F. B. Norman Co. v. E. I. duPont deNemours & Co.

108 A. 743, 12 Del. Ch. 155, 1920 Del. Ch. LEXIS 20
CourtCourt of Chancery of Delaware
DecidedJanuary 17, 1920
StatusPublished
Cited by7 cases

This text of 108 A. 743 (F. B. Norman Co. v. E. I. duPont deNemours & Co.) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. B. Norman Co. v. E. I. duPont deNemours & Co., 108 A. 743, 12 Del. Ch. 155, 1920 Del. Ch. LEXIS 20 (Del. Ct. App. 1920).

Opinion

The Chancellor.

By lease dated January 28, 1912, the defendant. leased to the complainant a lot of land and building on West Eleventh Street, in Wilmington, for five years at a money rent. The lessor agreed to make certain repairs and improvements theretofore agreed on, consisting of structural changes to adapt the building to the uses of the business of the complainant, and if they were not completed by February 1 the occupancy under the lease would begin upon their completion. There was delay in getting from the Building Inspector a permit for the improvements, and the permit could not have been obtained by the defendant .until June 21. Thereafter there was no reason why the defendant could, not have made the contemplated changes in the building, though the cost of doing so would have been greater than the earlier estimate thereof.

The lessor claims to have been released by the lessee from all obligations under the lease by a letter of the latter dated March 13, 1919, in which*it was stated that the uncertainties as to the lessor being in a position to give possession had made it necessary ■for the lessee “to make other arrangements,” and the lessor was in terms “released from any further obligations” to the lessee, followed by an offer by the lessee to return its copy of the lease “upon request by letter.’’

Obviously if accepted, of if the lessor had so acted as that its acceptance could reasonably have been implied, this letter was sufficient to-relieve the lessor, of a further duty to perform the [158]*158contract. On the other hand, it is not clear that the lessee then had a right to terminate the lease against the wishes of the lessor. But it is unimportant to consider this point, because after the letter of March 13 had beén received by the defendant, there were conferences between the parties as to the continuance of the relationship created by the lease, and by letter dated April 1, Daniel Cauffiel, acting for the lessor, and in confirmation of such prior conversations, expressed regret that the building was not in readiness to come up to the expection of the lessee, and said:

“However, we are going to rush this through and hope to be able to advise you at an early date that you may occupy it,” (meaning occupy the leased building).

There was nothing in the prior conversations which justified any special interpretation to this letter, for those conversations related to no other transaction between the parties than the lease, the lessee inquiring as to when the changes would be made and the lessor explaining delays. At this time the lessee desired to go on with the lease, and up- to this time nothing had been said or done by the lessor to the contrary, or to indicate that the letter of March 13 had been adopted by it as a finality in terminating the lease.

It isovery clear, then, that the lessee was justified in- interpreting the letter of April 1 as a rejection of its effort to terminate the léase. To hold otherwise would imply deceit by the writer of the letter. The letter referred not to a new proposition, but to the old one, and thereafter neither party could say, as against the other, that the lessor had been effectively discharged from its obligation to the lessee. Consequently the lessee thereafter had a right to expect that the building would as soon as practicable be put in condition for its occupancy under the lease.

For the lessee it was explained that because of delays of the lessor as to- the improvements after the making of the lease the lessee desired to acquire the use of other premises, and endeavored by the letter of March 13 to obtain a release from its obligation to the defendant, but having no reply thereto gave up the effort to get other quarters, and reverted to the lease. Confirmation of this is found in the letter of the defendant of April 1 referring to conversations.

[159]*159From April 1 to May 16 F. B. Norman, for the complainant, made at various times inquiries of the defendant, showing a desire and intention to carry out the lease, but as the permit was not obtainable until June 21 the improvements were not made. Cauffiel, for the defendant, sent the complainant an enigmatical letter dated May 16 referring to the delay as to the permit, and saying in substance that the defendant company would continue to use the building until a permit be obtained, and when obtained would give the complainant company “refusal” of the building, and asked for a return of the lease. What was the effect of this letter on the rights of the complainant? None. The offer of the complainant to abandon its rights under the lease had been rejected by the defendant, and the parties had thereafter, and at least to May 16, acted as if each intended to perform. By the letter of May' 16 “the lessor tried to accept a proposition which did not exist, the one made having been previously declined by the defendant. ■ The defendant could not in that way take away the rights of the lessee. Without necessarily relinquishing its advantage Mr. Norman suggested to Cauffiel that the defendant use the building of the complainant on Shipley Street, because in the letter of May 16 Cauffiel had stated as a reason for desiring to cancel the lease that the defendant company wanted to continue to use part of the demised property. The suggestion of Norman was a new element in the dealings, but it has no significance or evidential value to show an abandonment by the complainant of its rights under the lease.

After June 21 the Building Inspector was empowered to give the permit and this was known by the defendant company. From early in June to July 10 Mr. Norman was out of the city, and there is no evidence that he, or any officer of the complainant company, knew that the Building Inspector had authority to grant the permit. No reply was made to the letter of May 16, and matters drifted along again, Norman after his return on July 10 making no inquiries as to the delays in making the improvements, or demand for diligence or performance. When informed through the newspapers that the property had been sold by the defendant, the complainant promptly, by letter of August 13, demanded performance, and the bill was filed August 22, 1919.

Assuming that the letter of May 16 may fairly be regarded [160]*160as a declaration by the lessor of its intention to terminate the lease, which at that time was a subsisting agreement, performance thereof being held up by the Building Inspector and without fault of either of the parties, the important inquiry is whether inferen- . tially the lessee agreed to terminate the lease, there being no evidence of a direct acceptance or declination of the proposition by the defendant to that effect. As above stated, the suggestion of Norman that the lessor use the lessee’s property on Shipley Street did not show acquiescence in the letter of May 16. Neither did the inattention of the lessee between May 16 and August 13 of itself show acquiescence or abandonment, for it could stand on its rights under the lease, and did not know that the legal obstruction of the want of a permit had been removed. The lessee had a right to ignore the letter of May 16, and did so, and it is signifi-" 'cant that the lease was not returned by it to the lessor, as requested by the latter.

Therefore the lease is still in force, and if there is no legal difficulty as to the form of remedy the lessee has a right to have the lessor perform the contract of the lease, and has not abandoned or released its right thereto. Neither has it estopped itself from enforcing its rights thereunder.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Falciani v. Zinszer
Superior Court of Delaware, 2019
Lee Builders, Inc. v. Wells
95 A.2d 692 (Court of Chancery of Delaware, 1953)
Lee Builders v. Wells
95 A.2d 692 (Court of Chancery of Delaware, 1953)
Temple Enterprises, Inc. v. Combs
100 P.2d 613 (Oregon Supreme Court, 1940)
Rowan v. Harburney Oil Co.
91 F.2d 122 (Tenth Circuit, 1937)
Elliott v. Gentry
60 P.2d 203 (New Mexico Supreme Court, 1936)
Conner v. Jordin
181 A. 229 (Superior Court of Delaware, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
108 A. 743, 12 Del. Ch. 155, 1920 Del. Ch. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-b-norman-co-v-e-i-dupont-denemours-co-delch-1920.