Opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 13, 2000 Decided March 24, 2000

No. 97-1092

Exxon Corporation, et al., Petitioners

v.

Federal Energy Regulatory Commission, Respondent

Consolidated Edison Company of New York, Inc., et al., Intervenors

On Petition for Review of an Order of the Federal Energy Regulatory Commission

Thomas J. Eastment argued the cause for petitioners. With him on the briefs were Marc C. Johnson, Bruce A. Connell, Jennifer S. Leete, Linda L. Geoghegan and Michael L. Pate.

Timm L. Abendroth, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Jay L. Witkin, Solicitor, and Susan J. Court, Special Counsel. John H. Conway, Deputy Solicitor, entered an appearance.

Marc Richter, Harvey L. Reiter, Richard Arlen Rapp, Jr., James H. Byrd, L. Clifford Adams, Jr., Allen Weinberg, Kenneth R. Carretta, John E. Holtzinger, Jr., Jacolyn A. Simmons and Kevin M. Downey were on the brief for intervenors. Kent K. Carter, Joel F. Zipp, Michael J. Fre- muth, J. Paul Douglas and Mary L. Wright entered appear- ances.

Before: Williams, Randolph and Tatel, Circuit Judges.

Opinion for the Court filed by Circuit Judge Williams.

Dissenting opinion filed by Circuit Judge Randolph.

Williams, Circuit Judge: This case arises out of the Feder- al Energy Regulatory Commission's "unbundling" of inter- state gas pipelines' sales and transportation service. As part of that unbundling, parties with firm rights to buy natural gas in the downstream areas served by Transcontinental Gas Pipe Line Corporation ("Transco") were given the right to convert their gas purchase entitlements into transportation service rights. They evidently all did so, and are known as the "FT conversion shippers." When Transco reached an unbundling settlement with its customers, these conversion shippers sought assurance that their rights to use of the pipeline upstream would be sufficiently firm. FERC responded affir- matively, insisting that Transco give the service a priority that rendered it "essentially firm." Transcontinental Gas Pipe Line Corp., 55 FERC p 61,446 at 62,345-46 (1991) ("Settlement Order").

Ranged against the conversion shippers are "Indicated Shippers," led by Exxon, who are gas producers in Transco's production areas. They contend that if the conversion ship- pers are to enjoy firm transportation service in the produc- tion areas, they should pay for it in the way that is predomi- nant for firm transportation service, i.e., by a two-part

charge--first a reservation charge for the right to use the service, and second a usage charge covering the costs of actual usage.

Transco filed tariffs under s 4 of the Natural Gas Act, 15 U.S.C. s 717c, proposing such two-part rates, designating them "firm-to-the-wellhead" or "FTW" rates. (Petitioners note that this is technically a misnomer; the rates in fact would go only as far as producers' gathering systems. But, as have all the participants, we use the FTW label.) The Commission rejected the FTW rates, Transcontinental Gas Pipe Line Corp., 76 FERC p 61,021 ("Opinion No. 405"), denied rehearing, 77 FERC p 61,270 (1996) ("Opinion No. 405-A"), and finally issued a further "Order on Rehearing and Request for Clarification," 79 FERC p 71,205 (1997), adhering to the rejection. The Indicated Shippers petition for review.

The Indicated Shippers also attack prior decisions in which the Commission rejected two-part FTW rates that Transco had proposed under s 5 of the Act, 15 U.S.C. s 717d, Trans- continental Gas Pipe Line Corp., 63 FERC p 61,194, rehear- ing denied, 65 FERC p 61,023 (1993). We do not address those decisions directly. In the s 4 cases, we find no rea- soned decisionmaking to support the Commission's rejection of Transco's filings. If on remand the Commission adheres to that rejection and justifies it, the Indicated Shippers' ability to secure relief under s 5 will probably be remote; if on remand the Commission accepts the Indicated Shippers' posi- tion under s 4, then of course they will need no relief under s 5.

* * *

At stake are rates governing gas transportation on "later- als" linking gas producers' gathering systems with Transco's main pipelines. Transco was an early unbundler, reaching an unbundling settlement with its customers in 1991. When FERC reviewed the settlement, representatives of the FT conversion shippers sought assurance of high priority for their use of these laterals. (The service is dubbed "IT-feeder

service"; nominally interruptible, it feeds the conversion ship- pers' entitlements to mainline capacity.) FERC agreed, or- dering that

Transco's tariff should specifically set forth the capacity priority of Rate Schedule IT feeder service, i.e., that such service is not firm but that it has priority over any other interruptible service regardless of the date of the service agreement.

Settlement Order, 55 FERC at 62,377. As everyone under- stood at the time, including FERC, this grant of priority made Transco's IT-feeder service for the FT conversion shippers "essentially firm." Id. at 62,346. But the Commis- sion did not direct two-part rates for this "essentially firm" service, and it has been subject to only a single volumetric usage charge.

In 1992 the Commission adopted Order No. 636, extending its restructuring of the gas industry. See Pipeline Service Obligations and Revisions to Regulations Governing Self- Implementing Transportation under Part 284 of the Com- mission's Regulation of Natural Gas Pipelines after Partial Wellhead Decontrol, FERC Stats. & Regs. p 30,939 (1992). One of its goals was the creation of a "national gas market" with "head-to-head, gas-on-gas competition where the firm transportation rate structure is not a potentially distorting factor in the competition among merchants for gas purchasers at the wellhead and in the field." Id. at 30,434. To this end, FERC ordered that when pipelines provide firm transporta- tion with a two-part fee structure, all fixed costs are allocated to the reservation charge so that the usage charge is based only on variable costs. This new rate design was called "straight fixed variable" ("SFV"). It replaced "modified fixed variable" ("MFV") pricing, under which the usage charge for any two-part rate included a portion of a pipeline's fixed costs. See United Distribution Cos. v. FERC, 88 F.3d 1105, 1167-68 (D.C. Cir. 1996) (upholding FERC's abandonment of modified fixed variable pricing); see also 18 CFR s 284.8(d). With MFV the pipelines had varied in their allocation of fixed costs to the usage charge, and "[t]he Commission believed the

MFV rate design distorted the unit delivered prices of gas, and thereby hindered the development of an efficient national market for gas." Municipal Defense Group v. FERC, 170 F.3d 197, 199 (D.C. Cir. 1999). With SFV the Commission hoped "to promote competition at the natural gas wellhead by increasing the transparency of natural gas pricing." Texaco Inc. v. FERC, 148 F.3d 1091, 1094 (D.C. Cir. 1998).

Because conversion from MFV to SFV often contradicted contracts between pipelines and purchasers, the Commission could require SFV only by invoking its authority to modify private contracts under the so-called "Mobile-Sierra doc- trine." See Texaco Inc., 148 F.3d at 1096-97; see also United Gas Pipe Line Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Exxon Corp v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-corp-v-ferc-cadc-2000.