Ex Parte McFadden Engineering, Inc.

835 So. 2d 996, 2002 WL 1003713
CourtSupreme Court of Alabama
DecidedMay 17, 2002
Docket1010815 and 1010832
StatusPublished
Cited by5 cases

This text of 835 So. 2d 996 (Ex Parte McFadden Engineering, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ex Parte McFadden Engineering, Inc., 835 So. 2d 996, 2002 WL 1003713 (Ala. 2002).

Opinion

Petitioners McFadden Engineering, Inc., A. Frank McFadden, SJL, Inc., Michael B. Tew, and North American Specialty Insurance Company (hereinafter collectively referred to as "the petitioners") petition for a writ of mandamus directing the trial court to vacate its order refusing to allow the petitioners to conduct, or adequate time in which to conduct, certain discovery. We grant the petitions in part and deny the petitions in part.

I. Facts1
This case began on May 6, 1996, when the Town of Millry, Alabama, sued the petitioners asserting claims of fraud, breach of warranty, negligence, and wantonness stemming from the petitioners' design and construction of Millry's expansion of its existing sewer system ("the expansion system"). The expansion system, which was designed by McFadden Engineering in 1993 and constructed and installed by SJL, Inc., during the years *Page 998 1993-1994, included installation of, among other things, main sewer lines, service lines, and individual septic tanks at certain Millry households. However, the connection of those septic tanks to the individual households was left to others to complete; SJL, Inc., was not responsible for connecting the tanks to the households. Those connections were completed by August 1994; subsequently, certain problems developed, including stoppages, overflows, and venting of sewer gases.

On January 11, 2000, three and a half years after litigation began, 29 Millry residents filed a motion to intervene as individual plaintiffs. The trial court granted that motion on February 14, 2000. On April 17, 2000, 87 additional residents filed a similar motion to intervene. The last motion to intervene was filed by three Millry homeowners on May 22, 2000. The trial court granted those motions on June 9, 2000.

In sum, after three and a half years of litigation, and over the petitioners' objections, the trial court added 119 individual plaintiffs to the case (hereinafter "the intervenor plaintiffs"). Along with the new plaintiffs came new claims. In their intervenors' complaints, the intervenor plaintiffs adopted some of Millry's claims against the petitioners, but also added claims alleging nuisance, trespass, and the tort of outrage. Not surprisingly, the intervenor plaintiffs' claims alleged various individualized damages not only to their properties but also to their mental and emotional states.

Beginning in March 2000, and continuing through late November 2000, the petitioners sent various interrogatories and requests for production to each of the intervenor plaintiffs, in an attempt to assess, among other things: (1) the specific damages each intervenor plaintiff was claiming, (2) any problems that each intervenor plaintiff had had with the plumbing or septic system before the expansion system was installed; (3) any repairs that each intervenor plaintiff had made to his or her individual plumbing or septic system, and (4) the identification of any expert witnesses who would testify for the intervenor plaintiffs. However, the intervenor plaintiffs' responses arrived in a less-than-expedient fashion, to say the least.

For example, on September 1, 2000, after no responses had been received to the interrogatories and requests for production sent by McFadden Engineering, Inc., and A. Frank McFadden (hereinafter collectively referred to as "the McFadden defendants") on March 13, 2000, the McFadden defendants filed a motion to compel, which the trial court granted on September 12.2 Subsequently, on or about October 2, 2000, some of the intervenor plaintiffs submitted responses; however, *Page 999 these responses were incomplete and unresponsive, and they were not signed or notarized. Based on the intervenor plaintiffs' failure and/or refusal to "fully, completely, and individually" respond to discovery (as they had been ordered to do by the trial court), the McFadden defendants filed a second motion to compel on November 7, 2000, which was granted on the same day.3

Approximately one month later, on December 6, 2000, after having received nothing in response to the trial court's order granting thesecond motion to compel, the McFadden defendants filed a motion asking the trial court to dismiss the intervenors' complaint and/or to sanction the intervenor plaintiffs for their failure to comply with the trial court's orders compelling discovery responses. Finally, beginning on December 21, 2000, and continuing through May 4, 2001, the intervenor plaintiffs gradually submitted responses to the petitioners. While some of the responses were still somewhat incomplete, they were apparently sufficient to provide a foundation based on which the petitioners could prepare to take the depositions of each intervenor plaintiff. Accordingly, the depositions of 87 of the intervenor plaintiffs4 were taken between April 2001 and December 2001.5 Additionally, in November and December 2001, the plaintiffs took the depositions of the petitioners and their experts.

The depositions of the intervenor plaintiffs revealed particular facts surrounding their individualized allegations, which were, not surprisingly, not sufficiently known until those depositions were taken. For example, as to their claims of physical injury, the depositions revealed which doctors had treated them, and also revealed that some of the intervenor plaintiffs were claiming that they have been caused to suffer specific maladies such as headaches and/or nausea.6 Similarly, with regard to *Page 1000 their claims of damage to personal and real properties, the depositions revealed such specifics as: (1) what damage had been incurred (such as damage to bathrooms, kitchen floors, and yards), (2) when the damage began to occur, and (3) the details of the party's individual plumbing and electrical systems. Also, the deposed intervenor plaintiffs testified that they did not know how much, if any, the alleged wrongful acts had caused the value of their property to depreciate, and that no appraisals of their residences had been performed.

On December 14, 2001, the plaintiffs filed supplemental responses to interrogatories and requests for production, identifying 22 categories of individuals who may have knowledge of the facts surrounding the plaintiffs' claims. These categories included several individuals who had not yet been deposed. Also identified for the first time in the supplemental responses was an expert witness, Silas Williams, who was to testify as to the values of the intervenor plaintiffs' properties and the alleged diminution of those values. Accordingly, beginning on the same day and continuing through December 28, 2001, the petitioners began receiving Williams's appraisal reports of the intervenor plaintiffs' residences.7

To counter this new information, the petitioners retained their own expert property appraisers to examine the plaintiffs' properties and prepare their own appraisal reports. Additionally, having just completed taking the depositions of most of the intervenor plaintiffs as described above, the petitioners also sought to inspect the homes of each intervenor plaintiff in order to investigate the specific damage claims made by each intervenor plaintiff during deposition and the possible causes for that damage and to examine each intervenor plaintiff's particular electrical and plumbing connection to the expansion system.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trimble v. Trimble
26 So. 3d 445 (Court of Civil Appeals of Alabama, 2009)
ArvinMeritor, Inc. v. Handley
12 So. 3d 669 (Court of Civil Appeals of Alabama, 2008)
Zaden v. Elkus
881 So. 2d 993 (Supreme Court of Alabama, 2003)
Hertzberg v. Gainey
855 So. 2d 561 (Court of Civil Appeals of Alabama, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
835 So. 2d 996, 2002 WL 1003713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ex-parte-mcfadden-engineering-inc-ala-2002.