Fabian v. Lammers

84 P. 432, 3 Cal. App. 109, 1906 Cal. App. LEXIS 201
CourtCalifornia Court of Appeal
DecidedFebruary 15, 1906
DocketCiv. No. 161.
StatusPublished
Cited by6 cases

This text of 84 P. 432 (Fabian v. Lammers) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fabian v. Lammers, 84 P. 432, 3 Cal. App. 109, 1906 Cal. App. LEXIS 201 (Cal. Ct. App. 1906).

Opinion

*110 BUCKLES, J.

The parties to this action were, on March 4, 1898, owners of adjoining tracts of swamp and overflowed lands in San Joaquin county. It was understood and agreed by all said parties that all of their said lands could and would be most effectually and advantageously reclaimed and protected by a system of levees which would include both the lands of plaintiff and defendant, and in consideration thereof, and for their mutual advantage and for the benefit and reclaiming of said lands of both parties, on March 4, 1898, entered into a written contract, wherein each agreed that he would at his own expense build a suitable levee on his own land on a line designated and described, connecting with levees on the other’s land so as to protect the lands of all the parties then intended to be reclaimed, and each to keep his own levee in repair. The respective levees to be completed by December 1, 1898. After this contract had been duly signed by all the parties and on June 8, 1898, the same parties in modification of the aforesaid contract of March 4th, made and entered into a further and additional written contract, so as to change certain parts and portions of the levees described in the contract of March 4, 1898, to be constructed by each of the parties thereto, so that other lands would be embraced within said reclamation, and all to be completed by December 1, 1898. This latter contract contained a clause that it should not be binding upon either party to it unless Antoinette Naglee Burke should enter into a written contract with plaintiffs granting to them and the said Lammers the right to construct said levees over her lands. Antoinette Naglee Burke did enter into such written contract with plaintiffs. The complaint alleges that defendant failed to construct a part of the levee on his land he had by said written contract agreed to construct, and thereafter the plaintiffs built and completed his said levee at a cost to them of $5,022.22, and that payment was demanded January 20, 1900. The action was brought to recover from defendant the $5,022.22 as damages sustained by plaintiffs by reason of defendant’s failure to build his levee. A general demurrer was interposed and overruled. Defendant answered, denying the allegations of the complaint and plead that ‘‘ said cause of action is barred by the provisions of section 337 of the Code of Civil Procedure, the provisions of subdivision 2 of section 388, and subdivision 1, section 339, *111 all of the Code of Civil Procedure.” The case was tried by a jury, which found for plaintiff in the sum of $4,000, and judgment was entered for that sum. The appeal is from the judgment and order denying a motion for a new trial. Appellant and respondent agree that the only point in the case for this court to determine is as to whether plaintiffs’ action was barred by the statute of limitations. The action was commenced September 30, 1902. The defendant Lammers failed to build his levee and plaintiffs, after demanding that he build it, and his further neglect to do so, built such levee on defendant’s land as he had agreed to build. There is nothing in either the contract of March 4th or of June 8th providing that if one party should fail to build the levee he agreed to, the other party should do so. The contract is silent as to that. Plaintiff claims that this is a suit for damages for a breach of the contract on the part of the defendant in not building his levee as he had agreed to. If this can be treated as an action for damages for breach of contract, then it is upon the written contracts and is brought within four years of the time that the work was completed, to wit, December 1, 1898. As we understand the contract, the lands of neither would be reclaimed unless the levee should be built on the lands of both, as set forth in the contracts. Plaintiffs completed the levee on their lands, but such levee would not reclaim the land or keep the floods back unless the levee was completed on defendant’s land to connect with the levee on plaintiffs’ land. Had the floods come after December 1st, and after plaintiffs had completed their levee, and damage done thereby to plaintiffs’ land or levee by reason of the failure of defendant to construct his levee, plaintiffs would have had a right of action against defendant for his breach of its provisions, and in that case the damage might have been much more than the cost of completing defendant’s levee. The contract of June 8th provided “that the levee to be built by each of the parties hereto shall be of the same size, height, width, character, and in accordance with the said decision of the aforesaid George A. Atherton, civil engineer, and each and both of said levees shall be complete between the date of this contract and December 1, 1898.” It is true that the dimensions, which may be called the plans and specifications, were not set forth in the contract, but were left to the civil engineer *112 to determine, but this had been done else plaintiffs could not have completed their levee. The testimony of one of the plaintiffs, P. Fabian, shows that on June 8, 1898, the information was communicated to defendant that Civil Engineer Atherton had determined the size of the levee to be three feet above the high-water mark of 1890, with a ten-foot top and a slope of three to one on the sides, and defendant said that he had no objections to this.

Appellant claims the right of action is on a new contract and a contract not in writing, a mere implied contract, and cites Chipman v. Morrill & Webster, 20 Cal. 131, as authority. In that case the surety on a promissory note paid the note, and the court held that his right of action was not based upon the contract in the note, but upon a new contract not in writing, and his suit must be commenced within two years after he paid the note. We have examined McCarthy v. Mt. Tecarte L. & W. Co., 111 Cal. 328, [43 Pac. 956], cited by appellant, and are unable to see any application to the question here, for the case at bar is not an action in assumpsit, or a promise merely implied by law, as that case clearly was. It is true that where one enters into a written contract for the purchase of land and pays part of the purchase price, and the contract says nothing about refunding money paid in the event of the refusal of the vendor to convey as he agreed to, an action to recover back the money paid, upon breach of the contract on the part of the vendor, is not based upon the written contract, but upon an implied contract and is governed by two years’ limitation, as held in Thomas v. Pacific Beach Co., 115 Cal. 136, [46 Pac. 899], But this does not assist in the determination of the case before us. If the case at bar is not one founded upon contract, then it is not assumpsit founded upon an implied contract, for were it not for the contract of March 4th and June 8th, the plaintiffs would have been no more than mere volunteers in building the levee on Lammers’ land, and Lammers would have been under no obligation to pay anything. Appellant seems to ignore the fact that this is a mutual contract in which there is a consideration to each of the contracting parties. The lands of both were to be reclaimed by the construction of the levees as provided in the contract. The consideration to defendant in part was the construction by plaintiffs of their levee. Plaintiffs had paid *113

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Vista Land Co. v. Nipomo Water & Sewer Co.
266 Cal. App. 2d 331 (California Court of Appeal, 1968)
Lande v. Southern California Freight Lines
193 P.2d 144 (California Court of Appeal, 1948)
California Employment Stabilization Commission v. Matcovich
168 P.2d 702 (California Court of Appeal, 1946)
Sprague v. Fauver
162 P.2d 865 (California Court of Appeal, 1945)
Higgins v. Grant
295 P. 532 (California Court of Appeal, 1931)
Turner v. Howze
151 P. 751 (California Court of Appeal, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
84 P. 432, 3 Cal. App. 109, 1906 Cal. App. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fabian-v-lammers-calctapp-1906.