Evens & Howard Fire Brick Co. v. Tarry

157 P. 262, 98 Kan. 125, 1916 Kan. LEXIS 28
CourtSupreme Court of Kansas
DecidedMay 6, 1916
DocketNo. 20,178
StatusPublished

This text of 157 P. 262 (Evens & Howard Fire Brick Co. v. Tarry) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evens & Howard Fire Brick Co. v. Tarry, 157 P. 262, 98 Kan. 125, 1916 Kan. LEXIS 28 (kan 1916).

Opinion

The opinion of the court was delivered by

Dawson, J.:

The plaintiff sued the defendants for the value of four carloads of sewer pipe. The defendants answered alleging that they had been awarded a contract to construct a storm sewer on the Fort Leavenworth military reservation; that the plaintiff’s agent was present at-the letting of the contract and knew the government specifications, and that this agent solicited defendants’ order and offered to ship sewer pipe which would comply therewith and pass government in[126]*126spection; that defendants, relying upon this assurance, sent an order for pipe, directing the shipment of one carload, but that the four carloads were forwarded in disregard of that order; that the sewer pipe so shipped was of inferior quality and did not comply with the government' requirements, and that the defendants, not knowing this, hauled the pipe and laid it along side the sewer ditch, where it was inspected and rejected and that the government officials ordered it removed from the federal premises; that the defendants notified the plaintiff of the rejection of the pipe, and that the plaintiff directed the defendants to hold the pipe until further order of the plaintiff, and that the plaintiff would make arrangements to remove it from the reservation. Defendants also alleged that they were compelled to purchase sewer pipe elsewhere, and not hearing further from plaintiff they were compelled by the government officials to remove the pipe at great expense, and that they stored it in Leavenworth city; that the pipe furnished by plaintiff was defective, “and very little of it was of any value for any purpose,” and that “they have been unable to use same, and that the same thereof and the whole thereof is of no value whatsoever.” Defendants further pleaded that by the failure of plaintiff to furnish sewer pipe in compliance with the specifications and order, as plaintiff “had agreed to do,” the defendants were damaged in specified particulars, aggregating $562.30, for which sum defendants asked judgment.

Plaintiff’s reply denied that its agent submitted prices for sewer pipe; denied the making of guaranties; denied that he saw the government specifications or knew their contents; denied the receipt of an order for one carload of pipe with directions to hold the remainder until it would be determined if the government would approve the pipe, but averred that on July 22, 1911, the defendants sent a written order to ship four cars of sewer pipe as quickly as possible, and on July 25 the defendants sent another written order asking that the eighteen-inch pipe be shipped first and the balance to follow down the line of sizes without any condition or restriction as to the time of loading or shipping. Plaintiff also denied any notification that all the pipe was rejected by the government, and alleged that most of it had been used and accepted by the government and that the defendants stated that they could and [127]*127would use the balance elsewhere and that they did use a large .amount of the sewer pipe elsewhere. Plaintiff also denied receipt of notification that the government had ordered defendants to remove all of the sewer pipe, and alleged that such pipe as was hauled away was done at defendants’ own instance, and denied that it had given directions to hold the sewer pipe until further order or that plaintiff agreed to have the pipe removed from the reservation.

At the trial defendants stated that they were not seeking a rescission of the contract, but grounded their action upon damages sustained by breach of warranty and upon special damages because the goods sold to them were for a specific and guaranteed purpose.

The jury gave a general verdict for defendants and assessed their damages at $358.50. Special, questions were answered thus:

“If the jury find the defendants entitled to recover any special damages herein, they will answer the following questions and each of them:
“(1) If you find there was a warranty of the sewer pipe in question, state when the warranty was made and whether verbally or in writing? Answer. Verbally and writing.
“(2) Was the condemned sewer pipe in question of any value? Answer. No.
“(3) Did the defendants take any precaution to lessen the damages which they intended to claim against the plaintiff? Answer. Yes.
“(4) Did the defendants make any claim of damages at or about the time of the alleged breach of warranty? Answer. No.
“(5) Did the defendants use any part of the sewer pipe in question in their government contract, and if so what -sizes and how much of each? Answer. Yes, 45 ft. 18", 600 ft. 8", 200 ft. 10".
“(6) Did the defendants claim the right to hold the sewer pipe or any part thereof until payment of their claim for damages? Answer. Yes.
“(7) What, if anything, do you allow the defendants for demurrage? Answer. $8.00.
“ (8) What, if anything, do you allow the defendants for labor in unloading cars? Answer. $9.00.
“(9) What amount, if any, do you allow defendants for hauling pipe to sewer ditch? Answer. $16.00.
“(10) • What amount, if any, do you allow defendants for hauling pipe off the sewer site? Answer. $24.00.
“(11) What amount, if any, do you allow defendants for foreman in keeping sewer ditch open? Answer. $50.00.
“(12) Whát amount, if any, do you allow defendants for other help than the foreman in keeping sewer ditch open? Answer. $120.00.
[128]*128“(13) What amount, if any, do you allow defendants for penalty paid to the United States Government? Answer. $73.00.
“(14) What amount, if any, do you allow defendants for hauling sewer pipe off the military reservation? Answer. $86.00.
“(15) Do you find the market price at Ft. Leavenworth, Kansas, of the rejected sewer pipe in question to be. as invoiced to the defendants? Answer. No.
“(16) If you answer question No. 15 in the negative, then state what was the market price of the pipe? Answer. No evidence to show.”

Plaintiff assigns errors which will be considered in order.

1. To support the finding of warranty, one of the defendants testified that at the time of the letting of the contract the plaintiff’s agent solicited defendants for an order and guaranteed that its sewer pipe would satisfy the government’s demands, and the subsequent correspondence between the parties amounted to a written ratification of the oral warranty. This is far from correct. The same defendant testified that he thought the plaintiff’s agent represented “the Athens people,” a different firm, and he wrote them, giving an order which was not filled. Then he tried to get the order filled by a “Mr. Dickey,” who represented a Kansas City firm. It was only after repeated failures to procure pipe from others, and after some weeks had elapsed, that he opened negotiations with plaintiff for sewer pipe. In such situation, if plaintiff’s agent did offer to guarantee the quality of its sewer pipe at the time of the letting, such offer was not accepted and there was no oral warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
157 P. 262, 98 Kan. 125, 1916 Kan. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evens-howard-fire-brick-co-v-tarry-kan-1916.