
Docket110548
StatusPublished
Cited by1 cases

This text of 2022 Ohio 1395 (Fabrizi Recycling, Inc. v. Cleveland) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fabrizi Recycling, Inc. v. Cleveland, 2022 Ohio 1395 (Ohio Ct. App. 2022).

Opinion

[Cite as Fabrizi Recycling, Inc. v. Cleveland, 2022-Ohio-1395.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

FABRIZI RECYCLING, INC., :

Plaintiff-Appellee, : No. 110548 v. :

CITY OF CLEVELAND, :

Defendant-Appellant. :

JOURNAL ENTRY AND OPINION

JUDGMENT: VACATED AND REMANDED RELEASED AND JOURNALIZED: April 28, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-21-945381

Appearances:

Frantz Ward LLP and Nora E. Loftus; Audra J. Zarlenga, for appellee.

Mark Griffin, Cleveland Director Law, Craig J. Morice and Amy K. Hough, Assistant Directors of Law, for appellant.

LISA B. FORBES, J.:

The city of Cleveland (“Cleveland”) appeals from the trial court’s

judgment granting Fabrizi Recycling, Inc.’s (“Fabrizi”) request for declaratory

judgment and injunctive relief. After reviewing the facts of the case and pertinent law, we vacate the lower court’s judgment and order that the complaint be dismissed

for lack of subject-matter jurisdiction unless all necessary parties are joined.

I. Facts and Procedural History

In November 2020, Cleveland solicited contractors to submit bids for

two construction projects (the “Cleveland Project” and the “Parma Project”;

collectively, the “Projects”). The solicitations called for bidders to use their “best

efforts” to ensure that at least 30 percent of the Projects were performed by entities

certified as Cleveland Area Small Businesses, Minority Business Enterprises, or

Female Business Enterprises (collectively “CASB”) under Cleveland Codified

Ordinances (“C.C.O.”) 187.03.

Fabrizi and another contractor, the Vallejo Company (“Vallejo”),

submitted bids for the Projects. It was later determined that Fabrizi’s bids were the

lowest bids for each Project. Fabrizi’s bids identified Sydby Enterprises, L.L.C.,

(“Sydby”) as a subcontractor providing “Hauling/Deliveries,” “Pipe/Fittings,” and

“Hydrants/Valves.” Sydby is a certified CASB subcontractor under C.C.O. 187.03.

Sydby’s subcontract value amounted to at least 30 percent of Fabrizi’s respective

bids for the Projects.

According to C.C.O. 185.01, Cleveland shall award public contracts

“only to the lowest responsible bidder.” Furthermore, pursuant to C.C.O. 185.12,

Cleveland

shall reserve the right to reject any or all bids, and any part of any bid, and also the right to waive any informalities in the bid. In awarding a contract, [Cleveland] shall reserve the right to consider all elements entering into the question of determining the responsibility of the bidder. Any bid which is incomplete, conditional, obscure or which contains additions not called for or irregularities of any kind, may be cause for rejection of such bid.

On January 29, 2021, Cleveland allegedly approved Vallejo’s bid for

the Parma Project, which was allegedly higher than Fabrizi’s bid, and authorized

entering into a contract with Vallejo.

On February 10, 2021, Cleveland notified Fabrizi that its bids

regarding the Projects were “non-responsive.” Specifically, Cleveland determined

that Sydby was not certified to provide “Pipe, Fittings, Hydrants and Materials,” and

declined to give Fabrizi credit for Sydby as a subcontractor.

On March 12, 2021, Cleveland allegedly approved Vallejo’s bid for the

Cleveland Project, which was allegedly higher than Fabrizi’s bid, and authorized

On March 22, 2021, Fabrizi filed a complaint against Cleveland

requesting declaratory judgment and injunctive relief. It is undisputed that Vallejo

was not named as a party to these proceedings.

Fabrizi’s first claim requests that the trial court declare that Cleveland

violated C.C.O. 185.01 and 187.01, improperly rejected Fabrizi’s bids for the projects,

and unlawfully awarded both contracts to Vallejo. Fabrizi further requested the

court to declare that the Vallejo contracts were void ab initio.

Fabrizi’s second claim requests that the court issue a “temporary,

preliminary, and permanent mandatory injunction” to enjoin Cleveland from:

“entering into contracts with Vallejo for the Projects”; “authorizing Vallejo to perform any work on the Projects”; “issuing a notice to proceed to Vallejo on either

Project”; and “making any payment to Vallejo for work performed on the Projects.”

Fabrizi also requested that the court “issue an Order awarding the contracts to

Fabrizi.”

That same day, the court issued an ex parte temporary restraining

order (“TRO”) in favor of Fabrizi prohibiting Cleveland from entering into contracts

and doing business with Vallejo regarding the Projects.

The court held a combined hearing and a trial on the merits, via

Zoom, on Fabrizi’s complaint on April 21, 2021, and April 23, 2021. At the close of

the case, the court ordered the parties to submit proposed findings of fact and

conclusions of law, which the parties did on April 30, 2021.

On May 6, 2021, the court issued a journal entry, which mirrored

Fabrizi’s findings of fact and conclusions of law, and granted Fabrizi’s requests for

preliminary and permanent injunction, as well as declaratory relief. Specifically, the

court stated as follows:

The Court finds by clear and convincing evidence that [Cleveland’s] rejection of Fabrizi’s initial bids in both [Projects] was an abuse of discretion.

* * * Cleveland is permanently enjoined and restrained from granting the [Projects] to any contractor, person, or entity other than Fabrizi * * *.

The Court declares any contracts for the [Projects] between [Cleveland] and The Vallejo Group or any other contractor beside Fabrizi are void ab initio.

* * * Cleveland is directed to award the contracts for the [Projects] to Fabrizi * * * under the terms of its initial bids. It is from this order that Cleveland appeals, raising the following three

assignments of error for our review:

The trial court erred in its opinion and order as it is predicated upon insufficient evidence.

The trial court erred in its opinion and order as it was against the manifest weight of the evidence.

The trial court erred as a matter of fact and law in its ordering the city to award both contracts at issue to [Fabrizi], said order constituting an abuse of discretion under controlling Ohio precedent.

After oral argument, this court sua sponte ordered the parties,

pursuant to State v. Tate, 140 Ohio St.3d 442, 2014-Ohio-3667, ¶ 21, to file briefs

regarding the following issue:

Whether the trial court had the authority to declare that “any contracts for the [Projects] between the City and The Vallejo Group or any other contractor beside Fabrizi are void ab initio,” taking into consideration: * * * R.C. 2721.12(A) * * * and Portage Cty. Bd. of Commrs. v. Akron, 109 Ohio St.3d 106, 2006-Ohio-954, 846 N.E.2d 478, ¶ 99 * * *.

II. Standard of Review

A. Competitive Bidding Litigation — Abuse of Discretion

The legislative intent behind requiring competitive bidding of

government entity contracts is “to provide for open and honest competition in

bidding for public contracts and to save the public harmless, as well as bidders

themselves, from any kind of favoritism or fraud in its varied forms.” Chillicothe Bd.

of Edn. v. Sever-Williams Co., 22 Ohio St.2d 107, 115,

Related

M.F. v. Cuyahoga Cty. Div. of Children & Families
2024 Ohio 3306 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 1395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fabrizi-recycling-inc-v-cleveland-ohioctapp-2022.