Evans & Howard Fire Brick Co. v. National Surety Co.

173 N.W. 448, 42 S.D. 109, 1919 S.D. LEXIS 94
CourtSouth Dakota Supreme Court
DecidedJune 24, 1919
DocketFile No. 4515
StatusPublished
Cited by9 cases

This text of 173 N.W. 448 (Evans & Howard Fire Brick Co. v. National Surety Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evans & Howard Fire Brick Co. v. National Surety Co., 173 N.W. 448, 42 S.D. 109, 1919 S.D. LEXIS 94 (S.D. 1919).

Opinions

SMITH, P. J.

Appeal from an order overruling defendant’s demurrer to plaintiff’s complaint. The allegations of the complaint, so far as material to this appeal, are substantially as follows ;

[114]*114That on August 23, 1915, the Offerman Construction Company entered into a contract with the city of Watertown for the construction of certain sanitary sewers. That, as a condition precedent to awarding said contract, the ctiy of Watertown required said contractor to give a bond which was furnished by the National -Surety Company, defendant and appellant, and contained the following recitals and conditions:

“That we, Offerman Construction Company, a corporation of Omaha, Neb., principal, and National Surety Company of New York, as surety, are held and firmly bound unto the city of Watertown, South Dakota, a municipal corporation in the sum of $ro,ooo * * * for the payment of which well and truly to be made we hereby bind ourselves, etc. The condition of the foregoing obligation is such that, if the a'bove-bounden Offerman Construction Company * * * shall assume the defense of and indemnify and save harmless the city of Watertown * * * from all claims relating to- labor and materials furnished under such contract, * * * and shall also pay for all labor performed and materials used or furnished in the carrying out of said contract: Then-this obligation to be null and void; otherwise to remain in full force and effect and virtue.”

That said bond was accepted by said city, and in reliance thereon plaintiff furnished to the Offerman Construction Company materials (described) to the aggregate sum and value of $1,846.28, which materials were used by said company in the construction of said sewers pursuant to its contract. That the Offerman Construction Company became and was adjudged bankrupt on April 2, 1918, and never paid plaintiff for said material. That on July 8, 1918, plaintiff demanded of defendant surety company payment of the sum due for said materials so used, but that defendant refused and still refuses to pay the same or any part thereof, and denies its liability on said bond ■upon the ground that it is “not liable to labor and materials claimants.”

Two other causes of action similar in every respect are set forth in plaintiff’s complaint. Demurrer to the complaint on the ground that it does not state facts sufficient to constitute a cause of action. Demurrer overruled, and defendant appeals.

[115]*115[1] Appellant contends: First, that the city of Watertown was without power to enter into a contract for the use and benefit of third persons, viz., laborers and materialmen; second, that the contract of indemnity in this case was for the sole use- and benefit of the city; that laborers and materialmen are not, and were not intended to become, parties thereto, and cannot maintain this action.

In response to the first contention, it is sufficient to observe that, if the contract was clearly intended to be for the use and benefit of laborers and materialmen as well as the city itself- — in other words, if the defendant guaranty company contracted and agreed to become liable for and to pay for labor and material entering into the sewer in case the contractor failed to pay therefor ■ — no question of ultra vires arises.

[2] The contractor had the right, for its- own benefit, to enter- into a contract with the defendant guaranty company; whereby the guaranty company might obligate'itself to pay laborers and) materialmen, if it should fail to pay, even in the absence of any bond for the protection of the city, and clearly laborers or materialmen for whose benefit such bond might be given, even though, not named therein, could accept the contract thus tendered by the guaranty company, and become parties thereto with a right of action thereon in case the contractor defaulted in his payments. The rights acquired by laborers and materialmen under such a contract would not foe affected by the fact that the same contract also indemnified the city against claim-s of laborers and materialmen. The question then would seem to be, not whether the city might enter into a contract for the benefit of third persons, to wit, laborers and materialmen, but whether the contractor and the guaranty company -have entered into-a contract for their protection. The consideration for the bond was paid, not by the city of Watertown, but by the contractor. Such payment would constitute a sufficient' consideration, even though 'third persons for whose benefit such- bond may have been given were not named as parties thereto, nor even cognizant of its existence, and such persons by adopting the promise made for- their benefit could bring themselves into privity with the promisor and enforce the promise as though made directly to them. Thorp. v. Keokuk Coal Co., 48 N. Y. 257; Clark v. Howard, 150 N. Y. 238, 44 N. E. 695.

[116]*116[3,4] Whether the provisions of the bond in this case entitle laborers and materialmen to accept and become privies thereto presents a question of much greater difficulty. The complaint alleges that plaintiff accepted and relied upon the bond. It is appellant’s contention, however, that the bond, on its face and by all its provisions, discloses that it was given solely for the protection of the city, and not for the benefit of laborers and material-men; that a surety cannot be held beyond the express terms of his contract.

In Fish & H. v. N. E. H. Co., 27 S. D. 221, 130 N. W. 841, this court held that persons for whose benefit a contract of this kind is made need not be named therein. In Fry v. Ausman, 29 S. D. 30; 135 N. W. 708, 39 L. R. A. (N S.) 150, Ann. Cas. 1914C, 842, it was held that—

“Recovery can only be had in case the contract was ‘made expressly for the benefit of a third person.’ ”

In Chung Kee v. Davidson, 73 Cal. 522, 15 Pac. 100, the court held that—

“It must appear, however, by the direct. terms of the contract, that it was made for the benefit of such parties. It cannot be implied from the fact that the contract would, if carried out between the parties to it, operate incidentally to their benefit.’

The general rule is that — ■

“Where contracts are evidently part of the same transaction, a person who beomes a party to one of such contracts which provides for the other is bound by the terms of both.” 13 C. J. 713, § 821.

That is, the guarantor of a contract binds himself to a performance of the same acts which the principal himself has undertaken to perform. Therefore where a contractor, by the terms of his contract, has expressly agreed to pay all claims for labor and material, the guarantor binds himself to pay for such labor and material equally with the contractor, and laborers and materialmen may adopt such guaranty and enforce it the same as though made directly to them. Jordan v. Kavanaugh, 63 Iowa, 152, 18 N. W. 831. The general rule undoubtedly is that to sustain an action there must be privity of contract between the parties, though in many jurisdictions it is held, even in the absence of statutory provision, that, if one person makes a promise to another upon a [117]*117consideration for the benefit of a third party, the latter may maintain an action upon it, though the consideration did not move from him. The conflict of decisions, however, appears irreconcilable upon principle.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc.
2002 SD 136 (South Dakota Supreme Court, 2002)
Harms v. Northland Ford Dealers
1999 SD 143 (South Dakota Supreme Court, 1999)
State Ex Rel. Farmers State Bank v. Kuipers Const. Co.
190 N.W.2d 769 (South Dakota Supreme Court, 1971)
Foster v. Kerr & Houston, Inc.
179 A. 297 (Supreme Judicial Court of Maine, 1935)
Thompson Yards, Inc. v. Van Nice
239 N.W. 753 (South Dakota Supreme Court, 1931)
Gary Hay Grain Co., Inc. v. Carlson
255 P. 722 (Montana Supreme Court, 1927)
J. F. Anderson Lumber Co. v. National Surety Co.
207 N.W. 53 (South Dakota Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
173 N.W. 448, 42 S.D. 109, 1919 S.D. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evans-howard-fire-brick-co-v-national-surety-co-sd-1919.