F. W. Woolworth Co. v. Federal Inv. Co.

5 F.2d 787, 1925 U.S. App. LEXIS 2756
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 30, 1925
DocketNo. 6706
StatusPublished

This text of 5 F.2d 787 (F. W. Woolworth Co. v. Federal Inv. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. W. Woolworth Co. v. Federal Inv. Co., 5 F.2d 787, 1925 U.S. App. LEXIS 2756 (8th Cir. 1925).

Opinion

LEWIS; Circuit Judge.

In the main this action presents the issue as to which of the parties was liable to pay the cost of changes made in a building which the Federal Investment Company, plaintiff below, constructed for occupancy by the F. W. Woolworth Company as its tenant. The other claims made by the Investment Company, based on delay in completing the building because of the time taken to make the changes, will be pointed out later.

The Investment Co. held an option for a 99-year lease on premises fronting 46 feet on Nicollet Avenue, Minneapolis, on which there was an old building. Negotiations were carried on in the early part of 1921 between Mr. White, representing the Investment Co., and Mr. Miekler, representing the Woolworth Co., which resulted in a contract between the two companies, by the terms of which Investment Co. agreed to construct and did construct a new building on the premises to be occupied by the Woolworth Co., for a term of 25 years and 6 months at an agreed rental, the lease term to end, however, on May 1, 1947. The contract was in the form of a letter bearing date June 15, 1921, addressed by Woolworth Co. to Investment Co., to which was attached the proposed lease agreement. Both the letter and lease were prepared by the Investment Co. In this letter the Woolworth Co. said:

“ * * * "W"e hereby agree that if you wifi have constructed upon said premises, in the place of the present building, a two story and basement fireproof store building (substantially as per preliminary sketches heretofore submitted, and for which building we will submit complete working drawings and specifications), we will enter into a lease, effective from the date said building is completed, said lease to be according to the terms and conditions of the form hereto attached, and made a part hereof, the rental from the date of possession to be at the rate of $25,-000.00 per annum.
“The work of wrecking the present building (and the construction of the new building to begin on August 1, 1921, or as soon thereafter as it can be reasonably done, and to be completed and ready for occupancy on November 1, 1921, or as soon thereafter as the conditions then and there existing shall warrant, it being the intent that you shall use all due diligence in completing said building as rapidly as possible. >
“We agree to furnish you with completed working drawings and specifications from time to time as may be necessary in order not to delay the construction work of said building, and sufficient detailed drawings and spe’eifieations on or before June 25, 1921, so that you can get accurate figures on the cost of said new building.”

The Investment Co. put its acceptance of the proposal on the letter thus:

[789]*789“F. W. Woolworth Company, Minneapolis, Minnesota. '
“We hereby accept the above proposition, subject to the completed plans for the building being satisfactory to us as to construction and costs.”

Woolworth Co.’s agent at Minneapolis sent this letter, with the lease attached, to Woolworth Co.’s New York office, where the letter was signed and the lease executed by the Woolworth Co., and it returned them to its Minneapolis agent. At the same time (June 27) it sent its Minneapolis agent this telegram, copy of which was delivered to Investment Co. on June 28th:

“Lease Nicollet Avenue and letter June fifteenth to Federal Investment Company signed and posted today but plans and specifications not approved as we have decided not to let off any office space and instead have salesroom on second floor and stock room in basement this revised scheme will work out more satisfactorily also will decrease cost of -construction posting letter today showing revised requirements so you can start detail plans and specifications.”

Before Investment Co. formulated the letter and proposed lease Woolworth Co. had its architect at Minneapolis prepare preliminary plans, mentioned in the letter of June 15th, for the building it desired, and submitted them to Investment Co. so that it could get an approximate estimate of what the building would cost. The estimates obtained were about $50,000.00. Then the letter and lease were delivered to Woolworth Co.’s agent. When Woolworth Co. signed the letter and lease at its New York office it had there a copy of the preliminary plans on which the Investment Co. had gotten the approximate cost of the new building. On receipt by Investment Co. of a copy of the telegram, quoted above, from the Woolworth Co.’s representative at Minneapolis, the Investment Co. took up its option on the premises, notified tenants in the old building to vacate and let a contract for the wrecking and removal of that building. Mr. Weaver, Woolworth Co.’s architect at Minneapolis, complying with directions in the telegram, began preparation of detailed plans and specifications for the new building, completed them, blue-printed nine sets of them and gave seven of those sets to Mr. White, president of Investment Co., about the last of July or first of August. On August 3d Mr. White wrote to six or seven contractors in the city to call at his office and get the plans and specifications for the new building, if •they eared to bid on the work, and said that aE bids must be in on August 17th. Mr. Hegg’s bid was accepted, and on August 22d he entered into a contract with the Investment Co. to construct the buüding, in accordance with those plans and specifications, for $50,850.00. After the plans and specifications “Were delivered to Investment Co., on which it took bids, changes were made in those plans and specifications by Mr. Weaver, at the request of Woolworth Co.’s New York office. Those changes were handed to Investment Co. and were made in the building, it paid the extra cost therefor, and it was to recover that cost that the Investment Co. sued in its first cause of action. The rental was to begin when the building was completed and Woolworth Co. took possession, and the second cause of action was for loss of rent, $1,716.67, during delay in completing the budding, because of the extra time taken in making the changes. Under the lease, in addition to $25,000.00 annual rental, which was to be paid in equal monthly in-staEments, Woolworth Co. also agreed to pay Investment Co. a fixed sum of $5,000.00 per annum in lieu of additional rent and taxes which might be assessed against the property during the term. The third cause of action was for recovery of a proportionate part, $424.66, of this sum during delay in making the changes. The budding was not complete for occupancy untd in February, 1922. Investment Co. paid the contractor $7,456.32 for making the changes, demanded payment of that and the other amounts sued for from Woolworth Co., which was refused, and thereupon brought this suit and recovered a verdict and judgment of $5,285.73 on October 24, 1923.

Before answering, however, defendant challenged the sufficiency of the complaint by demurrer; and the District Judge, in overruling the demurrer, said:

“The complaint is evidently framed upon the theory of an implied contract. It conforms to the requirements of such a pleading under the Minnesota practice. Lufkin v. Harvey, 125 Minn. 458, 147 N. W. 444, and cases therein cited. Whether there was in fact such a contract between the parties, must depend upon all of the facts and circumstances which may be disclosed by the evidence. Lombard v. Rahilly, 127 Minn. 449, 149 N. W. 950.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lufkin v. Harvey
147 N.W. 444 (Supreme Court of Minnesota, 1914)
Lombard v. Rahilly
149 N.W. 950 (Supreme Court of Minnesota, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
5 F.2d 787, 1925 U.S. App. LEXIS 2756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-w-woolworth-co-v-federal-inv-co-ca8-1925.