Excelsior Ambulance Service, Inc. v. United States

126 Fed. Cl. 69, 2016 U.S. Claims LEXIS 222, 2016 WL 1160214
CourtUnited States Court of Federal Claims
DecidedMarch 23, 2016
Docket15-189C
StatusPublished
Cited by2 cases

This text of 126 Fed. Cl. 69 (Excelsior Ambulance Service, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Excelsior Ambulance Service, Inc. v. United States, 126 Fed. Cl. 69, 2016 U.S. Claims LEXIS 222, 2016 WL 1160214 (uscfc 2016).

Opinion

RCFC 24; Postjudgment Motion for Leave to Intervene; Timeliness; Bid Protest

OPINION AND ORDER

SWEENEY, Judge

Plaintiff Excelsior Ambulance Service, Inc. (“Excelsior”) successfully protested the award of a contract by the United States Department of Veterans Affairs (“VA”) to LMC Med Transportation, LLC (“LMC”). LMC now moves for leave to intervene in this protest for the purpose of appealing the merits of this court’s decision in Excelsior’s favor. For the reasons set forth below, the court denies LMC’s motion.

*70 I. BACKGROUND

On February 27, 2015, the VA awarded a contract to LMC to provide ambulance services for William Jennings Bryan Dorn VA Medical Center in Columbia, South Carolina. 1 That same date, Excelsior, an unsuccessful offeror, protested the VA’s decision in this court. In its complaint, which was not filed under seal, Excelsior set forth three claims for relief. First, it alleged that the VA improperly awarded the contract to LMC even though LMC did not possess the required licenses. Second, it alleged that the VA awarded the contract to LMC despite knowing that LMC was violating regulations regarding limits on subcontracting. And third, it alleged that the VA awarded the contract to LMC despite knowing that LMC was violating the applicable federal wage determination.

The contracting officer for the procurement notified LMC that Excelsior had protested the award decision in the United States Court of Federal Claims (“Court of Federal Claims”). In a February 27, 2015 letter to the contracting officer, LMC’s Chief Operating Officer, Tracy L. Beasley, wrote:

It is our understanding that Excelsior’s protest is solely based on pricing....
After much consideration of the information we have concerning the basis for this protest, LMC does not anticipate hiring an attorney at this point to intervene in this process, but we would like to self-intervene and be kept abreast of the challenges Excelsior presents and the VA’s defense of various challenges. LMC would also like to present evidence of our understanding of the pricing of this solicitation if required or needed during this process. 2

As Mr. Beasley represented to the contracting officer, LMC did not move for leave to intervene in Excelsior’s protest, but rather opted to “self-intervene.”

Defendant filed a notice with the court on March 20, 2015, indicating that the VA intended to take corrective action. The court stayed proceedings, and on August 31, 2015, the parties informed the court that upon taking corrective action, the VA confirmed the contract award to LMC.

On September 18, 2015, Excelsior filed an amended complaint in which it challenged the VA’s corrective action. LMC had retained an attorney the prior week, on September 11, 2015, but did not move for leave to intervene in the protest. Proceedings continued without LMC’s participation. Excelsior and defendant cross-moved for judgment on the administrative record, and the court heard argument on November 10, 2015.

In a December 4, 2015 Opinion and Order, filed under seal, the court held that the VA’s award of the contract to LMC was improper because LMC did not provide a business license with its proposal, as required by the solicitation. It further held that the VA improperly permitted LMC to rewrite its proposal during the corrective action. The court therefore granted plaintiffs motion for judgment on the administrative record, enjoined the VA from awarding the contract to LMC, vacated the contract award to LMC, and remanded the matter to the VA to take action consistent with its decision. Judgment was entered on December 7, 2015, and the court released a public version of its Opinion and Order on December 15, 2015.

Defendant advised LMC on January 4, 2016, that the VA had decided not to appeal the court’s December 4, 2015 Opinion and Order. Thereafter, on January 22, 2016, LMC moved for leave to intervene in this protest pursuant to Rule 24 of the Rules of the United States Court of Federal Claims (“RCFC”) for the purpose of pursuing an appeal. Excelsior and defendant both oppose LMC’s motion.

*71 II. DISCUSSION

A. RCFC 24 and the Timeliness Requirement

LMC moves for leave to intervene as a matter of right pursuant to RCFC 24(a)(2), which provides:

On timely motion, the court must permit anyone to intervene who ... claims an interest relating to the property or transaction that is the subject of the action, and is so situated that disposing of the action may as a practical matter impair or impede the movant’s ability to protect its interest, unless existing parties adequately represent that interest.

In the alternative, LMC seeks to intervene permissively pursuant to RCFC 24(b)(1), which provides: “On timely motion, the court may permit anyone to intervene who: (A) is given a conditional right to intervene by a federal statute; or (B) has a claim or defense that shares with the main action a common question of law or fact.”

Excelsior and defendant argue that LMC’s postjudgment motion fails to meet the threshold timeliness requirement described in both subsections of RCFC 24. In considering whether LMC’s motion is timely, the court examines: (1) the length of time a putative intervenor knew or should have known of its right to intervene prior to filing its motion; (2) whether the prejudice to the rights of the existing litigants, if intervention is granted, is outweighed by the prejudice a putative intervenor would suffer if intervention is denied; and (3) the existence of unusual circumstances that weigh in favor of or against the granting of the motion. Belton Indus., Inc. v. United States, 6 F.3d 756, 762 (Fed.Cir.1993); Sumitomo Metal Indus., Ltd. v. Babcock & Wilcox Co., 69 CCPA 75, 669 F.2d 703, 707 (1982). “Timeliness is to be determined from all the circumstances,” and is an issue committed to the court’s discretion. NAACP v. New York, 413 U.S. 345, 366, 93 S.Ct. 2591, 37 L.Ed.2d 648 (1973).

B. LMC’s Motion for Leave to Intervene Is Not Timely

With respect to the first factor, LMC concedes that it knew of its right to intervene in this protest on February 27, 2015, when Excelsior filed its complaint. LMC argues, however, that it chose not to intervene at that time because it was misinformed by the contracting officer regarding the nature of Excelsior’s protest, Specifically, LMC contends that the contracting officer only indicated that the protest concerned pricing, and that had the contracting officer accurately described all of the grounds for Excelsior’s protest, LMC would likely have retained an attorney and pursued intervention.

LMC’s reliance on the information it purportedly received from the contracting officer is misplaced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
126 Fed. Cl. 69, 2016 U.S. Claims LEXIS 222, 2016 WL 1160214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/excelsior-ambulance-service-inc-v-united-states-uscfc-2016.