Fabich v. Ppl Montana

2007 MT 258
CourtMontana Supreme Court
DecidedOctober 9, 2007
Docket06-0315
StatusPublished
Cited by9 cases

This text of 2007 MT 258 (Fabich v. Ppl Montana) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fabich v. Ppl Montana, 2007 MT 258 (Mo. 2007).

Opinion

DA 06-0315

IN THE SUPREME COURT OF THE STATE OF MONTANA 2007 MT 258

DANIEL J. FABICH,

Plaintiff and Appellant,

v.

PPL MONTANA, LLC a Delaware Company and JOHN DOES I through 10,

Defendant and Appellees.

APPEAL FROM: District Court of the Third Judicial District, In and For the County of Anaconda-Deer Lodge, Cause No. DV-03-92 Honorable Ted L. Mizner, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Patrick T. Gallagher; Skakles & Gallagher, Anaconda, Montana

Robert G. McCarthy; McCarthy Law Firm, Butte, Montana

For Appellees:

Robert L. Sterup; Holland & Hart, Billings, Montana

Submitted on Briefs: January 31, 2007

Decided: October 9, 2007

Filed:

__________________________________________ Clerk Chief Justice Karla M. Gray delivered the Opinion of the Court.

¶1 Daniel Fabich filed this action seeking damages for injuries he suffered when he fell

from scaffolding. The Third Judicial District Court, Anaconda-Deer Lodge County, granted

summary judgment for PPL Montana, LLC (PPL). Fabich appeals. We affirm.

¶2 We restate the issues as follows:

¶3 1. Was summary judgment premature because discovery had not been completed?

¶4 2. Did the District Court correctly interpret the Montana Scaffolding Act?

¶5 3. Did the District Court correctly apply Montana law concerning liability for

negligence?

¶6 4. Do genuine issues of material fact preclude summary judgment?

BACKGROUND

¶7 Daniel Fabich was employed as a boilermaker by Power Maintenance Resources, Inc.

(PMRI), which contracted to perform maintenance work at PPL’s Colstrip, Montana, power

plant. On June 14, 2000, Fabich was working inside a scrubber vessel which he and other

members of a PMRI crew were relining with steel plates. In performing the work, PMRI’s

crew was using scaffolding erected by other PMRI employees. While Fabich was climbing

the scaffolding inside the scrubber vessel, his foot and hand slipped off the rungs of the

scaffolding. He fell approximately 25 feet to the floor. Fabich fractured his ankle, back and

wrist. After the accident, PMRI issued Fabich a safety violation citation for climbing with

materials in his hands when buckets and ropes were available—and should have been used—

for hauling materials up the scaffolding. 2 ¶8 In June of 2003, Fabich filed this negligence suit against PPL and John Does 1

through 10—unknown owners, builders, contractors or subcontractors who allegedly erected,

provided, installed or otherwise were responsible for the scaffolding or its condition. In

October of 2005, PPL moved for summary judgment pursuant to M. R. Civ. P. 56. The

following March, after briefing and oral argument, the District Court granted PPL’s motion

for summary judgment. Fabich appeals.

STANDARD OF REVIEW

¶9 Summary judgment is proper under M. R. Civ. P. 56(c), if “the pleadings

depositions, answers to interrogatories, and admissions on file, together with the affidavits, if

any, show that there is no genuine issue as to any material fact and that the moving party is

entitled to a judgment as a matter of law.” We review a summary judgment ruling de novo.

Cole v. Valley Ice Garden, L.L.C., 2005 MT 115, ¶ 4, 327 Mont. 99, ¶ 4, 113 P.3d 275, ¶ 4.

ISSUE 1

¶10 Was summary judgment premature because discovery had not been completed?

¶11 Fabich contends summary judgment was premature because PPL failed to identify its

safety people in its discovery responses. He contends the District Court erred in “not

allowing” him to depose PPL’s “undisclosed safety persons” before granting summary

judgment. The record does not support Fabich’s contentions.

¶12 Fabich filed this action in June of 2003. In an August of 2005 deposition, a PMRI

supervisor stated PPL did not routinely check safety, but that a PMRI employee checked the

3 scaffolding on a daily basis. PPL filed its motion for summary judgment on October 5, 2005.

¶13 Fabich did not make his first written discovery requests of PPL until October 27,

2005—over two years and four months after he filed this action, nine months after the

District Court issued its scheduling order including a discovery deadline of December 30,

2005, and more than three weeks after PPL moved for summary judgment. In the discovery

requests, Fabich asked for the names of persons with knowledge of the operating condition

and safety features of the scaffolding involved in his accident, the names of persons who

inspected the scaffolding, the name and address of the owner of the scaffolding, a description

of the scaffolding, and whether PPL had conducted an investigation of the circumstances of

the accident. The gist of PPL’s answers—provided on December 16, 2005—was that PPL

was unaware of any PPL safety person who had inspected the scaffolding or work site and

that PMRI, not PPL, was responsible for supplying, erecting, inspecting, maintaining,

moving and cleaning the scaffolding.

¶14 On December 29, 2005, Fabich moved to extend the discovery deadline of December

30, 2005, on grounds that PPL had not provided names of its safety employees, whom Fabich

wanted to depose. The court ordered all deadlines and further briefing suspended pending its

ruling on PPL’s motion for summary judgment. After a hearing in January of 2006, the court

granted summary judgment to PPL.

¶15 Fabich has not established an entitlement to additional discovery. He moved to extend

the discovery deadline, but not the scheduled summary judgment hearing. More importantly,

Fabich did not meet the requirements for continuing a summary judgment proceeding on

4 grounds that further discovery was necessary. M. R. Civ. P. 56(f) provides:

Should it appear from the affidavits of a party opposing [a motion for summary judgment] that the party cannot for reasons stated present by affidavit facts essential to justify the party’s opposition, the court may refuse the application for judgment or may order a continuance to permit affidavits to be obtained or depositions to be taken or discovery to be had or may make such other order as is just.

Fabich did not file a Rule 56(f) affidavit at any time.

¶16 On this record, we hold summary judgment was not premature.

ISSUE 2

¶17 Did the District Court correctly interpret the Montana Scaffolding Act?

¶18 The District Court concluded that the Montana Scaffolding Act (Act), by its terms, did

not apply to PPL. Fabich asserts error.

¶19 The Act provides:

[A] contractor, subcontractor, or builder who uses or constructs a scaffold on a construction site is liable for damages sustained by any person who uses the scaffold [subject to comparative negligence principles and excluding a fellow employee or an immediate employer] when the damages are caused by negligence of the contractor, subcontractor, or builder in the use or construction of the scaffold.

Section 50-77-101(3), MCA. Fabich appears to contend that, as the “builder” of the lining in

the scrubber vessel, PPL is liable for his damages. This contention merits little discussion.

¶20 The record before us is clear that PPL neither used nor constructed the scaffolding at

issue. Fabich’s PMRI supervisor stated via affidavit that PMRI carpenter crews erected and

maintained the scaffolding and moved it as required. On this record, we conclude PPL is not

a “contractor, subcontractor, or builder” which “use[d] or construct[ed] the scaffold.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steichen v. Talcott Properties, LLC
2013 MT 2 (Montana Supreme Court, 2013)
Slack v. Landmark Company
2011 MT 292 (Montana Supreme Court, 2011)
Paull v. Park County
2009 MT 321 (Montana Supreme Court, 2009)
Runstrom v. Allen
2008 MT 281 (Montana Supreme Court, 2008)
Peterson v. Eichhorn
2008 MT 250 (Montana Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 MT 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fabich-v-ppl-montana-mont-2007.