Executors of Lord v. Carbon Iron Manufacturing Co.

42 N.J. Eq. 157
CourtNew Jersey Court of Chancery
DecidedOctober 15, 1886
StatusPublished

This text of 42 N.J. Eq. 157 (Executors of Lord v. Carbon Iron Manufacturing Co.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Executors of Lord v. Carbon Iron Manufacturing Co., 42 N.J. Eq. 157 (N.J. Ct. App. 1886).

Opinion

Van Fleet, V. C.

The questions in dispute in this case relate to the rights and duties of persons owning adjoining mines. The litigants own adjacent iron mines in the county of Morris. They have both worked the same vein of ore, but at different levels, and at different times, the defendants’ mine being above that of the com[159]*159plainants’, and having been first worked in order of time. The main purpose of the complainants’ suit is to procure a decree which will protect them against injuries which they allege they now suffer from the flowing of water from the defendants’ mine into theirs, and which will also give them protection against injuries, which they say they will inevitably sustain in the future, if the defendants are allowed to do what they threaten, namely, reduce the pillars and walls of their mine, and let its surface subside. The complainants ask protection, it will be observed, against both present and prospective injury.

The facts on which the complainants rest their right to be relieved against present injury may be summarized as follows: The Carbon Iron Company were the predecessors in title of the defendants; they owned the mine now owned by the defendants up until June, 1878, when, under a decree of this court directing the sale of certain mortgaged premises, this mine, with other lands, was conveyed to the defendants. The Carbon Iron Company, while they owned the defendants’ mine, worked over the boundary line and took ore from the complainants’ land. The time when this trespass was committed is not fixed with entire certainty. The bill does not allege when it was committed—it simply says that the Carbon Iron Company, while they were in possession, committed a trespass by working over the line; the answer, however, says that it was committed somewhere about the year 1872, and the proofs render it tolerably clear that it was committed near that time—certainly prior to 1875. The point where it was committed is about one hundred feet, measured vertically, below the surface. There is a dispute between the parties as to the true location of the division line, and a large amount of evidence was submitted by each in support of their respective claims, but, without expressing an opinion as to which claim is vindicated by the evidence, I shall, for the purposes of this discussion, treat the line claimed by the complainants as the true one. Adopting their line as the true one, the wrongful act of the Carbon Iron Company, which the complainants seek to make, in part, the basis of the relief they ask against the defendants, consisted in making an excavation or [160]*160hole in the complainants’ land, one hundred feet below the surface, for a distance of about forty-seven feet beyond the property line. A second trespass was committed in 1881. The defendants’ lessees were the wrong-doers in this instance. This trespass was committed at a point about two hundred feet, vertical measurement, below the surface, and consisted in making an excavation beyond the division line for a distance of about thirty feet.

The two wrongful acts just described form the sole foundation of the complainants’ right to relief against present injury. Neither the defendants, nor those who preceded them in title, nor those who have succeeded to any of their rights, have, by the exercise of force or violence, committed any other wrong against the complainants. It is not claimed that these trespasses, at the time they were committed, did the complainants any immediate, irreparable injury, or even serious harm, but it is consequences which have since flowed from them-consequences produced by the complainants’ own subsequent acts—which have inflicted the injuries against which they ask protection.

The complainants did not begin to open their mine until the fall of 1880. They then sunk a shaft at a point where they knew it must, if carried down on the vein, strike the excavation which the Carbon Iron Company had previously made in their land, and that an opening between the two mines would thus be made, and that when it was made the inevitable result would be, if no barrier was erected to bay back the water rising in the defendants’ mine, that the water would flow down into their mine. The location of their shaft was judiciously selected. It was placed where it could be constructed with the least expense and be used to the greatest advantage. Their superintendent, however, says—and he is the person who selected the site for the shaft—that he expected, when he located the shaft, that in sinking it he would break into the excavation made by the Carbon Iron Company, and that he knew if he did an opportunity would be afforded to the complainants to turn the water rising in their mine, above that point, into the defendants’ mine; and he also [161]*161says that he thought, if at any subsequent time it should become necessary to protect the complainants’ mine against the water rising in the defendants’ mine, that he could do it by building a dam across the opening. The first opening between the two mines was made in sinking the shaft, in the manner in which the complainants’ superintendent expected it would be made. And the second was made by the complainants’ miners in blasting. A hole was drilled immediately above where the second excavation across the line had been made, and was then charged with powder and fired. The blast was not successful. Two of the complainants’ miners say that they supposed the reason why it was not successful was that the bottom of the drill-hole happened to be near a crevice or fissure in the rock, and that when the powder exploded the force produced spent itself in this opening. A new bottom was then made for the hole and it was again charged with powder, and when this second charge exploded, a hole as large as a man’s head was made between the two mines. This hole was afterwards enlarged by the use of picks so that an ordinary person could pass through it from one mine to the other. At the time this last opening was made, the complainants’ mine had no means of ventilation except through its shaft and the upper opening made into the defendants’ mine. One of the miners, who assisted in making the second opening, says that the complainants’ mine needed ventilation, and that after the second opening was made its ventilation was much better than it was before.

The surface above the mines is low and wet, and they both, consequently, carry a large quantity of water. They are both wet mines. Through the two openings made in the manner just described, all the water rising in the defendants’ mine, above the openings, is given a free passage into the complainants’ mine, and it is against the injury inflicted by this flowage that the complainants ask protection. They insist that upon the facts above stated they are entitled to an injunction restraining the defendants from permitting the .water rising in the defendants’ mine from flowing through these openings into theirs. The complainants’ right to the relief they ask, it will be perceived, stands dis[162]*162tinctly and exclusively on two simple trespasses, neither of which was committed by the defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
42 N.J. Eq. 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/executors-of-lord-v-carbon-iron-manufacturing-co-njch-1886.