Faber v. Muir

64 S.W. 938, 27 Tex. Civ. App. 27, 1901 Tex. App. LEXIS 201
CourtCourt of Appeals of Texas
DecidedOctober 23, 1901
StatusPublished
Cited by16 cases

This text of 64 S.W. 938 (Faber v. Muir) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Faber v. Muir, 64 S.W. 938, 27 Tex. Civ. App. 27, 1901 Tex. App. LEXIS 201 (Tex. Ct. App. 1901).

Opinion

KEILL, Associate Justice.

This suit was brought by M. A. Faber •against the appellees, Burt Muir, S. McKell, and L. A. Wilson, for an .alleged debt for $750, due by Muir, and to foreclose an alleged attachment and mechanic’s lien on- a certain lot and a building thereon, for •which the debt was contracted, as against him and the other appellees.

The ease was tried without a jury, and the trial resulted in a judgement in favor of the appellant against Muir for the alleged debt, and in favor of appellees, refusing to establish and foreclose the alleged •mechanic’s lien.

Conclusions of Fact.—On the 11th day of December, 1899, the appellee, Joseph S. McKell, being the owner of a certain lot situated in the •city of Dallas (it being the lot upon which the lien was claimed), entered into a written contract- with Burt Muir, by which the latter agreed to purchase said lot for the consideration of $2200,—$300 to be paid in cash, and the balance in sixty promissory notes for $31.86 2-3, to be •dated and executed upon the completion of certain improvements to be ■erected on said lot, and payable monthly on or before the first of each month after the date thereof, with interest at the rate of 8 per cent per annum, payable annually, and to be secured by the usual form of vendor’s .lien and trust deed; it being understood that the deed from McKell to 'Muir should be executed and delivered upon the completion of certain improvements to be made on the lots by Muir as hereinafter stated. By the contract Muir agreed and obligated himself to build on said lot a •one-story frame cottage of rooms according to the plans and specifications to be thereafter made and attached to and made a part of the contract. Muir also agreed to have said work commenced immediately .after the delivery of the agreement, or as soon thereafter as practicable, •and to have the same completed with as little delay as possible, free from any and all liens, except a lien to be reserved by McKell for .part of the ■purchase money.

By said contract McKell agreed to deposit with his agents, Seay, Terry & Co., the sum of $1600, to be disbursed by them in the erection •of said improvements, which should cost not less than that sum, upon the order of the superintendent as the improvements progressed, and not otherwise. It was also agreed that if Muir failed to erect the improvements according to the plans and specifications agreed upon, McKell • or his agents should have the power to stop the work, and take actual possession of the same, and have the improvements made according to the plans and specifications.

The agreement recites that in consideration thereof Muir had deposited with the agents of McKell the sum of $100 as a guarantee- of good faith •of the fulfillment of the contract, and that should the title prove defec *29 ti ve and should not be made good within not exceeding sixty days, the deposit should be returned to Muir; but if the title should prove good, the deposit should be applied as a part of the cash payment,—the balance of the cash payment to be made at once upon the completion of said improvements. Upon the execution of the contract by both parties thereto, the $1600 provided for therein was' immediately deposited by McKell with his agents, Seay, Terry & Co., for the purposes stated.

After the execution of the contract, and during the month of December, 1899, said agents of McKell and Burt Muir agreed orally that Muir, who was both a contractor and architect, should proceed to erect and construct on the lot the cottage stipulated for, and agreed to pay the money deposited as before stated to Muir as the construction of the building progressed, the plans and specifications of the building being at that time agreed upon between the parties, and it being mutually understood between them that Muir, as contractor, should construct the building and supervise and act as superintendent in constructing the same.

On February 15, 1900, the appellant, M. A. Faber, entered into a verbal contract with Burt Muir to erect and construct a one and one-half story frame residence upon the lot described in the contract between McKell and Muir. By the agreement Faber was to furnish the labor and' material for the erection of said house. In consideration therefor Muir agreed to pay him for the job the sum of $1600 on or before the completion of the work. Immediately thereafter Faber proceeded to perform the work, and on March 15, 1900, completed it in compliance with his contract, furnishing the material and labor therefor, and delivered the building to Muir, who accepted the same on that date, admitting that Faber had furnished the material and labor and constructed the house in compliance with the agreement, and was entitled to be paid in full the amount therefor. But under said contract Faber was not to complete the house—the doors and windows, stairway, papering and painting not being included in his contract.

As the work progressed, Seay, Terry & Co., the agents of McKell, without notice of appellant’s contract with Muir, or of his claim to a mechanic’s lien, under the apprehension that Muir was furnishing the labor and material for the erection of the building, paid him, during the progress of its construction, the sum of $1600, deposited by McKell with said agents, for the purpose stated in the written contract of sale hereinbefore mentioned. Of this $1600 Muir paid appellant $850 for labor done and material furnished in constructing said house, leaving a balance due him therefor of $750, which has never been paid biro by Muir or any one else.

Keither McKell nor his said agents knew of appellant’s contract with Muir, nor of the balance due him from Muir, until after payment by said agents to Muir of said sum of $1600. The agents thought Muir was doing the work himself, and for that reason the payments were made to him by them. Though one of the agents, during the construction of the building, did see appellant at work thereon, he thought he was simply *30 a laborer employed by Huir. When appellant made the contract with Muir, he thought the latter was the owner of the lot upon which the house was to be built, and did not learn to the contrary, nor of Muir’s contract with McICell, until after he had furnished the material and did the work on the building, as provided for in his contract with Muir.

Ko part of the $1600 advanced to Muir to build the house under the contract with him has ever been repaid. Muir abandoned the property, and failed to complete the building, and the contract between him and McKell was rescinded in April, 1900, Muir verbally consenting to said rescission, and stating that he could not complete the building, nor comply with his agreement to purchase.

On the 19th day of May, 1900, McKell, in pursuance of a written contract theretofore made on the 15th day of said month, for a valuable consideration, conveyed by warranty deed the lot upon which the lien is claimed to the appellee, L. A. Wilson. Wilson paid,. princinally in promissory notes, full value for the premises, without notice that appellant was asserting any claim or lien thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wotola Royalty Corp. v. Bethlehem Supply Co.
152 S.W.2d 480 (Court of Appeals of Texas, 1941)
Bledsoe v. Colbert
120 S.W.2d 909 (Court of Appeals of Texas, 1938)
Spinks Co., Inc. v. Pachoud Bros.
92 S.W.2d 50 (Court of Appeals of Kentucky (pre-1976), 1936)
Hamman v. H. J. McMullen & Co.
62 S.W.2d 59 (Texas Supreme Court, 1933)
Morrison v. State Trust Co.
274 S.W. 341 (Court of Appeals of Texas, 1925)
Sumrall v. Russell
255 S.W. 239 (Court of Appeals of Texas, 1923)
Hicks v. Faust
212 S.W. 608 (Texas Supreme Court, 1919)
De Bruin v. Santo Domingo Land & Irrigation Co.
194 S.W. 654 (Court of Appeals of Texas, 1917)
Eardley Bros. v. Burt
182 S.W. 721 (Court of Appeals of Texas, 1916)
Cleburne St. Ry. Co. v. Barber
180 S.W. 1176 (Court of Appeals of Texas, 1914)
William Cameron & Co. v. Trueheart
165 S.W. 58 (Court of Appeals of Texas, 1914)
Cornwell v. State
134 S.W. 221 (Court of Criminal Appeals of Texas, 1910)
Hubbell v. Texas Southern Railway Co.
126 S.W. 313 (Court of Appeals of Texas, 1910)
Carbough v. State
93 S.W. 738 (Court of Criminal Appeals of Texas, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
64 S.W. 938, 27 Tex. Civ. App. 27, 1901 Tex. App. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/faber-v-muir-texapp-1901.