Essick v. Bauman Iron Works

25 Pa. D. & C. 597, 1936 Pa. Dist. & Cnty. Dec. LEXIS 44
CourtPennsylvania Court of Common Pleas, Berks County
DecidedMarch 9, 1936
Docketno. 1755
StatusPublished

This text of 25 Pa. D. & C. 597 (Essick v. Bauman Iron Works) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Berks County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essick v. Bauman Iron Works, 25 Pa. D. & C. 597, 1936 Pa. Dist. & Cnty. Dec. LEXIS 44 (Pa. Super. Ct. 1936).

Opinion

Shanaman, J.,

The receiver of the Bauman Iron Works filed his first and partial account, which was referred to Abraham H. Rothermel, Esq., for audit. Some of the creditors of the Bauman Iron Works have filed exceptions to the auditor’s findings and awards in their respective claims, and these, after argument, are before us for determination.

Coco Metalcraft Corporation excepts to the auditor’s disallowance of a claim of $245.56. This claim is for an unpaid balance on an account, arising out of a contract between the Bauman Iron Works and the exceptant. Under the contract claimant, as subcontractor, constructed bronze handrails for the balustrades on the stairways of the Pratt Library in Baltimore, Maryland. The contract price was $945.56, of which $700 was paid. When the balustrades were erected it was found that a number of the bronze rails did not fit over the iron rails, or templets, which they were to cover. The Bauman Iron [599]*599Works had to reheat the bronze rails and bend them to proper shape before the Pratt Library would accept the work. There was evidence that this reworking upon the bronze rails was performed by the Bauman Iron Works at a cost of $661.90, and there was testimony, pro et contra, in an effort to place the blame for the faulty construction. The auditor found that the faulty construction of the bronze rails was the fault of the claimant, and disallowed its claim. We have carefully read and reread the testimony, and are not satisfied that by the fair weight of the credible evidence claimant performed its contract properly and without fault. Since the burden is on claimant to establish its claim we must disallow it, dismiss its exception to the auditor’s dis-allowance, and sustain the said finding of the auditor.

The auditor also found that the Bauman Iron Works has overpaid the claimant in the amount of $416.34 and is entitled to reimbursement for the correction of the bronze rails. Exception is taken to this finding. Since the auditor was not appointed or empowered to try and adjudicate any right that the receiver may possess to recover damages or money paid in excess from the claimant, the auditor’s finding that the Bauman Iron Works is entitled to be reimbursed for the correction of the bronze rails is overruled and vacated and the exception to that finding is sustained.

The remaining exceptions concern the claim of the Penn National Bank & Trust Company for $65,296.09. This claim is made up of principal and interest on a number of promissory notes of varying amounts. The bank held certain securities for the payment of the notes. The question at issue is whether the bank may claim for the whole amount of the debt and recover a dividend thereon, equally with unsecured creditors upon their respective claims, or whether the securities held by the bank must be deducted from the total amount of its claim and the dividend awarded only upon the unsecured remainder. The auditor has upheld the latter con[600]*600terition, and, after deducting the amount of the securities, finds that the unsecured remainder is $9,987.59, and has awarded a dividend thereon. To this finding the bank has excepted.

As security for the payment of one of the notes, which is the direct note of the Bauman Iron Works for $35,000, dated January 30, 1933, the bank holds a mortgage on the plant of the Bauman Iron Works which was originally executed in the sum of $50,000 and was reduced before the appointment of the receiver to $35,000. The bank has not delivered this mortgage to the receiver. The auditor has valued it at $35,000 and no exception has been taken to that valuation, the parties having agreed upon $35,000 as the fair value of the mortgage with its accompanying bond.

The bank also held as collateral security for the payment of certain others of the notes, namely, one for $9,034, one for $7,000, and one for $9,250, several life insurance policies on the life of Robert L. Kift, aggregating $70,000, under a life insurance trust agreement dated July 28, 1932. Robert L. Kift died on June 25, 1933, and the bank, as trustee under said trust agreement, collected the net sum of $69,573.25. Under the terms of the trust agreement the bank was authorized to reimburse itself for a note held by it against Robert L. Kift in the sum of $47,000, plus interest thereon amounting to $1,856.50, and for insurance premiums paid by the bank on the life insurance policies, amounting to $408.25. The balance under the trust agreement, namely $20,308.50, was to be applied by the bank to the payment of the three notes in the sums respectively mentioned above of $9,034, $7,000, and $9,250, in the order named. This balance, agreed upon by the bank and the receiver after the payment of the personal note of Robert L. Kift and other charges, was $20,308.50. Under the terms of the trust agreement it became the duty of the bank to apply this sum as follows: namely, to the payment in full of the note for $9,034 and of the note [601]*601for $7,000, and to the payment of a remainder of $4,274.01 on account of the note for $9,250. Thus there was a balance due and unpaid on the note for $9,250, which was found by the auditor to amount to $4,975.99. Certain other notes on which the Bauman Iron Works is liable, held by the bank, total $5,000.60, making a total indebtedness not secured by any collateral, including $11 protest fees, of $9,987.59.

The auditor held the proceeds of the insurance policies to be an existing collateral security for the debt, a view which did not affect his decision. The point is, however, of importance, in the event that the auditor’s enforcement of the so-called “bankruptcy rule” should ultimately be determined to have been erroneous. We have therefore carefully considered the nature of the proceeds of the policies and are of opinion that, whatever rule may be ultimately applied to the distribution, the bank’s claim must first be diminished by the net proceeds applicable thereto, to wit, by the amount of $20,308.50, for the reason that the bank’s claim must be considered to have been liquidated, paid and settled in said amount and that the bank cannot be considered as having held or as now holding the proceeds as collateral security for the full amount of the notes even though it did hold the policies themselves as such security.

When the receiver was appointed on March 3, 1933, the bank held the policies as collateral security for the payment of the notes. Kift, the insured, died on June 25, 1933. Under the so-called “equity rule”, the bank could apply the proceeds to the debt and still claim upon the whole amount of it, unless the contract under which it held the policies and received their proceeds created an equity adverse to such right; “that right rested not on general laws disposing of the property of insolvent debtors, dead or alive, but on the contract of the parties”: Fulton’s Estate, 65 Pa. Superior Ct. 437, 442.

[602]*602The contract between the parties in the present case was the trust agreement, by the terms of which the bank, in addition to holding the policies as collateral security, undertook as follows:

“. . . and upon receipt of the proceeds of said policies the Trustee shall pay therefrom to Penn National Bank and Trust Company of Reading, Pennsylvania, the sums of money to it owing at the time of grantor’s demise as principal and interest upon the several promissory notes mentioned in the Schedule hereto annexed and marked Exhibit ‘A’ . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merrill v. National Bank of Jacksonville
173 U.S. 131 (Supreme Court, 1899)
Brock's Assigned Estate (No. 2)
166 A. 782 (Supreme Court of Pennsylvania, 1933)
Chambersburg Trust Co. v. Alexander
156 A. 615 (Superior Court of Pennsylvania, 1931)
United Security Trust Company's Case
177 A. 588 (Superior Court of Pennsylvania, 1934)
Morris v. Olwine
22 Pa. 441 (Supreme Court of Pennsylvania, 1854)
Miller's Appeal
35 Pa. 481 (Supreme Court of Pennsylvania, 1860)
Yeager v. Wallace
44 Pa. 294 (Supreme Court of Pennsylvania, 1863)
Patten's Appeal
45 Pa. 151 (Supreme Court of Pennsylvania, 1863)
Brough's Estate
71 Pa. 460 (Supreme Court of Pennsylvania, 1872)
Graeff's Appeal
79 Pa. 146 (Supreme Court of Pennsylvania, 1875)
Miller's Estate
82 Pa. 113 (Supreme Court of Pennsylvania, 1876)
United States Brick Co. v. Middletown Shale Brick Co.
77 A. 395 (Supreme Court of Pennsylvania, 1910)
Commonwealth v. Overholt
23 Pa. Super. 199 (Superior Court of Pennsylvania, 1903)
Fulton's Estate
65 Pa. Super. 437 (Superior Court of Pennsylvania, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
25 Pa. D. & C. 597, 1936 Pa. Dist. & Cnty. Dec. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essick-v-bauman-iron-works-pactcomplberks-1936.