Evans v. United States

200 F.2d 201
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 16, 1953
Docket14613_1
StatusPublished
Cited by3 cases

This text of 200 F.2d 201 (Evans v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evans v. United States, 200 F.2d 201 (8th Cir. 1953).

Opinion

RIDDICK, Circuit Judge.

The appellants brought this action against the United States in the United States District Court for the Eastern District of Missouri. The complaint alleged:

1. That the action was brought under the War Contracts Hardship Claims Act of August 7, 1946, as amended, 60 Stat. 902, 62 Stat. 992, 41 U.S.C.A. § 106 note, “for relief from losses incurred between September 16, 1940, and August 14, 1945,” without negligence on the part of appellants in the performance of a contract entered into between appellants and the United States, under which appellants agreed to furnish the materials and to perform the *203 woik for the construction of a sewage disposal plant at a proposed internment camp at Weingarten, Missouri, “in accordance with specifications, schedules and drawings” attached and made a part of the contract, for the contract price of $94,376.75;

2. That appellants began work on September 9, 1942, and continued work in accordance with the specifications and the contract until December 29, 1942, when they were notified by the United States that their contract was terminated;

3. That on the 13th day of January, 1943, the United States entered into a contract with one Fischer for the completion of the work for a price of $47,896;

4. That appellants incurred a loss, exclusive of profits and overhead, in the amount of $40,952.22 in their work under the contract;

5. That included in the appellants’ loss is the claim of the United States against appellants for $12,750.42 representing alleged cost to the United States in the completion of appellants’ contract;

6. That appellants’ loss was not the result of negligence on their part in the bidding of the contract or in its performance;

7. That appellants’ loss was caused by

(a) the failure of the United States to pay when due for extra work performed by appellants at the request of the United States,

(b) the refusal of the United States to pay appellants’ estimates for work performed as and when due under the contract,

(c) the encountering by appellants of unusual soil and rock conditions not indicated on the plans and specifications for the work to be done, increasing the unit cost of appellants under the contract,

(d) the requirement by the United States that appellants employ overtime and additional labor to speed up the work under the contract,

(e) the requirement by the United States that appellants employ labor at a higher wage scale than called for in the wage schedules set out in the specifications without compensating appellants for the excess cost incurred,

(f) the unforeseen change in labor conditions brought about by the war effort, causing a constant turnover of employees and loss of efficient man hour labor,

(g) the inability of appellants to obtain necessary equipment because of the use of such equipment on other projects having the same or higher priority rating than appellants,

(h) the unwarranted interference in the 'work by the supervisory personnel of the United States Engineers,

(i) the improper inspection of equipment and materials to be used on the project, and the furnishing of equipment unfit for use by the supervisory employees of the United States,

(j) the excessive charges made by the United States on Government owned equipment, and

(k) the wrongful act of the United States in letting a contract for completion of the project at a price in excess of the reasonable value of the work to be done. Appellants also alleged that they had complied with all the regulations governing the settlement of claims under the War Contracts Hardship Claims Act. They ask for “a determination by the Court of the equities involved in this claim, and a judgment in the sum of $40,952.22,” and for an order directing the United States to pay the judgment.

The United States answered, denying the allegations of the complaint, alleging that appellants failed to state a claim upon which relief could be granted by the District Court, and by way of counterclaim alleged that appellants abandoned performance of their contract before completion, making it necessary for the United States to employ another contractor to complete the work at a cost of $11,933.72 in excess of the price stipulated in the contract with appellants. The United States asked for judgment on its counterclaim.

In reply to the counterclaim the appellants admitted that they refused to complete the contract on which the action was brought becausé the United States itself *204 breached the contract, by refusing to give appellants credit for the correct amount of rock excavation performed by appellants and by refusing to allow appellants the just and equitable price for such excavation and for other work required under the contract.

The District Court entered judgment for the United States on the complaint of the appellants and on the cross complaint of the United States.

In appellants’ action the District Court made the following findings of fact:

“3. Plaintiffs did not file with defendant’s agency, the War Department, on or before August 14, 1945, a ‘Written Request for Relief’ within the meaning of Section 3 of the Lucas Act.
“4. Plaintiffs did not file ‘Written Request for Relief’ prior to August 14, 1945, under the First War Powers Act with the War Department or an agency concerned with the contract.”

On these findings the court concluded that the appellants were not entitled to recover.

On the counterclaim the court made the following findings of fact:

“8. Plaintiffs refused and failed to prosecute the work with such diligence as would have insured its completion -within the time specified in Article 1 of the contract or any extension thereof and failed to complete the work within such time.
“9. The defendant by written notice to plaintiffs terminated the right of plaintiffs to proceed with the work after being advised by the plaintiffs that they could not proceed further toward completion of the contract.
“10. Under the provisions of Article 9 * * * [of the contract] the defendant had the right to take over the work and prosecute it to completion because of the refusal and failure of plaintiffs to prosecute the work with proper diligence and the defendant took over the work.”

The court found that the appellants were indebted to the United States in the amount claimed on the counterclaim, and entered judgment in that amount with interest at 6 per cent from September 5, 1945.

We agree with the District Court that appéllants were not entitled to a judgment against the United States in an action under the War Contracts Hardship Qaims Act. In the opinion of this court in Fo-garty v. United States, 8 Cir., 176 F.2d 599

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estrada v. Ahrens
296 F.2d 690 (Fifth Circuit, 1961)
Hub Industries, Inc. v. United States
115 F. Supp. 450 (Court of Claims, 1953)
Holt-Fairchild Co. v. United States
111 F. Supp. 930 (Court of Claims, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
200 F.2d 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evans-v-united-states-ca8-1953.