Essential Housing v. Walker

CourtCourt of Appeals for the Fourth Circuit
DecidedJune 9, 1998
Docket97-2150
StatusUnpublished

This text of Essential Housing v. Walker (Essential Housing v. Walker) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essential Housing v. Walker, (4th Cir. 1998).

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

ESSENTIAL HOUSING MANAGEMENT, INCORPORATED, Plaintiff-Appellee, No. 97-2150 v.

THOMAS F. WALKER, Defendant-Appellant.

Appeal from the United States District Court for the Middle District of North Carolina, at Winston-Salem. N. Carlton Tilley, Jr., District Judge. (CA-95-375-6)

Argued: January 29, 1998

Decided: June 9, 1998

Before HAMILTON, WILLIAMS, and MICHAEL, Circuit Judges.

_________________________________________________________________

Affirmed in part, vacated in part, and remanded for further proceed- ings by unpublished per curiam opinion.

_________________________________________________________________

COUNSEL

ARGUED: James A. Merritt, Jr., BERRY, ADAMS, QUACKEN- BUCH & STUART, P.A., Columbia, South Carolina, for Appellant. B. Gordon Watkins, III, KILPATRICK STOCKTON, L.L.P., Winston-Salem, North Carolina, for Appellee. ON BRIEF: Daniel R. Taylor, Jr., KILPATRICK STOCKTON, L.L.P., Winston-Salem, North Carolina, for Appellee.

_________________________________________________________________ Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).

_________________________________________________________________

OPINION

PER CURIAM:

In this diversity action for recovery on a contract, defendant Thomas F. Walker appeals from the district court's grant of summary judgement for plaintiff Essential Housing Management, Inc. (EHM). Walker first argues that the district court was wrong to deny his motion to amend his answer because EHM did not show it was preju- diced by his delay in seeking to amend. Next, Walker argues that the court incorrectly granted summary judgment for EHM because it mis- interpreted the contract on which EHM sued. We reject Walker's first argument because he failed to show good cause for revising the court's scheduling order, which had set a deadline for amendments to pleadings. However, his second argument has merit because the dis- trict court's reading of the contract renders some of its language superfluous. Therefore, we affirm part of the district court's order granting summary judgment to EHM, but we vacate the order in part and remand the case for further proceedings consistent with this opin- ion.

I.

Walker was a general partner in several limited partnerships, each of which owned a low or moderate income housing project in South Carolina. Each partnership hired EHM to manage its project. Under the management agreement that each partnership and EHM entered into (all of the agreements were identical), EHM was obliged to col- lect rent from the project's residents and deposit it into the project's general operating account. The agreement also required that EHM pay all of the project's operating costs out of this account. One such cost was EHM's compensation, a monthly management fee calculated in accordance with the agreement. The agreement gave EHM the right to take its fees out of the operating account when they came due, without regard to any of the project's other obligations or expenses.

2 Further, EHM was not required to pay for project operating costs from its own funds.

EHM and the partnerships terminated their relationship in about June 1995. EHM, which is a North Carolina corporation, then brought suit in federal court against Walker, a resident of South Carolina, to recover debts that the partnerships allegedly owed to it. According to EHM, these debts totaled $56,466.02 in unpaid management fees and unreimbursed operating costs, plus interest. EHM claimed that Walker was liable for the full amount of these debts because he was a general partner in each partnership.

Walker filed his answer on May 22, 1996. In a scheduling order of July 18, 1996, the district court established August 15, 1996, as the last date to amend pleadings and January 15, 1997, as the discovery cutoff date. The order scheduled a trial for July 14, 1997.

On December 3, 1996, Walker moved to amend his answer to add a counterclaim. The proposed counterclaim arose out of the same transactions as EHM's claim and was therefore compulsory under Federal Rule of Civil Procedure 13(a). The thrust of the proposed counterclaim was that EHM was not entitled to the fees it sought because it had mismanaged the projects. Judge Osteen denied Walk- er's motion, noting that the motion came nearly four months after the scheduling order's deadline for pleading amendments and only six weeks before the end of discovery. The judge said that granting the motion would extend discovery and would not allow the case to remain on the July trial docket. However, the judge made no finding that granting the motion would prejudice EHM.

Walker made a motion for reconsideration that Judge Osteen also denied. This time the judge found that Walker "set forth no sufficient reason to indicate that the basis for the amendment was not known in sufficient time to comply with the original schedule." In fact, the judge noted that Walker's counsel had left the case unattended for a substantial period of time with no apparent excuse for doing so. Finally, the judge found that allowing Walker to assert a counterclaim at that late date would prejudice EHM because it"would not have suf- ficient discovery and preparation time."

3 At the pretrial conference Walker again moved for reconsideration of his motion to amend his answer to add a counterclaim. Judge Tilley denied this motion. The judge held that Walker had not complied with the deadline for amendments to pleadings set by the scheduling order and that he had shown "no justification" for his failure to do so. The judge reasoned that the court's overall schedule depended "on people doing what they should do in a timely fashion."

On July 14, 1997, the day trial was to begin, EHM moved for sum- mary judgment. It argued that the sole issue was the proper interpreta- tion of the management agreements' provision for compensation and indemnification to EHM. The crux of the parties' dispute, it said, was the extent to which this provision constituted a guarantee by the part- nerships that EHM would be repaid for costs it incurred in operating the housing projects. According to EHM, each management contract made the relevant partnership liable for all costs of operating the proj- ects, including EHM's monthly management fees. As a result, EHM argued, Walker was liable to EHM for all unreimbursed costs and all unpaid management fees.

Accompanying EHM's motion for summary judgement was an affidavit from EHM's chief operating officer. She attested to the exis- tence of the management agreements between EHM and the partner- ships, explained her understanding of how EHM's monthly management fees were calculated, and claimed that the management agreements' indemnification provision made the partnerships liable to EHM for all costs EHM incurred in operating the housing projects, including its management fees. Attached to this affidavit were busi- ness records that purported to show that Walker's partnerships owed EHM a total of $59,466.02 for uncollected management fees and unreimbursed out-of-pocket expenses.1 However, the EHM official _________________________________________________________________ 1 In her affidavit the EHM official segregated these costs into three cat- egories: (1) management fees owed to EHM, (2) "on-site employee costs," that is, the cost of a "site manager" at each housing project, and (3) other costs paid by EHM to third parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Marcoin, Inc. v. McDaniel
320 S.E.2d 892 (Court of Appeals of North Carolina, 1984)
Maddox v. Colonial Life & Accident Insurance
280 S.E.2d 907 (Supreme Court of North Carolina, 1981)
Goodman v. Resolution Trust Corp.
7 F.3d 1123 (Fourth Circuit, 1993)
Baker v. Whitley
361 S.E.2d 766 (Court of Appeals of North Carolina, 1987)
Johnson v. Oroweat Foods Co.
785 F.2d 503 (Fourth Circuit, 1986)
Forstmann v. Culp
114 F.R.D. 83 (M.D. North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Essential Housing v. Walker, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essential-housing-v-walker-ca4-1998.