Evan Johnson & Sons Construction, Inc. v. State of Mississippi

CourtMississippi Supreme Court
DecidedAugust 27, 2001
Docket2001-CA-01675-SCT
StatusPublished

This text of Evan Johnson & Sons Construction, Inc. v. State of Mississippi (Evan Johnson & Sons Construction, Inc. v. State of Mississippi) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evan Johnson & Sons Construction, Inc. v. State of Mississippi, (Mich. 2001).

Opinion

IN THE SUPREME COURT OF MISSISSIPPI

NO. 2001-CA-01675-SCT

EVAN JOHNSON & SONS CONSTRUCTION, INC.

v.

THE STATE OF MISSISSIPPI AND TOMPKINS, BARRON & FIELDS ARCHITECTS, A PARTNERSHIP

DATE OF JUDGMENT: 08/27/2001 TRIAL JUDGE: HON. W. SWAN YERGER COURT FROM WHICH APPEALED: HINDS COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: RICHARD M. DYE PHIL B. ABERNETHY ATTORNEYS FOR APPELLEES: OFFICE OF THE ATTORNEY GENERAL BY: T. HUNT COLE, JR. EDWARD OMER PEARSON PETER LARKIN DORAN T. CALVIN WELLS BARRY CLAYTON CAMPBELL NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 03/04/2004 MOTION FOR REHEARING FILED: MANDATE ISSUED:

EN BANC.

CARLSON, JUSTICE, FOR THE COURT:

¶1. The State of Mississippi Military Department (State) and Tompkins, Barron & Fields Architects

(Tompkins) were granted summary judgment dismissing with prejudice all claims asserted against them by

Evan Johnson & Sons Construction, Inc. (Johnson) under a construction contract. The State was also

thereafter granted summary judgment as to its counterclaim for liquidated damages against Johnson and its

surety in the amount of $119,150.34, and a final judgment consistent with the opinion and order was likewise entered the same day for this amount with post-judgment interest at the rate of 8% per annum.

Johnson appeals the ruling of the circuit court citing numerous errors. Finding that the motions for summary

judgment dismissing Johnson’s claims were properly granted in favor of the State and Tompkins and that

the State’s motion for summary judgment as to its counterclaim for liquidated damages against Johnson was

likewise properly granted, this Court affirms the final judgment entered consistent with these opinions by

the Circuit Court of the First Judicial District of Hinds County.

FACTS AND PROCEEDINGS IN THE TRIAL COURT

¶2. On May 16, 1995, Johnson was awarded a contract to build the STARC Armory facility which

was owned by the State through the Mississippi National Guard. Tompkins was selected as the architect.

Independent Roofing, Inc. (Independent Roofing) was Johnson's roofing subcontractor. A portion of the

project required Johnson to construct a curved barrel vault roof. Prior to the bids being submitted,

prospective bidders raised several questions concerning how this roof was to be constructed. In response

to these questions, Tompkins prepared Addendum No. 1 which consisted of seven drawings clarifying the

design of the curved portion of the barrel vault roof.

¶3. Johnson completed all portions of the project except the construction of the curved portion of the

roof, which was to be performed by Independent Roofing. As construction of the curved portion of the

roof was begun, Independent Roofing informed Johnson that the construction as specified in the plans and

in Addendum No. 1 would not achieve the results sought by the State. Johnson notified the State of

Independent Roofing's discovery; however, the State and Tompkins instructed Independent Roofing to

install the roof as specified in the design. Notwithstanding this clear directive from the State and Tompkins

to construct the roof in compliance with the original plans and Addendum No. 1, Johnson attempted to

2 place the roof over a structure of corrugated "S" deck which did not incorporate the use of bent or rolled

"Z" purlins. As Independent Roofing was constructing the last layer of the roof, the State rejected the

project stating it did not produce the appearance the State desired.

¶4. After work was ceased, two cure notices were sent to Johnson directing the company to proceed

with the project. After an eleven-month impasse, Johnson finally presented this dispute for hearing before

a Contract Dispute Review committee on April 30, 1997. The committee found that Johnson had deviated

fromthe design and specifications without written authorization. The review committee also recommended

that Johnson replace the existing roof with one constructed in accordance with the design and

specifications. On May 6, 1997, after a review of the committee's recommendations the Adjutant General

directed Johnson to complete the roof.

¶5. As of the scheduled completion date of May 8, 1997, the roof had not been completed by

Johnson, and the contract was then terminated by the State. The contract was later rebid, and the roof was

eventually completed on October 6, 1998, by Mandal's of Gulfport. However, it was not built according

to the original design and specifications due to the fact that in order to save time, the State and Tompkins

modified the design substituting bent pipe for the "Z" purlins.

¶6. On November 21, 1997, Johnson filed a complaint against the State and Tompkins in the Circuit

Court of the First Judicial District of Hinds County. This five-count complaint charged (1) breach of

contract by the State due to the State’s alleged failure to submit plans and specifications which would

produce the desired result; (2) breach of implied warranty by the State; (3) negligence by Tompkins; (4)

wrongful termination and breach of contract by the State; and, (5) breach of contract by the State due to

the State’s alleged failure to make timely payments under the contract. The State filed a counterclaim

3 against Johnson for liquidated damages and costs paid to complete the project. On December 15, 1999,

Tompkins, joined by the State, filed a motion for summary judgment to dismiss Johnson's action with

prejudice. A hearing was held on May 15, 2000, and the circuit judge took the motion under advisement

for subsequent ruling. On September 18, 2000, the circuit judge entered his 14-page Memorandum

Opinion and Order on Motions for Summary Judgment in which he found, inter alia, that Johnson had no

good justification for non-performance, and thus, summary judgment was granted against Johnson and in

favor of the State and Tompkins. In this same opinion and order, the circuit judge dismissed with prejudice

all claims asserted by Johnson against the State and Tompkins, and also kept viable the State’s

counterclaim for liquidated damages against Johnson.

¶7. On May 14, 2001, the State filed a motion for summary judgment on its counterclaim for liquidated

damages. After a hearing held on July 16, 2001, the trial court took the motion under advisement and on

August 27, 2001, entered its 7-page Opinion and Order on State’s Claim for Liquidated Damages. In its

opinion and order, the trial court granted the State’s motion for summary judgment and found that a

judgment for the State and against Johnson and its surety in the amount of $119,150.34 should be entered.

On the same day, the trial court entered its final judgment consistent with the opinion.

¶8. On September 13, 2001, Johnson attempted to supplement the record with numerous affidavits

and deposition transcripts.1 What amounted to Johnson’s second attempt to supplement the record (see

1 Of significant import is the fact that likewise, four days prior to the summary judgment hearing of July 16, 2001, Johnson filed a notice of filing with attached affidavits and depositions (consuming 191 pages of the record) in an effort to defeat the State’s motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Natus Corporation v. The United States
371 F.2d 450 (Court of Claims, 1967)
Brown v. Credit Center, Inc.
444 So. 2d 358 (Mississippi Supreme Court, 1983)
Shaw v. Burchfield
481 So. 2d 247 (Mississippi Supreme Court, 1985)
Smith v. Sanders
485 So. 2d 1051 (Mississippi Supreme Court, 1986)
Mississippi Transp. Com'n v. SCI, INC.
717 So. 2d 332 (Mississippi Supreme Court, 1998)
Pearl River Cty. Bd. v. South East Collections
459 So. 2d 783 (Mississippi Supreme Court, 1984)
Smith v. HC Bailey Companies
477 So. 2d 224 (Mississippi Supreme Court, 1985)
Grisham v. JOHN Q. LONG VFW POST, NO. 4057, INC.
519 So. 2d 413 (Mississippi Supreme Court, 1988)
Short v. Columbus Rubber and Gasket Co.
535 So. 2d 61 (Mississippi Supreme Court, 1988)
Bourn v. Tomlinson Interest, Inc.
456 So. 2d 747 (Mississippi Supreme Court, 1984)
Jones v. James Reeves Contractors, Inc.
701 So. 2d 774 (Mississippi Supreme Court, 1997)
Richardson v. APAC-Mississippi, Inc.
631 So. 2d 143 (Mississippi Supreme Court, 1994)
Galloway v. Travelers Ins. Co.
515 So. 2d 678 (Mississippi Supreme Court, 1987)
Oak Adec, Inc. v. United States
37 Cont. Cas. Fed. 76,220 (Court of Claims, 1991)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
Jennie-O Foods, Inc. v. United States
580 F.2d 400 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Evan Johnson & Sons Construction, Inc. v. State of Mississippi, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evan-johnson-sons-construction-inc-v-state-of-miss-miss-2001.