Executive Plaza, LLC v. Peerless Insurance

717 F.3d 114, 2013 WL 2249134, 2013 U.S. App. LEXIS 10394
CourtCourt of Appeals for the Second Circuit
DecidedMay 23, 2013
DocketDocket 12-1470-cv
StatusPublished
Cited by5 cases

This text of 717 F.3d 114 (Executive Plaza, LLC v. Peerless Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Executive Plaza, LLC v. Peerless Insurance, 717 F.3d 114, 2013 WL 2249134, 2013 U.S. App. LEXIS 10394 (2d Cir. 2013).

Opinion

CHIN, Circuit Judge:

This case asks us to consider the interplay between two provisions in a fire insurance policy. One requires the insured to file suit on the policy within two years. The second requires the insured, when seeking replacement costs, to replace the damaged property before bringing suit, and to complete the replacement work “as soon as reasonably possible.” What happens to insured property that cannot reasonably be replaced within two years? As New York case law does not clearly resolve the question raised by this appeal, we conclude that certification to the New York State Court of Appeals is appropriate.

BACKGROUND

A. The Facts

The facts relevant to this appeal are not in dispute. Plaintiff-appellant Executive Plaza, LLC (“Executive”) owns a building insured at all relevant times by defendantappellee Peerless Insurance Co. (“Peerless”). The property was insured by a policy providing up to $1 million of coverage (the “Policy”). On February 23, 2007, a fire destroyed the building. Executive promptly notified Peerless of the damage. Within days, Executive had retained both an architect and a construction company. By July 2007, Peerless had paid Executive the actual cash value of the property, $757,812.50, less certain adjustments.

In the years after the building was originally erected, zoning laws had changed. To rebuild, Executive needed a variance and other forms of consent from local governmental entities. Despite first submitting its application for review in June 2007, a final building permit was not granted until November 2008, seventeen months *116 later. By October 2010, Executive had “substantially replaced” the property.

Two Policy provisions are the focus of this appeal. First, section E.4 required Executive to file suit to recover unpaid losses within two years of the fire:

No one may bring a legal action against us under this insurance unless:
a. There has been full compliance with all of the terms of this insurance; and
b. The action is brought within 2 years after the date on which the direct physical loss or damage occurred.

Second, section E.6 of the Policy provided that Peerless would pay either the actual cash value or the replacement cost of the property, up to the policy limit. It further provided that an insured could first receive the actual cash value of the property and then later seek the replacement cost. If, however, an insured sought the replacement cost, section E.6(d)(l)(b) imposed two additional caveats:

(b) We will not pay on a replacement cost basis for any loss or damage:
(i) Until the lost or damaged property is actually repaired or replaced; and
(ii) Unless the repairs or replacement are made as soon as reasonably possible after the loss or damage.

B. Procedural History

On February 23, 2009, before it had completed rebuilding the property but within the two-year limitations period, Executive filed suit in New York State Supreme Court, Nassau County, to recover replacement costs under the Policy. Peerless removed the case to the Eastern District of New York on diversity grounds (the “First Action”). As construction on the property had not yet been completed, the district court (Wexler, J.) dismissed the claim as not yet ripe. Executive did not appeal this decision.

After having substantially replaced the property, on October 5, 2010, more than two years after the loss, Executive sent Peerless a demand letter to recover an additional $242,087.50 (the replacement cost permitted by the Policy, less what Peerless had already paid). Peerless rejected the demand. Executive filed suit in New York State Supreme Court, Nassau County, and Peerless again removed the action to the Eastern District of New York on diversity grounds (the “Second Action”). The district court below (Seybert, J.) dismissed the Second Action as time-barred. This appeal followed.

DISCUSSION

Peerless argues that “full compliance” with the terms of the Policy, see Policy § E.4, requires that Executive both (1) rebuild the property “as soon as reasonably possible” but also (2) before the two-year limitations period for filing suit. By contrast, Executive contends that it defies logic to require an insured to fully rebuild an insured property before filing a claim and to bring suit within two years when rebuilding the property within two years is not reasonably possible. For the reasons that follow, we conclude that certification to the New York State Court of Appeals is appropriate. See Country Wide Ins. Co. v. Nat’l R.R. Passenger Corp., 407 F.3d 84, 85-86 (2d Cir.2005).

A. Applicable Law

Under Second Circuit Local Rule 27.2, we may “certify a question of state law to that state’s highest court.” Local R. 27.2(a); see also N.Y. Comp.Codes R. & Regs. tit. 22, § 500.27(a) (allowing courts to certify “determinative questions of New York law ... for which no controlling *117 precedent of the Court of Appeals exists”). Our decision to certify is made after considering three questions:

(1) whether the New York Court of Appeals has addressed the issue and, if not, whether the decisions of other New York courts permit us to predict how the Court of Appeals would resolve it; (2) whether the question is of importance to the state and may require value judgments and public policy choices; and (3) whether the certified question is determinative of a claim before us.

Osterweil v. Bartlett, 706 F.3d 139, 142 (2d Cir.2013) (quoting Barenboim v. Starbucks Corp., 698 F.3d 104, 109 (2d Cir.2012)).

B. Application

First, we note that the New York State Court of Appeals has not resolved this question. It has interpreted the suit limitations provision alone, see Blitman Const. Corp. v. Ins. Co. of N. Am., 66 N.Y.2d 820, 822, 498 N.Y.S.2d 349, 489 N.E.2d 236 (1985) (twelve-month suit limitations clauses was enforceable); Proc v. Home Ins. Co., 17 N.Y.2d 239, 243-46, 270 N.Y.S.2d 412, 217 N.E.2d 136 (1966) (holding that limitations period begins to run on date of fire), but never the replacement cost provision. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farage v. Associated Ins. Mgt. Corp.
2024 NY Slip Op 05875 (New York Court of Appeals, 2024)
Executive Plaza, LLC v. Peerless Insurance
745 F.3d 615 (Second Circuit, 2014)
Executive Plaza, LLC v. Peerless Insurance
5 N.E.3d 989 (New York Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
717 F.3d 114, 2013 WL 2249134, 2013 U.S. App. LEXIS 10394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/executive-plaza-llc-v-peerless-insurance-ca2-2013.