Exchange Bank & Trust Co. v. Texarkana School Dist. No. 7

301 S.W.2d 453, 227 Ark. 759, 1957 Ark. LEXIS 487
CourtSupreme Court of Arkansas
DecidedApril 29, 1957
Docket5-1267
StatusPublished
Cited by2 cases

This text of 301 S.W.2d 453 (Exchange Bank & Trust Co. v. Texarkana School Dist. No. 7) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exchange Bank & Trust Co. v. Texarkana School Dist. No. 7, 301 S.W.2d 453, 227 Ark. 759, 1957 Ark. LEXIS 487 (Ark. 1957).

Opinion

Carleton Harris, Chief Justice.

On December 30, 1952, McDougald Construction Company, a partnership composed of G. W. McDougald and B. V. McDougald (hereinafter called McDougald) entered into a contract with Texarkana School District No. 7 of Miller County, Arkansas, for the construction of a senior high school building. Under the contract, McDougald was to furnish all material and perform all work, receiving as compensation therefor the sum of $377,111. McDougald furnished to the district two performance bonds, with United States Fidelity and Guaranty Company as surety, under the terms of which the principal and surety agreed to the faithful performance of the terms and conditions of the construction contract, and the surety agreed that in case of default of the contractor to perform, the surety would, to the extent of the bond, make good any snch default. It was agreed between the school district (sometimes called owxier) and McDougald that the owner would pay the contract price in monthly installments as the work progressed. The amount of each installment was to be based on estimates covering the preceding month’s progress, work done, and materials delivered on the job, with ten per cent retained until filial completion and acceptance of the entire job. McDougald was to furnish satisfactory evidence of payment of all laborers, materialmen, and subcontractors, and owner was authorized to withhold from McDougald’s unpaid compensation a sum of money sufficient to pay any and all such unpaid claims. The contract provided that in paying any unpaid bills of McDougald, the owner was deemed the contractor’s agent, and any payment so made was to be considered as a payment made under the contract by the owner to the contractor. In furnishing the bond, Mc-Dougald entered into an agreement with the United States Fidelity and Guaranty Company, (hereinafter called surety), under which McDougald agreed “* * * to indemnify the Company (surety) against all loss, damages, claims, suits, costs and expenses, whatever, including court costs and couxisel fees at law or ixx equity, or liability therefor, which the Company may sustain or incur by reason of: executing or procuring said bond, or making any investigation on account of same, or procux-ing its release or evidexxce thereof from same, or defending, prosecuting or settling axiy claim, suit or other proceeding. * * *” To secure the surety, McDougald did “* * * assign and coxxvey to the Company as collateral to secure the obligations herein and any other indebtedness or liabilities of the undersigned to the Company, whether heretofore or hereafter incurred, all the right, title and interest of the undersigned in and to: (a) said contract 1 axid axxy change, addition, substitution or xxew contract (including all retained percexxtages, deferred payments, earned moneys and all moneys and properties that may be due or become due under said contract, change, addition, substitution or new contract) * * *; such assignment to be effective as of the date of the construction contract but only in event of (1) any breach of any of the agreements herein contained or of said contract or performance bond or of any other bond executed or procured by the Company on behalf of the applicant herein. * * * ” This agreement was executed on December 30, 1952.

On January 27, 1953, McDougald executed another assignment of its rights under the contract with the school district, to the Exchange Bank and Trust Company, appellant herein, to secure advances to be made to it. The stipulation does not reflect that all such advances were made in connection with McDougald’s performance of his contract with the district, and no advances were made after November 13, 1953. Appellant notified the district of its assignment. Based on eleven monthly estimates covering the construction period from the beginning of the contract through November, 1953, installments of the contract price were made to McDougald for its account amounting in the aggregate to $272,-556.41. Ten per cent of such monthly estimates, amounting in the aggregate to $27,055.23, was retained by the school district. The eleventh such estimate, covering work done and materials furnished in November, 1953, was filed by McDougald with the district after December 1,1953, and payment based thereon was remitted for Mc-Dougald’s account by owner on December 10, 1953. 2 Around the middle of December, McDougald was in such financial straits that it was unable to meet its payroll, and on December 28, 1953, formally notified appellee owner that it was unable to continue in the performance of the contract in question. Two days later, the owner notified intervener of McDougald’s default, and intervener elected to complete the performance of the construction contract in its capacity as surety under the bond, and in accordance with its obligation. Shortly after January 1, 1954, McDougald filed its twelfth estimate covering work done during the month of December. At the time of default, the aggregate of the retained percentages under the construction contract, which was being held by the school district, was $27,055.23. This amount was subsequently paid to the surety, who completed Mc-Dougald ’s contract at a cost of $206,414.89. Appellant filed suit against the school district, alleging that the district owed it $14,469.39. 3 This was based upon the assignment from McDougald to appellant, wherein appellant was to receive all monies due McDougald under the contract. (The amount sought was the total sum of indebtedness due the hank from McDougald.) The school district filed its answer, setting up that the United States Fidelity and Guaranty Company, as surety, “# * * under equitable subrogation, became entitled to receive all of the contract price stipulated for in said construction contract which remained at the time of contractor’s said default unpaid, upon the completion by surety of the performance of the construction and improvements in accordance with the terms of the construction contract after contractor’s default thereunder * * The United States Fidelity and Guaranty Company filed its intervention, adopting the answer of the school district. At the conclusion of the hearing, the court entered its decree dismissing appellant’s complaint. From such decree comes this appeal.

There is really only one question to he determined in this litigation, i.e.: “Was the right of appellant to funds in the hands of appellee, Texarkana School District No. 7, superior to the right of appellee, United States Fidelity and Guaranty Company?” At the time of McDougald’s default, it owed its materialmen, subcontractors, and employees for work done and materials furnished during the month of December, the sum of $28,-147.54. For work done and materials furnished on the job prior to December 1, 1953, it owed the additional sum of $71,418.58. This amount was past due and remained unpaid until paid by the surety. Appellant contends that it had a valid assignment from McDougald, which was accepted by the school district, and that no subsequent assignee of McDougald, and no creditor, could acquire any rights superior to the rights of the bank, the first assignee, and any monies due McDougald for work done in December should properly have been paid to appellant. It is also contended that appellant is entitled to a sufficient amount of the retained percentages as will liquidate McDougald’s indebtedness to it. We do not agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
301 S.W.2d 453, 227 Ark. 759, 1957 Ark. LEXIS 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exchange-bank-trust-co-v-texarkana-school-dist-no-7-ark-1957.