Essex v. Murray

68 S.W. 736, 29 Tex. Civ. App. 368, 1902 Tex. App. LEXIS 316
CourtCourt of Appeals of Texas
DecidedMay 10, 1902
StatusPublished
Cited by2 cases

This text of 68 S.W. 736 (Essex v. Murray) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex v. Murray, 68 S.W. 736, 29 Tex. Civ. App. 368, 1902 Tex. App. LEXIS 316 (Tex. Ct. App. 1902).

Opinion

CONNER, Associate Justice.

This suit was instituted in the County Court of Tarrant County by appellee to recover from appellants certain collateral securities or their value, consisting of a promissory note for $650 made by S. P. Gibson, and a certified check for $100. From the judgment in appellee’s favor this appeal has been duly prosecuted.

The issues and facts necessary to an understanding of our conclusions may be thus briefly stated: On July 15, 1899, one Angus McLeod contracted with the Missouri Avenue M. E. Church South in the city of Fort Worth to erect, in accordance with certain plans and specifications, a church building for the contract price of $9179. One Howard Messer was employed as the architect under whose “directions” (acting as agent of said owner) and to whose “satisfaction” said building was to be completed. Among other things, the contract provided:

“Sec. 3. Should any alterations be required in the work shown or described by the drawing and specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architect, and the sum herein agreed to be paid for the work according to the original specifications shall be increased or diminished as the case.may be. In case such valuation is not agreed to, the contractor shall proceed with the alteration upon the written order of the architect, and the valuation of the work added or omitted shall be referred to three arbitrators (no one of whom shall have been personally connected with the work to *370 which these presents refer), to be appointed as follows: one by each of the parties to this contract, and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of . the parties hereto shall pay one-half of the expense of such reference.

“Sec. 9. The contractor shall make no claim for additional work unless the same shall be done in pursuance of an order from the architect, and notice of all claims shall be made to the architect in writing within ten days of the beginning of such work.”

The contract also provided that at stated periods the architect should make estimates of the value of the work and material and pay to the contractor 90 per cent thereof, the balance, not to exceed the contract price, to be paid upon the completion and acceptance of the building; and it was further provided that should the contractor abandon the contract and building the church should have the right to complete the work, “at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor, but if such expense shall exceed such unpaid balance the contractor shall pay the difference to the owner.”

To secure the contract so made McLeod gave bond with appellee as surety, the latter as further security also depositing with appellants, members of the church building committee, the collateral for the recovery of which this suit was instituted; it being stipulated by separate written contract then made by appellee, that in case of default on the part of McLeod the trustee therein designated should proceed to collect said collaterals and apply the proceeds “to the payment of whatever damages said church may suffer by reason of the failure of said McLeod to perform his covenants.” McLeod in fact defaulted. For labor and material furnished by McLeod the church paid on certified estimates of the architect $8168, and in the further construction and completion of the building the further sum of $1711.70; thus paying in all $697.75 in excess of the contract price. Hence arises the contention of appellants, fully set out in their answer, that they have the right in behalf of said church to retain and apply, so far as necessary, the collaterals sued for in accordance with appellee’s said contract.

In answer to this appellee asserts: (1) That the church from time to time paid McLeod more than 90 per cent of the value of the labor and material furnished by him, and that therefore appellee as surety for McLeod was discharged; and (2) that certain changes in the turrets from the original plans and specifications were made, and certain specified extra labor and material was furnished by McLeod in the erection thereof for which under his contract he was entitled to compensation, the aggregate value of such extras being alleged to be in a sum more than said amount overpaid by the church.

By demurrer to the petition, and by objection to charges given and refused, appellants first insist, in substance, that appellee failed to show-right for an allowance of the value of the extras submitted in the charge *371 of the court because of a failure to allege and prove compliance with the terms of the contract relating thereto, in that it was not alleged or proven that notice to the church had been given of the change in turrets and of the increased cost of construction, and that it was not shown that the price for such extras had been agreed upon or submitted to arbitration.

Changes and extras other than said turrets were alleged and shown, but under the evidence it seems that the issues relating to the turrets aloné were submitted to the jury, and we confine ourselves alone to such issues, and in our disposition have also confined ourselves to the second and third propositions under the assignments presenting this phase of the case, the first proposition being too general for consideration. Thus limited, we overrule the first, second, and fourth assignments of error. It will be apparent from a careful consideration of section 3 of the original contract that the written order of the architect for an alteration in the original plans and a reference to arbitrators to fix the value of extra cost thereby occasioned was required only in event of a failure of the contractor and architect to agree upon the value. In such event alone also does the contract provide (inferentially) for notice to the owner of the change or of extra cost. The contract constitutes the architect the agent of the owner. To him seems to be committed the discretion of determining when and what alterations shall be made, and if required by him, it is made the duty of the contractor to conform to the alteration; for which a “reasonable valuation of the work added or omitted shall be made by the architect,” and the contract price “increased or diminished as the ease may be.” There was evidence to the effect that McLeod made the change in the turrets from galvanized iron to stone for Ins own benefit, and that he made no charge or claim for the extra value of the stone turrets. The architect also denied having ordered the change, but appellee testified: “Mr. Messer was there.. He said that the stone would be better and he told us to put in the stone. That he did not remember whether there was any agreement as to price or not. That the architect said that he would allow them to make the extra cost.” There is no controversy in the evidence as to the reasonableness or amount of the extra cost involved, and we think the evidence authorized the submission of the issues of whether the architect ordered the change, and if so whether the price or value of the extra labor involved was substantially agreed to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Employers' Ins. Co. v. Huddleston
39 S.W.2d 952 (Court of Appeals of Texas, 1931)
Cudlipp v. C. R. Cummings Export Co.
149 S.W. 444 (Court of Appeals of Texas, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
68 S.W. 736, 29 Tex. Civ. App. 368, 1902 Tex. App. LEXIS 316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-v-murray-texapp-1902.