Exxon Corporation v. Federal Energy Regulatory Commission, Louisiana Gas Service Company, a Division of Citizens Utilities Company, Intervenors

114 F.3d 1252, 325 U.S. App. D.C. 44, 1997 U.S. App. LEXIS 13899
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 13, 1997
Docket96-1226, 96-1238
StatusPublished
Cited by10 cases

This text of 114 F.3d 1252 (Exxon Corporation v. Federal Energy Regulatory Commission, Louisiana Gas Service Company, a Division of Citizens Utilities Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exxon Corporation v. Federal Energy Regulatory Commission, Louisiana Gas Service Company, a Division of Citizens Utilities Company, Intervenors, 114 F.3d 1252, 325 U.S. App. D.C. 44, 1997 U.S. App. LEXIS 13899 (D.C. Cir. 1997).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

This ease arises out of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) approval of a partially contested settlement agreement between Koch Gateway Pipeline Company (“Koch”) and its customers which set terms, conditions, and rates for Koch’s natural gas transportation services. The three orders under review are FERC’s initial order approving the settlement and its two consecutive denials of petitions for rehearing. Petitioners are various Koch customers who use the pipeline primarily for short hauls of natural gas; they urge this court to set aside the settlement, claiming (1) that the settlement approval process was proeedurally flawed; and (2) that certain portions of the settlement are not supported by substantial evidence. On review, we conclude that the Commission’s procedures, although somewhat unusual, were permissible here because petitioners did have an opportunity to submit objections to arguments and evidence put forth by the proponents of the settlement. We also find that there was substantial evidence in the record to support both the Commission’s approval of Koch’s use of averages from a twelve-month period in calculating its settlement rates, and its approval of Koch’s two percent flat fuel charge. However, we conclude that FERC’s approval of a significant change in Koch’s methodology for calculating mileage-based interruptible transportation rates was unsupported by substantial evidence and therefore we remand to the Commission for further consideration of that issue.

I. Background

On January 31, 1994, Koch filed this Natural Gas Act (“NGA”) section 4 rate case in order to institute an increase in its transportation rates. On March 2,1994, the Commission set the proposed rate increase for hearings before an Administrative Law Judge (“ALJ”). Discovery and settlement negotiations ensued. On February 10, 1995, Koch submitted a proposed comprehensive settlement to the ALJ. In contrast with Koch’s original 1994 increase proposal, the settlement produced a reduction in Koch’s level of cost recovery from its customers and a reduction in its firm services rates, but an increase in some of its interruptible rates. Joint Appendix (“J.A.”) 377. The settlement was either supported or not opposed by the Commission staff, Koch’s competitors, and some of Koch’s customers, but was contested by other customers including the petitioners here. J.A. 195, 252.

Koch requested that the ALJ first sever the contesting parties so that they could litigate their claims, and then certify the settlement to the Commission as uncontested for parties supporting or not opposing the agreement. The ALJ denied Koch’s request in an order dated May 22,1995. 71 F.E.R.C. ¶ 63,012 (1995) (J.A. 194). Although the ALJ agreed that the contesting parties ultimately would “have an opportunity to be severed from the Settlement, and to proceed to hearings,” J.A. 201, nevertheless he concluded that he could not yet certify the settlement. He explained that, under Rule 602(h)(2) of FERC’s Settlement Rules, a settlement cannot be certified if any participant originally contested the settlement — even if that participant is ultimately severed — unless the ALJ makes a finding either (1) that there is no genuine material factual issue, or (2) that an initial decision may be omitted and the record contains substantial evidence from which the Commission may reach a reasoned decision on the merits of the contested issues. 2 The ALJ determined that this Rule 602(h)(2) requirement was not satisfied because peti *1256 tioners had raised genuine issues of material fact with regard to the interruptible rate design, the flat fuel charge, and several other issues not relevant here, and that the record did not contain substantial evidence sufficient for the Commission to resolve these issues. 3 To remedy this problem, the ALJ ordered that the noncontesting parties submit certain supplemental evidence about contested issues. J.A. 199-200.

The ALJ denied a motion for reconsideration. 72 F.E.R.C. ¶ 63,001 (July 12, 1995) (J.A. 232). However, the ALJ agreed that he would sever the contesting parties, and would also sever the issue of interruptible rate design from the settlement and set that issue for hearing. J.A. 240-41.

Several parties filed interlocutory appeals from the ALJ’s July 12 order. These appeals, which were referred to the Commission by the Commission Chair on July 25, 1995, complained that a long delay in entering the settlement would deprive the settling parties of the benefit of their bargain. In response to the appeals, the Commission directed the ALJ to certify the entire record to the Commission. 72 F.E.R.C. ¶ 61,150 (Aug. 2, 1995) (J.A. 309). Subsequently, on September 29, 1995, FERC directed Koch to provide additional evidence on seven specific aspects of the settlement. Koch complied with this request, and the Commission afforded petitioners an opportunity to respond with their own data and arguments. J.A. 311; 317-36; 340-45. However, petitioners did not submit additional data or testimony to rebut Koch’s new submissions and instead relied solely upon unsubstantiated assertions by counsel. J.A. 340-45.

On February 1, 1996, after receiving the additional evidence and arguments from the parties, the Commission issued an order reaching the merits of each of the substantive issues raised by petitioners in opposition to the settlement. Koch Gateway Pipeline Co., 74 F.E.R.C. ¶ 61,088 (Feb. 1, 1996). The Commission concluded that “no additional hearings are necessary to resolve any of the issues raised by the opposing parties,” and therefore that there was no need to sever the contesting parties or to set the matter for a hearing as the ALJ had indicated. Id. at 61,272. Accordingly, the Commission approved the settlement with one modification not at issue here. 4 Two successive requests for rehearing by Koch and the petitioners were denied. This petition for review followed.

A. The Commission’s Initial Order Approving the Contested Settlement

In its initial February 1 order, the Commission first turned its attention to procedural questions. The Commission assumed that it was proper to direct the ALJ to certify the entire record in the proceeding to the Commission, and further held: (1) that the ALJ erred by concluding that, once an issue has been contested, it remains “contested” — and thus subject to the requirements of Rule 602(h)(2) — regardless of whether the parties contesting the issue are severed, (2) that the ALJ’s decision to direct the consenting parties to file additional evidence “is contrary to one of the basic purposes of the settlement rules,” which is “to provide an expedited procedure for approval of uncontested issues,” and (3) that the practice of severing contesting parties need not be followed if “the contested issues can be resolved on the basis of Commission policy or on the basis of the record already developed in the proceedings.” Id. at 61,270-71 (J.A 378-79).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
114 F.3d 1252, 325 U.S. App. D.C. 44, 1997 U.S. App. LEXIS 13899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-corporation-v-federal-energy-regulatory-commission-louisiana-gas-cadc-1997.